Polymetal International plc (POLY) Polymetal: Nezhda start-up 18-Oct-2021 / 09:00 MSK Dissemination of a Regulatory Announcement, transmitted by EQS Group. The issuer is solely responsible for the content of this announcement.

-----------------------------------------------------------------------------------------------------------------------

Release time  IMMEDIATE                                                         LSE, MOEX, AIX: POLY / ADR: AUCOY 
Date          18 October 2021 Polymetal International plc 

Nezhda start-up

Polymetal announces first concentrate production at the Nezhda gold-silver mine.

"Starting production on schedule, first announced in Q4 2018, demonstrates Polymetal's executing strength in the face of multiple challenges", said Vitaly Nesis, Group CEO of Polymetal. "The mine should ramp-up to full capacity and start generating free cash flows by Q2 2022".

Following the completion of all construction and commissioning activities, Nezhda successfully produced first gold and silver concentrate on October 16th. This is two weeks ahead of the previously announced target date of November 1st . The concentrator now enters a ramp-up period, and is expected to reach its nameplate capacity and full design recovery by April 2022.

The 2 Mtpa open-pit mine and combined gravity/flotation concentrator were built in 38 months following the final construction decision. Total project CAPEX by the time of full ramp-up will be approximately USUSD 370 million.

This year, Polymetal plans to produce up to 30 Koz of Gold Equivalent ("GE") at Nezhda with average production of 180 Koz per year in 2022-2024 at estimated AISC of USUSD 850-900/oz. Further production upside is linked to the opportunity of processing ore from the high-grade Prognoz silver deposit 100% owned by Polymetal.

JORC-compliant Ore Reserves at Nezhda are estimated at 4.4 GE Moz at a grade of 3.6 g/t with 24 years of mine-life. Mineral Resources additional to reserves amount to 8.1 Moz of GE at 5.1 g/t grade.

Starting from Q3 2022, 100% of energy for Nezhda will be sourced via the power line which is currently under construction. Grid connection will result in a 65% reduction of Green House Gas emissions[1] for Nezhda (from 118 Kt to 42 Kt per year) while the emission intensity level is expected to stand at 624 kg CO2e/oz GE in 2023, which is in line with the Group's trajectory for carbon footprint reduction (680 kg CO2e/oz GE by 2025).

Tailings from the plant will be stored in the form of dry cake. No impoundments or dam structures will be required.

Nezhda will create more than 1,000 permanent jobs and generate more than USUSD 20 million per year in taxes for all levels of government. The Company has invested approximately USUSD 1.7 million into various social projects in the region related to education, culture, sports, indigenous people, and health, including USUSD 0.5 million for COVID preventive measures.

About Polymetal

Polymetal International plc (together with its subsidiaries - "Polymetal", the "Company", or the "Group") is a top-10 global gold producer and top-5 global silver producer with assets in Russia and Kazakhstan. The Company combines strong growth with a robust dividend yield.

Enquiries

Media                                                   Investor Relations 
                                                        Polymetal          ir@polymetalinternational.com 
FTI Consulting 
                                                        Evgeny Monakhov    +44 20 7887 1475 (UK) 
Leonid Fink                            +44 20 3727 1000 
                                                        Timofey Kulakov 
Viktor Pomichal 
                                                        Kirill Kuznetsov   +7 812 334 3666 (Russia) 
Joint Corporate Brokers 
Morgan Stanley & Co. International plc +44 20 7425 8000 
Andrew Foster 
                                                        RBC Europe Limited 
Richard Brown 
                                                        Marcus Jackson     +44 20 7653 4000 
 
Panmure Gordon                                          Jamil Miah 
 
John Prior 
                                       +44 20 7886 2500 
Rupert Dearden 

Forward-looking statements

This release may include statements that are, or may be deemed to be, "forward-looking statements". These forward-looking statements speak only as at the date of this release. These forward-looking statements can be identified by the use of forward-looking terminology, including the words "targets", "believes", "expects", "aims", "intends", "will", "may", "anticipates", "would", "could" or "should" or similar expressions or, in each case their negative or other variations or by discussion of strategies, plans, objectives, goals, future events or intentions. These forward-looking statements all include matters that are not historical facts. By their nature, such forward-looking statements involve known and unknown risks, uncertainties and other important factors beyond the company's control that could cause the actual results, performance or achievements of the company to be materially different from future results, performance or achievements expressed or implied by such forward-looking statements. Such forward-looking statements are based on numerous assumptions regarding the company's present and future business strategies and the environment in which the company will operate in the future. Forward-looking statements are not guarantees of future performance. There are many factors that could cause the company's actual results, performance or achievements to differ materially from those expressed in such forward-looking statements. The company expressly disclaims any obligation or undertaking to disseminate any updates or revisions to any forward-looking statements contained herein to reflect any change in the company's expectations with regard thereto or any change in events, conditions or circumstances on which any such statements are based.

-----------------------------------------------------------------------------------------------------------------------

[1] Scope 1 + Scope 2

-----------------------------------------------------------------------------------------------------------------------

ISIN:           JE00B6T5S470 
Category Code:  MSCM 
TIDM:           POLY 
LEI Code:       213800JKJ5HJWYS4GR61 
OAM Categories: 3.1. Additional regulated information required to be disclosed under the laws of a Member State 
Sequence No.:   124517 
EQS News ID:    1241288 
 
End of Announcement  EQS News Service 
=------------------------------------------------------------------------------------
 

Image link: https://eqs-cockpit.com/cgi-bin/fncls.ssp?fn=show_t_gif&application_id=1241288&application_name=news

 

(END) Dow Jones Newswires

October 18, 2021 02:01 ET (06:01 GMT)

Polymetal (LSE:POLY)
Gráfica de Acción Histórica
De Mar 2024 a Abr 2024 Haga Click aquí para más Gráficas Polymetal.
Polymetal (LSE:POLY)
Gráfica de Acción Histórica
De Abr 2023 a Abr 2024 Haga Click aquí para más Gráficas Polymetal.