TIDMTXP

RNS Number : 7064Z

Touchstone Exploration Inc.

25 May 2021

TOUCHSTONE PROVIDES OPERATIONAL UPDATE

CALGARY, ALBERTA (May 25, 2021) - Touchstone Exploration Inc. ("Touchstone", "we", "our", "us" or the "Company") (TSX, LSE: TXP) provides an operational update, highlighted by the recovery of pressure gauges from the Cascadura Deep-1 well on the Company's Ortoire onshore exploration block in Trinidad (Touchstone 80 percent working interest operator, Heritage Petroleum Company Limited 20 percent working interest).

As previously announced, the Cascadura Deep-1 well was completed over a 199-foot-thick interval in Sheet Four of the overthrust Herrera Formation. Following production testing operations, the well was shut in for a pressure buildup test on April 11, 2021, and the pressure gauges were recovered on May 17, 2021.

Cascadura Deep-1 Testing Highlights

-- Buildup test data showed no depletion with a final bottomhole pressure of 4,746 psi, confirming a substantial liquids rich gas discovery.

-- Analysis of buildup data showed the test was unbounded with a minimum radius of investigation of 1,500 feet, confirming the significant size and reserves potential of the pool.

-- While the well test data indicated that the formation was damaged, we are confident that the well will require no stimulation and that flow rates will be consistent with those during testing (average flow back rate of 22.9 MMcf/d of natural gas and 449 bbls/d of NGLs).

-- Natural gas produced during the production test was approximately 94 percent methane with no hydrogen sulfide and NGLs consisted of 57 degree API condensate with no associated hydrogen sulfide.

-- There remains approximately 560 feet of potential pay above the completed zone which can be evaluated in future development.

Operational Highlights

-- The COVID-19 state of emergency in Trinidad currently has not had a significant impact on the Company's day-to-day operations, although related restrictions are causing delays to construction and field work.

-- The design for the main production facility at Cascadura has been completed with an initial production capacity of 90 MMcf/d (expandable to 200 MMcf/d).

-- Requested to complete an Environmental Impact Assessment ("EIA") on the Cascadura development project that will enable us to undertake a pre-approved multi-year program including drilling, completions, facilities, gathering lines and the main sales infrastructure without the time intensive application process that would have previously accompanied each individual workstream.

-- Royston location preparation has been delayed due to COVID-19 restrictions impacting construction, with the well anticipated to spud in June 2021.

-- Royston seismic program continues with 149 of 370 shot holes drilled and data acquisition anticipated to commence mid June 2021.

   --      Coho surface facility is nearing completion and awaiting pipeline installation and tie-in. 

-- Chinook-1 testing continues with the planned completion of the Cruse sands currently awaiting regulatory approval.

Paul Baay, President and Chief Executive Officer, commented:

"I am pleased to report that the downhole gauges recovered from Cascadura Deep-1 have provided excellent data, and the information has increased our confidence in the substantial size of the pool's reserves and its potential deliverability. The data is consistent with the previous testing performed at Cascadura-1ST1, and we are encouraged by the lack of any boundary limits observed on the reservoir.

The team continues to move all of our projects forward under the COVID-19 restrictions that were recently enacted in Trinidad. We continue to have a comprehensive COVID-19 protocol in place in collaboration with our industry partners, and we are committed to the safety and well being of our employees, contractors and the residents of the communities we operate in. For the most part, our routine operations remain uninterrupted, and we will recommence the affected operations as soon as we can safely do so.

I remain confident that we will spud Royston-1 in June despite recent construction delays due to COVID-19 emergency health measures. The drilling of Royston-1 will complete the first phase of our exploration program at Ortoire. The second phase is expected to include the Steelhead and Guabine prospects targeting the Herrera and Karamat Formations, as well as our Cretaceous prospect at Kraken. The phase two exploration program is anticipated to be performed in parallel with development programs at our confirmed Ortoire discoveries. Our future capital projects are anticipated to commence following the start of production from Coho and Cascadura, as these discoveries are expected to provide the funding for our future development and exploration programs. "

COVID-19 Update

A state of emergency was declared in Trinidad and Tobago on May 15, 2021 with a curfew between the hours of 9:00 p.m. to 5:00 a.m. in an effort to combat the rising number of COVID-19 cases and deaths. The state of emergency was an enhancement to other restrictions that were already in place including limitations on non-essential businesses and services. Our operations have been granted essential service status but some of our suppliers have not, which has resulted in partial delays to our current exploration activities. The state of emergency has not materially affected our base production operations but has impacted the preparation of the Royston-1 well access road and the shipping of the third-party rig to Trinidad.

Regulations that were due to expire on May 23, 2021 have been extended to July 4, 2021. This is separate from the current state of emergency, which will be debated in Parliament and will continue until necessary for up to three months. However, we will continue to manage our operations in accordance with domestic regulations and only proceed when we have access to all the required services available for safe and cost-effective operations.

