TIDMWRES

RNS Number : 3918M

W Resources PLC

21 January 2021

21 January 2021

W Resources Plc

("W" or the "Company")

Q4 2020 Production Report

W Resources Plc (AIM:WRES), the tungsten, tin and gold mining company with assets in Spain and Portugal, is pleased to announce its Q4 2020 quarterly production report for the La Parrilla mine in Spain.

During the three month period ending 31 December 2020, the Company continued to make plant improvements resulting in major production increases across the board. These improvements continue apace and should be completed in early February 2021.

During the quarter, the plant continued to work a four day week, moving to a five day working week in early January 2021, with a target to move to a seven day working week with effect from April 2021.

Currently each working day consists of three, eight hour shifts and once the plant moves to a seven day working week, it will revert back to two 12 hour shifts.

The Company looks forward to once again operating the La Parrilla mine on a true 24 / 7 basis, which is widely accepted within the mining community as "best practice".

Key Metrics

-- A total of 261,841 tonnes ("t") of Run of Mine ("ROM") ore fed to the La Parrilla plant in Q4 2020, up 53% on a like for like basis and up 15% on a pro rata basis compared to Q3 (adjusting for days worked).

-- Total tungsten and tin concentrate production of 133.4t during the quarter, up 72% on a like for like basis and up 29% on a pro rata basis compared to Q3.

-- Tungsten ("WO(3) ") concentrate production of 100.0t during the quarter, up 83% on a like for like basis and up 37% on a pro rata basis compared to Q3.

-- Tin ("Sn") concentrate production of 33.4 dry metric tonnes ("dmt"), up 46% on a like for like basis and up 9% on a pro rata basis compared to Q3.

La Parrilla Production Summary

Q3 was based on working a three day week, and Q4 is based on a four day week.

 
                             Q3 2020   Q4 2020     Variance   Variance 
                              Actual    Actual   Comparison   Pro rata 
==========================  ========  ========  ===========  ========= 
 WO(3) contained metal 
  (mtu)                        3,820     6,698          75%        32% 
==========================  ========  ========  ===========  ========= 
 Sn contained metal (dmt)        9.8      18.8          92%        44% 
==========================  ========  ========  ===========  ========= 
 Total contained metal 
  (dmt)                         48.0      85.8          79%        34% 
==========================  ========  ========  ===========  ========= 
 

('dmt' - dry metric tonnes, 'mtu' - metric tonne unit (1 mtu = 10kg of metal)

Michael Masterman, Chairman of W Resources , commented: "We are extremely encouraged by the increase in production during the quarter as we draw near to completing our improvement plan. As we continue to access the lower ore bodies of the mine we expect to see production numbers continue to rise in the months ahead.

"We are delighted to see that there is plenty of demand for our production from existing and potential new customers with healthy demand for all the tungsten and tin we can mine. It is also very reassuring to note both tungsten and tin prices strengthening.

"A great deal of thanks must go to our staff for their flexibility, determination and drive as they work towards improving the mine and making it run as efficiently as possible particularly in this challenging environment."

Q4 2020 Overview

In Q4, the plant improvement programme included the following:

-- Jigs: replaced screen panels and quaternary mill rolls with materials more resistant to abrasion and modifications to jigging speed to improve recovery.

-- Spirals: replaced polyethylene pipes with others more resistant to abrasion, modifications made to reagent feed to float arsenopyrite on shaking tables, and preparations for the recommissioning of the rod mill.

-- FME (Flotation, Magnetic and Electrostatic): integrated system for wet reprocessing of off-spec concentrates, improvements to flotation density, installation of a new magnetic separator, modifications to some pumping points to produce a higher capacity.

Benefits of the plant improvements:

Greater plant availability with better recoveries and improving maintenance has led to:

   --    Increasing process stability 
   --    Greater run times 
   --    Less impurities going into final concentrate 
   --   Increased production 

La Parrilla Production Summary

 
                                Q3 2020   Q4 2020     Variance    Variance 
                                 Actual    Actual   Comparison   Pro rata* 
-----------------------------  --------  --------  -----------  ---------- 
 ROM feed: tonnes mined 
  (wmt)                         171,454   261,841          53%         15% 
 Strip ratio                       1.38      1.19         -14% 
 Jig plant: tonnes processed 
  (dmt)                         148,417   236,677          59%         20% 
 
 WO(3) feed grade (ppm)             857       943          10% 
 WO(3) recovery (%)                 30%       31%           3% 
 WO(3) concentrate (dmt)           54.7     100.0          83%         37% 
 WO(3) concentrate grade 
  (%)                              69.8      67.0          -4% 
 WO(3) contained metal 
  (mtu)                           3,820     6,698          75%         32% 
 
