           Ore Reserves increase at Kyzyl 
 
  Polymetal announces a 25% increase in Ore Reserves at Kyzyl to 10.3 Moz of 
     gold following initial reserve estimate at East Bakyrchik of 2.2 Moz of 
           gold. 
 
  "A substantial reserve addition at East Bakyrchik extends the life-of-mine 
           at Kyzyl to 30 years", said Vitaly Nesis, Group CEO of Polymetal. 
           "Importantly, open-pit mining will now continue till 2036". 
 
HIGHLIGHTS 
 
? The initial JORC-compliant Ore Reserve estimate for East Bakyrchik (Zone 
2 of Kyzyl) as at 1 April 2020 comprises 18.8 Mt of ore at an average 
grade of 3.7 g/t containing 2.2 Moz of gold, roughly 80% of which are 
underground. 
 
? Total Kyzyl Ore Reserves now stand at 59.3 Mt of ore with an average 
grade of 5.4 g/t containing 10.3 Moz of gold. This represents a 25% 
increase compared with the estimate at the end of 2019. 
 
? Open-pit reserves increased by 9% to 4.3 Moz of gold contained at an 
average grade of 4.9 g/t, underground reserves were up 40% to 6.0 Moz at 
an average grade of 5.8 g/t. 
 
? East Bakyrchik has added 5 years to the total Kyzyl life of mine (2050), 
while life-of-mine (LOM) for the open pit has extended by 6 years (to 
2036). East Bakyrchik open-pit LOM average strip ratio is 27 t/t. 
 
? The new mining schedule assumes an increase in the capacity of the Kyzyl 
processing plant from 2.0 Mtpa to 2.2 Mtpa in 2022. 
 
? East Bakyrchik Ore Reserve estimate incorporates data from the 
exploration campaign in 2015-2020 including 29.9 km of drilling (168 
diamond drill holes). 
 
? Total Kyzyl Mineral Resources (additional to Ore Reserves) amount to 
15.6 Mt of ore with an average grade of 4.0 g/t representing 2.0 Moz of 
gold contained. 
 
           Ore Reserves (Proved + Probable) changes 
 
Ore Reserves    Category    01.01.2020    01.04.2020   Change, % 
                                 (       (Bakyrchik & 
                            Bakyrchik) 
 
                                             East 
                                          Bakyrchik) 
Open pit[1]   Tonnage, Mt      21.8          27.3        +25% 
             Au grade, g/t      5.7          4.9         -13% 
              Au content,       4.0          4.3          +9% 
                  Moz 
 
Underground   Tonnage, Mt      18.8          32.1        +71% 
             Au grade, g/t      7.1          5.8         -18% 
              Au content,       4.3          6.0         +40% 
                  Moz 
 
Total         Tonnage, Mt      40.6          59.3        +46% 
             Au grade, g/t      6.3          5.4         -15% 
              Au content,       8.2          10.3        +25% 
                  Moz 
 
ORE RESERVES 
 
The Ore Reserve estimate is reported in accordance with the JORC Code (2012) 
   and was prepared by Polymetal using a gold price of US$ 1,200/oz. For the 
Bakyrchik open pit and underground the previous estimate was performed as at 
       1 July 2019, the updated estimate was prepared as at 1 April 2020 and 
 accounts for the pit extension and depletion. A cut-off grade of 0.8 g/t of 
     gold was applied for the open pit and 3.0 g/t for the underground. East 
  Bakyrchik initial Ore Reserve estimate was performed as at 1 April 2020. A 
cut-off grade for recovered gold of 0.6 g/t was applied for the open pit and 
    2.0 g/t for the underground, the reserves were estimated on the basis of 
           variable recovery value for each of the blocks generated. 
 
           Kyzyl Ore Reserve estimate 
 
Ore Reserves           Tonnage, Gold grade,  Gold content, 
                          Mt        g/t           Moz 
Proved 
Open-pit (Bakyrchik)     1.4        7.4           0.3 
Stockpiles               0.4        5.2           0.1 
Total Proved             1.8        6.9           0.4 
 
Probable 
Open-pit                 25.5       4.8           3.9 
Bakyrchik                20.4       5.3           3.5 
East Bakyrchik           5.0        2.6           0.4 
Underground              32.1       5.8           6.0 
Bakyrchik                18.4       7.1           4.2 
East Bakyrchik           13.7       4.1           1.8 
Total Probable           57.5       5.3           9.9 
 
Proved + Probable 
Open-pit                 26.9       4.9           4.2 
Bakyrchik                21.8       5.4           3.8 
East Bakyrchik           5.0        2.6           0.4 
Underground              32.1       5.8           6.0 
Bakyrchik                18.4       7.1           4.2 
East Bakyrchik           13.7       4.1           1.8 
Stockpiles               0.4        5.2           0.1 
Total Proved+Probable    59.3       5.4           10.3 
 