Cascadura Deep-1 Testing

The pressure recorders were recovered from the Cascadura Deep-1 well on May 17, 2021 and provided 44 days of data that included initial completion pressure, isochronal flow and shut-in buildup data. During the buildup period, the Company observed bottomhole pressures returning to pre-test levels, with a final shut-in pressure of approximately 4,746 psi (Cascadura-1ST1 test one (lower): 4,762 psi, test two (upper): 4,715 psi). The buildup data suggested that the formation was damaged to some extent during drilling, with an estimated skin of between +4 and +7 (Cascadura-1ST1 test one (lower): +0.1, test two (upper): -1.1). Based on flowback observations, the Company believes that the well will continue to clean up once on production. No boundaries were observed during testing, with a radius of investigation of over 1,500 feet, confirming previous results observed at Cascadura-1ST1.

Gas analysis at Cascadura Deep-1 displayed a methane content of 93.7 percent (Coho 98.6 percent, Cascadura-1ST1 test one (lower) 93.3 percent) while NGL analysis indicated 57 degree API condensate (Cascadura-1ST1: 53 degree API condensate). No hydrogen sulfide was observed in any samples, and no produced water was recorded during testing.

James Shipka, Chief Operating Officer, commented:

"The data gathered from Cascadura Deep-1 reinforced our interpretation of the Cascadura structure and is extremely encouraging for the production potential of the well. This test completed 199 feet of a total of 1,007 feet of reservoir observed in the overthrust Herrera section, and there remains nearly 560 feet of high-quality sand above the existing zone in the Sheet Three section for future development. Given the nature of the Herrera sands, the existing completion should efficiently drain the gas and associated liquids trapped in Sheet Four. Flowback testing suggested that the formation had been damaged during drilling, and the buildup data quantified the magnitude of the damage. We believe that the well will clean up during production and that no stimulation is required at this time. We are now focused on bringing both Cascadura wells onto production as well as completing our comprehensive field development plan to efficiently exploit the potential of the Cascadura structure."

Cascadura EIA and Main Production Facility

The Company has been advised by the Trinidad Environmental Management Authority that an EIA is necessary for the Cascadura development project. While this will require considerable upfront work, once completed it will allow us to roll out a multi-year program including drilling, completions, facilities, gathering lines and the main sales infrastructure. The Company is expecting to receive the requirements for the EIA on May 28, 2021. While this will initially delay the project, it will bring predictable and clear timelines for Cascadura operations moving forward. The Company will provide further information on anticipated timing of the EIA as it becomes available.

We have completed the design for the Cascadura main production facility and will be soliciting bids for the required components and construction of the surface facilities. The design contemplates an initial production capacity of 90 MMcf/d (expandable to 200 MMcf/d as development progresses) with the ability to recover and sell all free liquids from current and expected future wells.

Royston

Touchstone is currently waiting on availability of the necessary soil stabilization materials to complete construction of the Royston-1 access road and surface location. Access to these materials is dependant on our suppliers being able to comply with the current COVID-19 restrictions. The drilling rig is in the final stages of pre-spud preparation and will be available to move immediately upon the completion of the access road. All drilling personnel are on the ground in Trinidad and have cleared the required quarantine protocols.

Independent of the drilling of Royston-1, we are currently in the process of acquiring 2D seismic data with 149 shot holes drilled to date out of a total of 370. Weather has been favorable thus far, and we are targeting to shoot and record data commencing the second week of June 2021. This data will provide information on possible development drilling at Royston, along with optimizing the location for the future Kraken well to test the Cretaceous Formation.

Coho

The Coho facility construction at the Coho-1 well is nearly completed and we expect to commence testing in the next three to four weeks. The Company is currently awaiting final direction from the National Gas Company of Trinidad and Tobago regarding the preferred delivery point for Coho gas volumes. Once this has been provided, the Company will begin pipeline construction which is anticipated to take 60 days subject to weather conditions.

Chinook

The testing of the Herrera zones at Chinook-1 has been completed, and the Company will move up-hole to test the Lower Cruse Formation which indicated gas while drilling. The Cruse Formation appears to be aerially extensive with hydrocarbons having been observed and produced throughout the Ortoire block and the surrounding area. Gas shows were encountered at the nearby Cascadura project while drilling, and the Company looks forward to testing the commercial potential of these sands.

In the Herrera zones, test three of the Chinook-1 well was put to pump and, after seven days, showed very limited to no new-fluid inflow with only load fluid and minimal oil being recovered. The well was shut in for a buildup period at which time the well experienced a substantial surge of reservoir fluid and solids from the formation. This inflow appears to have encapsulated the downhole assembly in sand, and following several attempts, we believe the pump to be unretrievable. This zone will be abandoned as we now focus on the shallow Cruse completion.

The Company has identified two additional locations significantly updip from the original Chinook well to evaluate the economics of the Chinook structure in the Herrera Formation. Given the limited inflow observed during testing and the skin damage reflected by the Cascadura Deep-1 testing, the Company is confident that the Herrera section of the Chinook-1 well was damaged while drilling. We are evaluating alternative drilling designs to limit possible reservoir damage in any future wells at Chinook.

