Hummingbird Resources plc / Ticker:
HUM / Index: AIM / Sector: Mining
9 August
2024
Hummingbird Resources
plc
("Hummingbird", "Group" or the
"Company")
Q2-2024 Operational and Trading Update and
TVR
Hummingbird (AIM: HUM) announces its
operational and trading update for the second quarter ending 30
June 2024 ("Q2-2024").
Operational update
Group
Production
· Q2-2024 Group
production totalled 19,855 ounces of gold ("oz") with a total of
42,722 oz produced in the first half of 2024
("H1-2024").
Yanfolila
Mine, Mali ("Yanfolila")
· Yanfolila
produced 12,065 oz of gold in Q2-2024 at an All-in Sustaining Cost
("AISC") of US$2,598 per oz. Performance was impacted by short-term
mining challenges, driven by poor availability and utilisation of
the mining fleet and the subsequent need to alter the mining
sequencing, increasing waste stripping, particularly at the
commencement of mining at the Gonka pit.
· The Company is
focused on improving ounce generation in Q3-2024 and has
implemented several short-term focused initiatives to maximise the
H2-2024 weighted production profile.
· During the
quarter, 12,457 oz of gold was sold at an average realised price of
US$2,075 per oz.
Kouroussa
Mine, Guinea ("Kouroussa")
· Kouroussa
production increased through Q2-2024 to 7,789 oz of gold, with
operations progressively ramping up towards commercial production.
During the quarter, 1,281,654 BCMs were mined at an average grade
of 2.64 grams per ton ("g/t") (Q1-2024: 1.88 g/t) as operations
mined higher-grade material at the Koekoe deposit.
· Post-period,
operational output has continued to improve with the mining
operation reaching c.30,000 BCMs per day and the commissioning of
the fresh rock plant increasing the blending of high-grade fresh
ore feed into the plant, which continues to operate at or above
design.
· Through July,
Kouroussa achieved average gold pours of c.1,200 oz per week, with
approximately 4,800 oz produced during the month. Based on current
progress, the Company expects to achieve commercial production in
late Q3-2024.
Corporate update
· The Group
reported a Lost Time Injury Frequency Rate ("LTIFR") of 0.99 per
million hours across 2.5 million hours worked in Q2-2024, ahead of
its target of 1.20 LTIFR.
· The Company
recorded a Group adjusted EBITDA loss of US$13.5 million in
Q2-2024, driven by reduced production from Yanfolila in the second
quarter.
· During the
quarter, the Company secured a short-term loan of US$10 million
from Nioko Resources, a wholly owned subsidiary of CIG SA, the
Company's largest shareholder.
· The Company is in
the advanced stages of finalising a refinancing package with Coris
Bank International to defer near term debt repayments on a portion
of the existing facility to H2-2025. Further information will be
provided in the coming days once finalised.
· In addition to
the refinancing package, the Company is progressing with several
non-equity financing options to further strengthen its balance
sheet as it reaches full operational capacity over the coming
quarters.
FY-2024 Outlook
With progress at Kouroussa and performance at
Yanfolila, the Company has updated its FY-2024 Group guidance to
115,000 - 145,000 oz at an AISC below US$1,500:
· Yanfolila:
Updated guidance to 65,000 - 75,000 oz at an AISC below US$1,600
per oz following a weaker H1-2024, focus on delivering on the
H2-2024 weighted mine plan and operational initiatives currently
being implemented.
· Kouroussa:
Reinstated guidance to 50,000 - 70,000 oz at an AISC below US$1,400
per oz, with refined guidance to be provided once operations reach
commercial production.
Investor Presentation
The Company's senior management team
will be holding an investor presentation today at 13:30
BST via the Investor Meet
Company platform.
The event will cover the release and
provide an opportunity for Q&A. The Company invites attendees
to pre-send questions to the Company
via IR@hummingbirdresources.co.uk
or via the Investor Meet
Company platform.
