TIDMRIO

RNS Number : 9222R

Rio Tinto PLC

03 July 2020

Oyu Tolgoi mine design confirms project schedule and cost ranges and update to Ore Reserves and Mineral Resources

3 July 2020

Oyu Tolgoi LLC has completed an updated feasibility study (OTFS20) and is in the process of submitting this to the Government of Mongolia. The OTFS20 has been prepared in accordance with Mongolian regulations and standards which require mining companies to submit updated feasibility studies every five years. The updated study incorporates a new mine design for Panel 0 of the Hugo Dummett North underground mine at Oyu Tolgoi. The new design also confirms that the caving method of mining remains valid and that the underground schedule and costs remain within the ranges previously disclosed.

These ranges include a delay of 21 to 29 months for first sustainable production compared to the original feasibility study guidance in 2016 and an increase of $1.3 billion to $1.8 billion from the original $5.3 billion development capital. Detailed study, design, engineering and optimisation work is ongoing to support the definitive estimate of Panel 0 for the development of this world-class orebody, which remains due in the second half of 2020. These estimates are subject to any additional scheduling delays or increases in capital costs arising from the impacts of the ongoing COVID-19 pandemic.

Arnaud Soirat, chief executive of Copper & Diamonds said "This amended mine design is another positive step in the development of the underground mine which will unlock the most valuable part of Oyu Tolgoi. We remain focused on delivering the underground project safely and within the guidance ranges we have announced on both cost and schedule."

The updated mine design is the result of the review announced by Rio Tinto in July 2019 when enhanced geotechnical and geological information obtained from drilling and mapping at depth suggested there may be some stability risks associated with the original mine design. The updated design retains two in-situ rock pillars on either side of Panel 0 for geotechnical stability. In the original mine design, these pillars were within the mining area. The updated design is supported by extensive geotechnical modelling and industry leading technical assurance.

As a consequence of leaving the pillars in place, the material contained in the pillars has been reclassified from Ore Reserves to Mineral Resources. It is expected that part of the material contained in these pillars will be recoverable at a later stage following additional studies which are currently underway.

Ore handling infrastructure will be relocated to the pillars, located immediately north and south of the current Panel 0 boundaries. Panels 1 and 2 will now be initiated as independent panels or mine blocks.

Optimisation of mine designs for Panels 1 and 2 is ongoing and it is anticipated that this next phase of study may result in further movements in classifications of Ore Reserves and Mineral Resources. Any such movements will be reported following completion of the studies.

On 3 July 2020 Rio Tinto released to the Australian Securities Exchange (ASX) updated Mineral Resources and Ore Reserves for the Oyu Tolgoi mine. Changes in the Hugo Dummett North Ore Reserves are shown below in Table A. Updates to Mineral Resources are shown in Table B. Ore Reserves and Mineral Resources are reported in accordance with the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves, 2012 (JORC Code) and the ASX Listing Rules.

Ore Reserves are presented in this release on a 100 per cent ownership basis. Rio Tinto's ownership share is 33.5% of Hugo Dummett North and 29.5% of Hugo Dummett North Extension. Mineral Resources are reported exclusive of Ore Reserves and on the same ownership basis.

Table A: Changes to the Hugo Dummett North and Hugo Dummett North Extension Ore Reserves estimates between 31 December 2019 and 01 July 2020.