 Sn feed grade (ppm)                181       321          77%         33% 
 Sn recovery (%)                    37%       26%         -30% 
 Sn concentrate (dmt)              22.9      33.4          46%          9% 
 Sn concentrate grade 
  (%)                              42.7      56.3          32% 
 Sn contained metal (dmt)           9.8      18.8          92%         44% 
 
 Total concentrate (dmt)           77.6     133.4          72%         29% 
 Total contained metal 
  (dmt)                            48.0      85.8          79%         34% 
-----------------------------  --------  --------  -----------  ---------- 
 

* Q3 2020 production was based on working 3 days a week and Q4 production was based on working four days a week.

Recoveries for the quarter were impacted by the performance of the jigs which slowed the recovery rates for both October and November. Whilst this was disappointing, especially after such a strong September, the improvement programme identified the issues which were resolved alongside other key plant improvements and resulted in December being the best ever month for concentrator recovery at 50% and WO(3) concentrate at 41.5%.

-- Safety performance continues to be a top priority for the Company. There were zero minor lost time injuries at La Parrilla during the quarter, however, there was one Covid-19 infection during the period. The case was detected while the worker was off duty and they remained in quarantine at home and none of W's other employees contracted the infection from their colleague.

-- The Company has acquired quick Covid-19 antigen tests to improve detection and control of the disease with the aim of keeping all employees and contractors safe whilst in the La Parrilla work place.

-- Mining operations continue to perform well and deliver the required ore feed to the plant at a low waste / ore strip ratio (1.19 in the quarter), while maintaining the required grades to feed ore to the plant.

   --    Plant utilisation remains over 90% for the quarter. 

Shipments

W Resources shipped 100.2t of tungsten concentrate and 26.1t of tin concentrate in Q4 2020, taking total shipments to offtake partners to 251.3t of tungsten concentrate and 105.0t tin concentrate for the 12 months to December 2020.

 
                         H1 2020   Q3 2020   Q4 2020 
                          Actual    Actual    Actual   Variance 
----------------------  --------  --------  --------  --------- 
 Tungsten Concentrate       89.0      62.1     100.2        61% 
 Tin Concentrate            40.8      38.1      26.1       -31% 
----------------------  --------  --------  --------  --------- 
 

Whilst the tonnage of tin shipped in Q4 was lower than Q3 it was a very high grade (57% compared to 31%) and therefore commanded a much higher price than previous shipments. This higher grade concentrate is a result of better recovery and improved separation, a direct result of the work undertaken to improve flotation and magnetic separation, which allows less impurities going into the final concentrate.

Commodity pricing

European ammonium paratungstate ("APT") pricing remains strong at US$235-US$240 / mtu with industry comment from Fastmarkets MB that: " There's very little material available in Europe in 2021 and shipments from China are delayed. That is continuing to push APT offers up."

The Tin price continues to strengthen reaching a 12 month high of over US$21,500 per tonne in January 2021, from a low of US$13,375 in March 2020 (source: LME).

The Company looks forward to issuing its Q1 2021 Production Report in April of this year.

Information communicated within this announcement is deemed to constitute inside information as stipulated under the UK Market Abuse Regulations. Upon the publication of this announcement, this inside information is now considered to be in the public domain.

Enquiries:

 
 W Resources Plc                  Grant Thornton UK LLP 
  Paul Hailes                      Colin Aaronson / Seamus Fricker 
  investor@wresources.com          T: +44 (0) 20 7383 5100 
  www.wresources.com 
 Joint Broker                     Joint Broker 
  Turner Pope Investments (TPI)    Alternative Resource Capital / 
  Ltd                              Shard Capital 
  Andy Thacker / Zoe Alexander     Alex Wood 
  T: +44 (0) 203 657 0050          T:+44 (0) 207 186 9004 
  www.turnerpope.com               www.altrescap.com 
                                   Damon Heath 
                                   T:+44 (0) 207 186 9952 
                                   www.shardcapital.com 
 Alma PR 
  Justine James 
  M: +44 (0) 7525 324431 
  wres@almapr.co.uk 
 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.

END

MSCUARARAWUAURR

(END) Dow Jones Newswires

January 21, 2021 02:00 ET (07:00 GMT)

W Resources (LSE:WRES)
Gráfica de Acción Histórica
De Feb 2024 a Mar 2024 Haga Click aquí para más Gráficas W Resources.
W Resources (LSE:WRES)
Gráfica de Acción Histórica
De Mar 2023 a Mar 2024 Haga Click aquí para más Gráficas W Resources.