Webcast link: https://www.investormeetcompany.com/hummingbird-resources-plc/register-investor
Dan Betts, CEO of Hummingbird,
commented:
"Despite the significant challenges faced by the
Company this quarter, much of the difficulty has stemmed from
delays in ramping up operations at Kouroussa, compounded by nearly
two months of lost production. These setbacks have had a
considerable impact on both production and mine plans. However,
it's crucial to understand that these issues are now behind us. We
are currently working closely and effectively with Corica to
achieve commercial production later this quarter. Since Corica's
return in May, they have consistently improved fleet availability
and utilisation, enabling the mine to shift the necessary volume of
BCM to sustain operations. Consequently, we have begun accessing
the fresh rock ore body, which contains the high-grade, undepleted
gold essential for Kouroussa's ramp-up. The fresh rock crushing
circuit is fully commissioned, and as more fresh material is
processed; we are witnessing a steady increase in gold
production.
Yanfolila also experienced a challenging
quarter. However, our FY-2024 mine plan was always heavily weighted
toward the second half of the year, and that remains unchanged. In
view of the challenges faced at Yanfolila in the second quarter, we
are implementing strategic initiatives to optimise production and
expect to see significant improvements in the coming
months.
The delays have undoubtedly placed significant
pressure on our balance sheet and liquidity, and I am deeply
grateful for the continued support of our partners. We are in
advanced stages of finalising the refinancing of a portion of our
debt with Coris to provide us additional financial flexibility. We
have also explored several non-equity financing options to
strengthen the balance sheet without diluting shareholder value,
ensuring additional resilience if needed. With gold prices high and
production increasing at Kouroussa, Hummingbird is positioned to
rapidly deleverage the balance sheet in the coming quarters. Our
primary focus remains on delivering value to our shareholders
through enhanced production and operational efficiency."
Yanfolila, Mali: Q2-2024
operational summary
|
Unit
|
Q2-2023
|
Q3-2023
|
Q4-2023
|
Q1-2024
|
Q2-2024
|
Gold poured
|
oz
|
23,885
|
18,399
|
14,419
|
16,999
|
12,065
|
Mined BCMs
|
BCMs
|
592,360
|
1,775,723
|
1,878,181
|
1,549,607
|
1,536,256
|
Ore mined
|
t
|
262,911
|
171,959
|
266,361
|
169,195
|
167,657
|
Avg.
mined grade
|
g/t
|
2.72
|
3.09
|
2.39
|
2.47
|
2.08
|
Ore
processed
|
t
|
364,459
|
339,333
|
312,045
|
344,510
|
331,910
|
Avg. mill feed
grade
|
g/t
|
2.21
|
1.79
|
1.66
|
1.61
|
1.31
|
Recovery
|
%
|
94.06%
|
92.93%
|
91.05%
|
92.41%
|
92.66%
|
Group Gold
inventory
|
oz
|
1,831
|
1,834
|
2,908
|
1,652
|
74
|
Note: Ore mined includes high grade,
low grade, and marginal material. Ore processed is a blend based
on preferential feed of high grade and low grade, with
marginal ore added as an incremental feed source.
· In Q2-2024,
Yanfolila achieved a rolling 12-month LTIFR of 0.68, meeting its
safety target of below 1.20.
· Yanfolila
produced 12,065 ounces of gold in Q2-2024, marking a decrease from
Q1-2024. This reduction is primarily due to a shift in mine
sequencing as part of the long-term mine plan. During this period,
lower tonnages of higher-grade ore were mined, resulting in
increased reliance on lower-grade stockpile material to meet
processing throughput requirements. This temporary adjustment was
necessary to increase waste stripping and prepare access to
higher-grade ore zones in future quarters.
· Total BCMs
slightly decreased to 1,536,256 BCMs in Q2-2024 from 1,549,607 BCMs
in Q1-2024. The volume of ore mined also saw a slight reduction,
with 167,657 tonnes mined at an average grade of 2.08 g/t in
Q2-2024 compared to 169,195 tonnes at 2.47 g/t in Q1-2024. Despite
the grades being within expected ranges, ore volumes were notably
impacted by excavator efficiency at the Sanioumale East ("SE") pit
driven by availability and spatial constraints. Looking ahead to
H2-2024, the Company anticipates increased ore volumes as access
improves at SE and mining operations at Gonka, which commenced ore
extraction in August following waste stripping through the
quarter.