 
                                           Hugo Dummett North 
                          Probable Ore Reserves          Average Mill Recovery       Recoverable Metal 
                    --------------------------------  --------------------------  ---------------------- 
                                                                                            Au      Ag 
                     Tonnes    Cu      Au       Ag       Cu        Au       Ag      Cu       (M      (M 
                      (Mt)     (%)    (g/t)    (g/t)     (%)       (%)      (%)     (Mt)    oz)     oz) 
                    -------  -----  -------  -------  --------  -------  -------  ------  ------  ------ 
 Reserves at 
  end 2019            447     1.64    0.34     3.35      93        79       81     6.81    3.84    39.02 
                    -------  -----  -------  -------  --------  -------  -------  ------  ------  ------ 
 Material removed     -47     2.75    0.68     5.36      94        82       86     -1.22   -0.85   -7.01 
                    -------  -----  -------  -------  --------  -------  -------  ------  ------  ------ 
 Reserves at 
  1 July 2020         400     1.51    0.29     3.11      93        79       80     5.60    2.99    32.00 
                    -------  -----  -------  -------  --------  -------  -------  ------  ------  ------ 
                                      Hugo Dummett North Extension 
-------------------------------------------------------------------------------------------------------- 
                          Probable Ore Reserves          Average Mill Recovery       Recoverable Metal 
                    --------------------------------  --------------------------  ---------------------- 
                                                                                            Au      Ag 
                     Tonnes    Cu      Au       Ag       Cu        Au       Ag      Cu       (M      (M 
                      (Mt)     (%)    (g/t)    (g/t)     (%)       (%)      (%)     (Mt)    oz)     oz) 
                    -------  -----  -------  -------  --------  -------  -------  ------  ------  ------ 
 Reserves at 
  end 2019             32     1.64    0.57     3.84      93        81       83     0.49    0.47    3.28 
                    -------  -----  -------  -------  --------  -------  -------  ------  ------  ------ 
 Material added       7.7     1.10    0.38     2.75      92        80       81     0.08    0.07    0.55 
                    -------  -----  -------  -------  --------  -------  -------  ------  ------  ------ 
 Reserves at 
  1 July 2020          40     1.54    0.53     3.63      92        81       83     0.57    0.55    3.84 
                    -------  -----  -------  -------  --------  -------  -------  ------  ------  ------ 
 

Table B: Changes to the Hugo Dummett North and Hugo Dummett North Extension Mineral Resource estimates between 31 December 2019 and 01 July 2020.

 
                                                               Hugo Dummett North 
                     Measured Mineral                Indicated Mineral                 Inferred Mineral                  Total Mineral 
                         Resources                        Resources                        Resources                        Resources 
             -------------------------------  -------------------------------  -------------------------------  ------------------------------- 
              Tonnes    Cu     Au       Ag     Tonnes    Cu     Au       Ag     Tonnes    Cu     Au       Ag     Tonnes    Cu     Au       Ag 
               (Mt)     (%)   (g/t)    (g/t)    (Mt)     (%)   (g/t)             (Mt)     (%)   (g/t)    (g/t)    (Mt)     (%)   (g/t)    (g/t) 
                                                                        (g/t) 
             -------  -----  ------  -------  -------  -----  ------  -------  -------  -----  ------  -------  -------  -----  ------  ------- 
 Resources 
  at end 
  2019          41     1.58   0.42     3.74     349     1.18   0.31     2.92     765     0.80   0.28     2.40     1155    0.94   0.29     2.61 
             -------  -----  ------  -------  -------  -----  ------  -------  -------  -----  ------  -------  -------  -----  ------  ------- 
 Material 
  added         17     2.54   0.64     5.34      52     2.39   0.54     4.63                                       69     2.43   0.57     4.81 
             -------  -----  ------  -------  -------  -----  ------  -------  -------  -----  ------  -------  -------  -----  ------  ------- 
 Resources 
  at 1 July 
  2020          58     1.86   0.48     4.21     401     1.34   0.34     3.14     765     0.80   0.28     2.40     1224    1.03   0.31     2.73 
             -------  -----  ------  -------  -------  -----  ------  -------  -------  -----  ------  -------  -------  -----  ------  ------- 
                                                          Hugo Dummett North Extension 
----------------------------------------------------------------------------------------------------------------------------------------------- 
                     Measured Mineral                Indicated Mineral                 Inferred Mineral                  Total Mineral 
                         Resources                        Resources                        Resources                        Resources 
             -------------------------------  -------------------------------  -------------------------------  ------------------------------- 
              Tonnes    Cu     Au       Ag     Tonnes    Cu     Au       Ag     Tonnes    Cu     Au       Ag     Tonnes    Cu     Au       Ag 
               (Mt)     (%)   (g/t)    (g/t)    (Mt)     (%)   (g/t)             (Mt)     (%)   (g/t)    (g/t)    (Mt)     (%)   (g/t)    (g/t) 
                                                                        (g/t) 
             -------  -----  ------  -------  -------  -----  ------  -------  -------  -----  ------  -------  -------  -----  ------  ------- 
 Resources 
  at end 
  2019                                           87     1.59   0.54     4.11     167     1.02   0.36     2.78     254     1.21   0.42     3.24 
             -------  -----  ------  -------  -------  -----  ------  -------  -------  -----  ------  -------  -------  -----  ------  ------- 
 No change 
             -------  -----  ------  -------  -------  -----  ------  -------  -------  -----  ------  -------  -------  -----  ------  ------- 
 Resources 
  at 1 July 
  2020                                           87     1.59   0.54     4.11     167     1.02   0.36     2.78     254     1.21   0.42     3.24 
             -------  -----  ------  -------  -------  -----  ------  -------  -------  -----  ------  -------  -------  -----  ------  ------- 
 