           Notes: discrepancies in calculations are due to rounding 
 
           MINERAL RESOURCES 
 
 The Mineral Resources estimate is reported in accordance with the JORC Code 
(2012) and was prepared by Polymetal using a gold price of US$ 1,200/oz. For 
  the Bakyrchik open pit and underground the previous estimate was performed 
 as at 1 July 2019, the updated estimate was prepared as at 1 April 2020 and 
 accounts for the pit extension and depletion. Cut-off grades of 0.8 g/t and 
3.0 g/t of gold were applied for the open and the underground, respectively. 
East Bakyrchik updated Mineral Resource estimate was performed as at 1 April 
2020. A cut-off grade for recovered gold of 0.6 g/t was applied for the open 
    pit and 2.0 g/t for the underground, the resources were estimated on the 
    basis of variable recovery for each of the blocks generated. The Mineral 
   Resource estimate for Bolshevik was prepared by Polymetal as at 1 January 
   2019, revised estimate was not performed due to lack of material changes. 
 Cut-off grades for the open pit and the underground are 1.0 g/t and 3.3 g/t 
           of gold, respectively. 
 
           Kyzyl Additional Mineral Resource estimate 
 
Mineral Resources           Tonnage, Gold grade,  Gold content, 
(additional to Ore 
Reserves) 
                               Mt        g/t           Moz 
Measured 
Open-pit (Bakyrchik)          0.0        2.5          0.003 
Total Measured                0.0        2.5          0.003 
 
Indicated 
Open-pit                      1.8        2.2           0.1 
Bakyrchik                     0.7        2.2           0.1 
East Bakyrchik                0.4        1.2           0.0 
Bolshevik                     0.7        2.9           0.1 
Underground                   5.0        4.5           0.7 
Bakyrchik                     2.1        4.8           0.3 
East Bakyrchik                2.5        4.0           0.3 
Bolshevik                     0.4        6.4           0.1 
Total Indicated               6.8        3.9           0.9 
 
Measured + Indicated 
Open-pit                      1.9        2.2           0.1 
Bakyrchik                     0.8        2.2           0.1 
East Bakyrchik                0.4        1.2           0.0 
Bolshevik                     0.7        2.9           0.1 
Underground                   5.0        4.5           0.7 
Bakyrchik                     2.1        4.8           0.3 
East Bakyrchik                2.5        4.0           0.3 
Bolshevik                     0.4        6.4           0.1 
Total Measured + Indicated    6.8        3.9           0.9 
 
Inferred 
Open-pit                      3.9        2.3           0.3 
Bakyrchik                     0.4        2.0           0.02 
Bolshevik                     3.5        2.3           0.3 
Underground                   4.9        5.6           0.9 
Bakyrchik                     2.4        6.4           0.5 
East Bakyrchik                0.6        3.7           0.1 
Bolshevik                     1.9        5.2           0.3 
Total Inferred                8.7        4.1           1.2 
 
Measured + Indicated + 
Inferred 
Open-pit                      5.7        2.3           0.4 
Bakyrchik                     1.2        2.1           0.1 
East Bakyrchik                0.4        1.2           0.02 
Bolshevik                     4.2        2.4           0.3 
Underground                   9.8        5.1           1.6 
Bakyrchik                     4.5        5.7           0.8 
East Bakyrchik                3.1        4.0           0.4 
Bolshevik                     2.2        5.4           0.4 
Total Measured + Indicated    15.6       4.0           2.0 
+ Inferred 
 
           Notes: discrepancies in calculations are due to rounding. 
 
           Competent persons 
 
This estimate was prepared by employees of JSC Polymetal Management Company, 
JSC Polymetal Engineering and subsidiaries of the Company, led by Mr. Valery 
           Tsyplakov. 
 
         Mr. Tsyplakov is employed full-time as the Managing Director of JSC 
      Polymetal Engineering and has 19 years' experience in gold, silver and 
 polymetallic mining. Being a Fellow of the Institute of Materials, Minerals 
     & Mining (FIMMM), London, he is a Competent Person under the JORC Code. 
 