· In Q2-2024,
331,910 tonnes of ore were processed with an average mill feed
grade of 1.31 g/t. Plant recovery rates remained stable at 92.66%.
To maintain processing throughput, the ore mined in Q2-2024 was
blended with a higher proportion of low-grade and marginal waste
material, resulting in a reduced mill feed grade. As ore mining
volumes increase in H2-2024, the Company expects a significant
improvement in throughput grades and, consequently, ounce
production.
· The Company has
implemented several short-term initiatives to improve gold
production efficiency. Strategic initiatives to address and
mitigate operational challenges and maximise production
include:
o Mine Plan Optimisation:
Implemented mine design optimisation and scheduling
strategies to maximise ore extraction from the resource models,
targeting high-grade ore.
o Excavator Fleet
Enhancement: Utilising additional excavators
with further equipment from Bamako being evaluated.
o Mill Optimisation:
Reviewed and optimised mill set points following recent
refurbishment, targeting an operational throughput of over 180
tph.
· Through Q2-2024,
development of the Komana East Underground ("KEUG") Mine continued,
with 170 meters ('m') completed in Q2-2024, leading to a total of
780 m of development now completed.
Yanfolila
ESG:
· Through Q2-2024,
the Company continued its focus on investing within the local
communities.
o Ongoing Community
Investment: In Q2 2024, the Company maintained
its strong commitment to local community investment and
successfully conducted 370 stakeholder engagements and 24 group
meetings, reinforcing community relations.
o Significant Infrastructure
Developments: Made notable progress on key
community projects, including health centre construction, maternity
extensions, and road rehabilitation.
o Extensive Training and Health
Programmes: Executed comprehensive training
initiatives with 270 inductions and 172 first aid trainings, and
effectively carried out community health campaigns and medical
support.
Kouroussa, Guinea: Q2-2024
operational summary
|
Unit
|
Q1-2024
|
Q2-2024
|
Gold poured
|
oz
|
5,868
|
7,789
|
Mined BCMs
|
BCMs
|
1,119,449
|
1,281,654
|
Ore mined
|
t
|
125,972
|
213,926
|
Average Mined
Grade
|
g/t
|
1.88
|
2.64
|
Ore
processed
|
t
|
182,505
|
234,706
|
Avg. mill feed
grade
|
g/t
|
1.08
|
1.17
|
Recovery
|
%
|
91.96%
|
93.76%
|
Note: Ore mined includes high grade,
low grade, and marginal material. Ore processed is a blend based
on preferential feed of high grade and low grade, with
marginal ore added as an incremental feed source.
· Through Q2-2024,
Kouroussa maintained its strong safety record, achieving a rolling
12-month LTIFR of 0.00, meeting its safety target of below 1.20.
Unfortunately, post-quarter, a serious accident occurred at
Kouroussa, where one employee lost their life. The Company and
relevant authorities are conducting a thorough investigation into
the event, ensuring all necessary measures are taken to prevent
future incidents.
· Kouroussa
production increased to 7,789 oz of gold in Q2-2024. Production
ramped-up following the remobilisation of Corica's fleets and
improved operational performance.
· 1,281,654 BCMs
were mined at an average grade of 2.64 g/t in Q2-2024, up from 1.88
g/t in Q1-2024. The operations were impacted by the previously
announced delay in ramp-up operations through to mid-May when
Corica operations recommenced. With Corica's on-site mining
performance significantly improved in line to the new operational
plan as the operation progressed through the transitional ore into
the high-grade material.
· Throughout
Q2-2024, the processing plant continued to operate at its designed
capacity, processing 234,706 tonnes at a grade of 1.17 g/t with
recoveries of c.93.76% achieved. The lower grade processed vs mined
was due to the significant blending of low grade and marginalised
waste material to compensate for impact of the Corica suspension
and ramp-up of mining on ore volumes. The Company expects an
improvement in milled grade through Q3-2024.