A copy of the full announcement to the ASX is available on Rio Tinto's website at riotinto.com/invest/financial-news-performance/resources-and-reserves .

Competent Persons Statement

The information in this release that relates to Ore Reserves is based on information compiled by Ferrin Prince and Mark Bixley, Competent Persons, who are a Member and Fellow respectively of The Australasian Institute of Mining and Metallurgy. Ferrin Prince and Mark Bixley are full-time employees of Rio Tinto. Ferrin Prince and Mark Bixley have sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as Competent Persons as defined in the 2012 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. Each of Ferrin Prince and Mark Bixley consents to the inclusion in the release of the matters based on the information that each of them has prepared in the form and context in which it appears.

The information in this release that relates to Mineral Resources is based on information compiled by Oyunjargal Dendev, a Competent Person who is a Member of The Australasian Institute of Mining and Metallurgy. Oyunjargal Dendev is a full-time employee of Oyu Tolgoi LLC. Oyunjargal Dendev has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as Competent Person as defined in the 2012 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. Oyunjargal Dendev consents to the inclusion in the release of the matters based on the information that he has prepared in the form and context in which it appears.

Contacts

media.enquiries@riotinto.com

riotinto.com

Follow @RioTinto on Twitter

 
 Media Relations, United Kingdom        Media Relations, Australia 
  Illtud Harri                           Jonathan Rose 
  M +44 7920 503 600                     T +61 3 9283 3088 
                                         M +61 447 028 913 
  David Outhwaite 
  T +44 20 7781 1623                     Matt Chambers 
  M +44 7787 597 493                     T +61 3 9283 3087 
                                         M +61 433 525 739 
  Media Relations, Americas 
  Matthew Klar                           Jesse Riseborough 
  T +1 514 608 4429                      T +61 8 6211 6013 
                                         M +61 436 653 412 
  Media Relations, Asia 
  Grant Donald 
  T +65 6679 9290 
  M +65 9722 6028 
=====================================  ================================ 
 
   Investor Relations, United Kingdom     Investor Relations, Australia 
   Menno Sanderse                         Natalie Worley 
   T: +44 20 7781 1517                    T +61 3 9283 3063 
   M: +44 7825 195 178                    M +61 409 210 462 
 
   David Ovington                         Amar Jambaa 
   T +44 20 7781 2051                     T +61 3 9283 3627 
   M +44 7920 010 978                     M +61 472 865 948 
=====================================  ================================ 
 
   Group Company Secretary                Joint Company Secretary 
   Steve Allen                            Tim Paine 
   Rio Tinto plc                          Rio Tinto Limited 
   6 St James's Square                    Level 7, 360 Collins Street 
   London SW1Y 4AD                        Melbourne 3000 
   United Kingdom                         Australia 
   T +44 20 7781 2000                     T +61 3 9283 3333 
   Registered in England                  Registered in Australia 
   No. 719885                             ABN 96 004 458 404 
                                       -------------------------------- 
 

This announcement is authorised for release to the market by Rio Tinto's Group Company Secretary.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

END

DRLEAAXAELAEEAA

(END) Dow Jones Newswires

July 03, 2020 02:00 ET (06:00 GMT)

Rio Tinto (LSE:RIO)
Gráfica de Acción Histórica
De Mar 2024 a Abr 2024 Haga Click aquí para más Gráficas Rio Tinto.
Rio Tinto (LSE:RIO)
Gráfica de Acción Histórica
De Abr 2023 a Abr 2024 Haga Click aquí para más Gráficas Rio Tinto.