   Listed below are other Competent Persons employed by the Company that are 
    responsible for relevant research on which the Mineral Resources and Ore 
           Reserves estimate is based: 
 
? Geology and Mineral Resources - Victor Pchelka, Head of Production and 
Geology Department, Polymetal Eurasia, PONEN, MIMMM, with 34 years' 
relevant experience; 
 
? Mining and Ore Reserves: Open Pit Bakyrchik - Anton Ignatov, Chief 
Specialist for Open-pit Mining, Technical Department, Polymetal Management 
Company, MIMMM, with 17 years' relevant experience; Open Pit East 
Bakyrchik - Dmitriy Teterin, Head of Mineral Resources and Ore Reserves 
Audit Department, Polymetal Engineering, FIMMM, with 11 years' relevant 
experience; Underground - Andrei Somov, Head of underground mining 
Department, Polymetal Engineering, PONEN, FIMMM, with 32 years' relevant 
experience; 
 
? Concentration and Metals - Igor Agapov, Director of Science and 
Technology Department, Polymetal Engineering, MIMMM, with 22 years' 
relevant experience; 
 
? Mineral Resources, Bolshevik - Alexander Cherepanov, Lead Geologist, 
Prospecting and Exploration Department, Polymetal Management Company, 
MIMMM, with 27 years' relevant experience. 
 
All the above-mentioned Competent Persons have sufficient experience that is 
         relevant to the style of mineralisation and types of deposits under 
consideration and to the activity being undertaken to qualify as a Competent 
         Person as defined in the 2012 Edition of the 'Australasian Code for 
 Reporting of Exploration Results, Mineral Resources and Ore Reserves' (JORC 
           Code). 
 
      All Competent Persons have given their consent to the inclusion in the 
 report of the matters based on their information in the form and context in 
           which it appears. 
 
           About Polymetal 
 
  Polymetal International plc (together with its subsidiaries - "Polymetal", 
   the "Company", or the "Group") is a top-10 global gold producer and top-5 
    global silver producer with assets in Russia and Kazakhstan. The Company 
           combines strong growth with a robust dividend yield. 
 
Enquiries 
 
Media                     Investor Relations 
 
FTI          +44 20 3727  Polymetal ir@polymetalinternational.com 
Consulting   1000 
 
                          Evgeny    +44 20 7887 1475 (UK) 
Leonid Fink               Monakhov 
 
Viktor                    Timofey 
Pomichal                  Kulakov 
 
                                    +7 812 334 3666 (Russia) 
 
                          Kirill 
                          Kuznetsov 
 
Joint Corporate Brokers 
 
Morgan       +44 20 7425  RBC       +44 20 7653 4000 
Stanley &    8000         Europe 
Co.                       Limited 
Internationa 
l plc 
 
                          Marcus 
                          Jackson 
Andrew 
Foster 
 
                          Jamil 
                          Miah 
Richard 
Brown 
 
Panmure 
Gordon 
             +44 20 7886 
             2500 
 
Daniel 
Norman 
 
John Prior 
 
Forward-looking statements 
 
       This release may include statements that are, or may be deemed to be, 
"forward-looking statements". These forward-looking statements speak only as 
        at the date of this release. These forward-looking statements can be 
   identified by the use of forward-looking terminology, including the words 
         "targets", "believes", "expects", "aims", "intends", "will", "may", 
   "anticipates", "would", "could" or "should" or similar expressions or, in 
each case their negative or other variations or by discussion of strategies, 
plans, objectives, goals, future events or intentions. These forward-looking 
      statements all include matters that are not historical facts. By their 
    nature, such forward-looking statements involve known and unknown risks, 
 uncertainties and other important factors beyond the company's control that 
  could cause the actual results, performance or achievements of the company 
 to be materially different from future results, performance or achievements 
           expressed or implied by such forward-looking statements. Such 
  forward-looking statements are based on numerous assumptions regarding the 
     company's present and future business strategies and the environment in 
which the company will operate in the future. Forward-looking statements are 
     not guarantees of future performance. There are many factors that could 
   cause the company's actual results, performance or achievements to differ 
     materially from those expressed in such forward-looking statements. The 
company expressly disclaims any obligation or undertaking to disseminate any 
  updates or revisions to any forward-looking statements contained herein to 
 reflect any change in the company's expectations with regard thereto or any 
  change in events, conditions or circumstances on which any such statements 
           are based. 
 
=--------------------------------------------------------------------------- 
 
[1] Including stockpiles 
 
ISIN:          JE00B6T5S470 
Category Code: MSCM 
TIDM:          POLY 
Sequence No.:  87431 
EQS News ID:   1146358 
 
End of Announcement EQS News Service 
 
 

(END) Dow Jones Newswires

November 09, 2020 02:00 ET (07:00 GMT)

Polymetal (LSE:POLY)
Gráfica de Acción Histórica
De Mar 2024 a Abr 2024 Haga Click aquí para más Gráficas Polymetal.
Polymetal (LSE:POLY)
Gráfica de Acción Histórica
De Abr 2023 a Abr 2024 Haga Click aquí para más Gráficas Polymetal.