· Since the restart
of operations, Corica have continually met expectations under the
agreed operational plan with movement reaching c.30,000 BCMs per
day. Post-period, despite the onset of the rainy season, mining
operations have continued to ramp up and output has continued to
improve. Through July, Kouroussa mined 683,066 BCMs at an average
grade of 2.70 g/t, resulting in the production of c.4,800 oz during
the month at an average of c.1,200 oz per week.
· Based on the
current rate of progress, the Company expects to achieve commercial
production in late Q3-2024.
Kouroussa
ESG:
· Through the
quarter, operations have continued to provide value to local
communities and enhancing overall well-being:
o Community and Environmental
Education: Launched radio communication
initiatives to educate local populations on environmental
protection. Conducted awareness sessions to highlight the value of
environmental conservation to the communities of
Kouroussa.
o Healthcare Support:
Successfully commissioned a borehole at the Kouroussa
hospital, ensuring a reliable water supply and delivered essential
medical equipment for emergency, maternity, and paediatric care in
collaboration with local authorities.
o Sanitation Improvement:
Continued the construction of twelve latrines at the
Kouroussa market in collaboration with local authorities. This
project aims to improve community health and support
income-generating activities for the municipality of
Kouroussa.
Dugbe, Liberia
· In Q2-2024
Pasofino Gold Limited ("Pasofino") completed its diamond core
drilling programme at the Bukon Jedeh 'gold camp' within the Dugbe
Gold Project, Liberia.
· Work is
progressing on optimising the 2022 Feasibility Study, focusing on
power usage and metallurgical recovery rates and is expected to be
completed later this year.
Q2-2024 Financial
update
|
Unit
|
Q2-2023
|
Q3-2023
|
Q4-2023
|
Q1-2024
|
Q2-2024
|
Yanfolila Gold Mine,
Mali
|
Gold sales
|
oz
|
24,770
|
18,550
|
12,952
|
18,230
|
12,457
|
Avg. gold sale
price
|
$/oz
|
$1,981
|
$1,918
|
$1,946
|
$2,030
|
$2,075
|
Operating cash
costs
|
$m
|
$30.0
|
$30.5
|
$19.5
|
$31.7
|
$31.2
|
AISC on gold
sold
|
$/oz
|
$1,234
|
$1,651
|
$1,508
|
$1,753
|
$2,598
|
Group Financial
Performance
|
Group Adjusted
EBITDA
|
$m
|
$15.5
|
$1.2
|
$2.7
|
$4.6
|
($13.5)
|
Net bank (debt) /
cash
|
$m
|
($122.8)
|
($123.0)
|
($140.4)
|
($138.8)
|
($153.5)
|
Net bank (debt) / cash
inc gold inventory value
|
$m
|
($119.3)
|
($119.5)
|
($134.4)
|
($135.1)
|
($150.1)
|
Note: The Company notes a number of
small non-material accounting adjustments have been made across the
previous two quarters which does not impact year to date
performance.
Financial
Overview:
· Q2-2024 AISC on
gold sold totalled $2,598 per oz, driven by the low ounce
production at Yanfolila. Kouroussa and Group AISC figures will be
provided once Kouroussa reaches commercial production.
· The Group
recorded an adjusted EBITDA loss for Q2-2024 of $13.5 million,
driven by low production.
· As of the end of
Q2-2024, the Company held a net bank debt position of approximately
$153.5 million (approximately $150.1 million including cash and
gold inventory value). For the period-end:
o Gross bank debt
of approximately $153.9 million.
o Cash at bank of
approximately $0.4 million.
o Gold inventory
value of approximately $3.4 million.
· The Company is in
the advanced stages of finalising a comprehensive refinancing
package with Coris Bank International. This arrangement is centred
around deferring near-term debt repayments on a portion of the
existing facility, extending the repayment period to the second
half of 2025. Further details will be provided in the coming days
once the agreement has been finalised.
· Additionally, the
Company is actively exploring and progressing with several
non-equity financing options. These initiatives are aimed at
further strengthening the Company's balance sheet and are designed
to provide the necessary capital to support the Company's
operational optimisation. The focus on non-equity financing
underscores the Company's commitment to minimising shareholder
value dilution.