Touchstone Exploration Inc.

Touchstone Exploration Inc. is a Calgary, Alberta based company engaged in the business of acquiring interests in petroleum and natural gas rights and the exploration, development, production and sale of petroleum and natural gas. Touchstone is currently active in onshore properties located in the Republic of Trinidad and Tobago. The Company's common shares are traded on the Toronto Stock Exchange and the AIM market of the London Stock Exchange under the symbol " TXP " .

For further information about Touchstone, please visit our website at www.touchstoneexploration.com or contact:

Touchstone Exploration Inc.

Mr. Paul Baay, President and Chief Executive Officer Tel: +1 (403) 750-4487

Mr. James Shipka, Chief Operating Officer

Shore Capital (Nominated Advisor and Joint Broker)

   Nominated Advisor: Edward Mansfield / Daniel Bush / Michael McGloin      Tel: +44 (0) 207 408 4090 

Corporate Broking: Jerry Keen

Canaccord Genuity (Joint Broker)

Adam James / Henry Fitzgerald O'Connor / Thomas Diehl Tel: +44 (0) 207 523 8000

Camarco (Financial PR)

Nick Hennis / Billy Clegg Tel: +44 (0) 203 781 8330

Advisory on Forward-Looking Statements

Certain information provided in this announcement may constitute forward-looking statements and information (collectively, "forward-looking statements") within the meaning of applicable securities laws. Such forward-looking statements include, without limitation, forecasts, estimates, expectations, and objectives for future operations that are subject to assumptions, risks and uncertainties, many of which are beyond the control of the Company. Forward-looking statements are statements that are not historical facts and are generally, but not always, identified by the words "expects", "plans", "anticipates", "believes", "intends", "estimates", "projects", "potential" and similar expressions, or are events or conditions that "will", "would", "may", "could" or "should" occur or be achieved.

In particular, forward-looking statements in this announcement may include, but is not limited to, statements with respect to the Company's focus, plans, priorities and strategies; the impact of the COVID-19 pandemic in Trinidad and the ability of the Company to carry on its operations as currently contemplated; the quality and quantity of prospective hydrocarbon accumulations; well test results; the Company's exploration and development plans and strategies, including anticipated drilling, future drilling locations, production testing, development, tie-in, facilities construction, the timing thereof and the benefits to be derived therefrom; regulatory approvals, including completing regulatory applications, achieving such approvals and the expected timing thereof; and the sufficiency of resources and available financing to fund future capital expenditures. Although the Company believes that the expectations and assumptions on which the forward-looking statements are based are reasonable, undue reliance should not be placed on the forward-looking statements because the Company can give no assurance that they will prove to be correct. Since forward-looking statements address future events and conditions, by their very nature they involve inherent risks and uncertainties. Actual results could differ materially from those currently anticipated due to a number of factors and risks. Certain of these risks are set out in more detail in the Company's 2020 Annual Information Form dated March 25, 2021 which has been filed on SEDAR and can be accessed at www.sedar.com. The forward-looking statements contained in this announcement are made as of the date hereof, and except as may be required by applicable securities laws, the Company assumes no obligation to update publicly or revise any forward-looking statements made herein or otherwise, whether as a result of new information, future events or otherwise.

Oil and Gas Matters

References in this announcement to production test rates and initial flow rates are useful in confirming the presence of hydrocarbons; however, such rates are not determinative of the rates at which the well will commence production and decline thereafter and are not indicative of long-term performance or of ultimate recovery. Additionally, such rates may also include recovered "load oil" fluids used in well completion stimulation. While encouraging, readers are cautioned not to place reliance on such rates in calculating the aggregate production for the Company.

Abbreviations

   bbls/d               barrels per day 
   MMcf                million cubic feet 
   MMcf/d             million cubic feet per day 
   API                   American Petroleum Institute gravity 
   NGLs                natural gas liquids 
   psi                     pounds per square inch 

Competent Persons Statement

In accordance with the AIM Rules for Companies, the technical information contained in this announcement has been reviewed and approved by James Shipka, Chief Operating Officer of Touchstone Exploration Inc. Mr. Shipka is a qualified person as defined in the London Stock Exchange's Guidance Note for Mining and Oil and Gas Companies and is a Fellow of the Geological Society of London (BGS) as well as a member of the Canadian Society of Petroleum Geologists and the Geological Society of Trinidad and Tobago. Mr. Shipka has a Bachelor of Science in Geology from the University of Calgary and has over 30 years of oil and gas exploration and development experience.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.

END

UPDPPUMCAUPGUAA

(END) Dow Jones Newswires

May 25, 2021 02:00 ET (06:00 GMT)

Touchstone Exploration (LSE:TXP)
Gráfica de Acción Histórica
De Mar 2024 a Abr 2024 Haga Click aquí para más Gráficas Touchstone Exploration.
Touchstone Exploration (LSE:TXP)
Gráfica de Acción Histórica
De Abr 2023 a Abr 2024 Haga Click aquí para más Gráficas Touchstone Exploration.