Issuance of new
Ordinary Shares to WACOM Group:
· Further to the
Company's announcement on 16 December 2021, as part of the
incentive package worth up to US$2.6 million, Hummingbird is in the
process of issuing 6,342,857 new ordinary shares of 1 penny each in
the Company ("Ordinary Shares") to WACOM Group (the "Incentive
Shares"). This issuance is in recognition of WACOM's delivery of
the civil and structural design, fabrication, and construction of
the processing plant at the Kouroussa Gold Mine, which was
completed on schedule and within budget.
· The Incentive
Shares issued to WACOM are valued at US$1.85 million, based on an
agreed price of £0.22 per share. This incentive was aimed to align
WACOM's interests with those of Hummingbird, promoting the
successful completion of the Kouroussa Gold Mine and enhancing
shareholder value.
Nioko
Resources Share Subscription:
· In accordance
with pre-emption rights under its shareholder agreement, Nioko, a
wholly owned subsidiary of CIG SA, has subscribed for 4,567,874 new
Ordinary Shares in Hummingbird at a negotiated subscription price
of £0.085 per share for a total cash subscription of c.US$0.5
million (the "Subscription Shares"). Following the issuance of the
Subscription Shares, Nioko's shareholding will be 339,233,148
Ordinary Shares, which maintains its holding at 41.87% of the
Company's total voting rights following the issuance of the new
Ordinary Shares to WACOM Group and Nioko.
Admission and Total Voting Rights
Application has been made to the London Stock
Exchange for the admission of the 6,342,857 Incentive Shares and
4,567,874 Subscription Shares to trading on AIM ("Admission"),
which is expected to take effect on or around 13 August
2024.
The Incentive Shares and Subscription Shares
will be issued fully paid and will rank pari passu in all respects with the
Company's existing Ordinary Shares.
Following Admission, the Company's issued share
capital will consist of 810,285,389 Ordinary Shares, all with
voting rights. The Company currently does not hold shares in
treasury. The total number of voting rights in the Company
following Admission is therefore 810,285,389, which may be used by
shareholders as the denominator for the calculations by which they
will determine if they are required to notify their interest in, or
a change to their interest in the Company under the FCA's
Disclosure Guidance and Transparency Rules.
**ENDS**
Notes to Editors:
Hummingbird Resources plc (AIM: HUM) is a
leading multi-asset, multi-jurisdiction gold producing Company,
member of the World Gold Council and founding member of
Single Mine Origin (www.singlemineorigin.com).
The Company currently has two core gold projects, the
operational Yanfolila Gold Mine in Mali, and
the Kouroussa Gold Mine in Guinea, which will more
than double current gold production once at commercial production.
Further, the Company has a controlling interest in the Dugbe
Gold Project in Liberia that is being developed by
joint venture partners, Pasofino Gold Limited. The final
feasibility results on Dugbe showcase 2.76Moz in Reserves and
strong economics such as a 3.5-year capex payback period once in
production, and a 14-year life of mine at a low AISC profile. Our
vision is to continue to grow our asset base, producing profitable
ounces, while central to all we do being our Environmental, Social
& Governance ("ESG") policies and practices.
For further information, please
visit hummingbirdresources.co.uk or
contact:
Daniel Betts,
CEO
Thomas Hill,
FD
Edward Montgomery,
CD
|
Hummingbird Resources
plc
|
Tel: +44 (0) 20 7409
6660
|
James
Spinney
Ritchie
Balmer
|
Strand Hanson
Limited
Nominated
Adviser
|
Tel: +44
(0) 20 7409 3494
|
James
Asensio
Charlie
Hammond
|
Canaccord Genuity
Limited
Broker
|
Tel: +44 (0) 20 7523
8000
|
Bobby Morse
Oonagh
Reidy
George Pope
|
Buchanan
Financial
PR/IR
|
Tel: +44 (0) 20
7466 5000
Email: HUM@buchanan.uk.com
|