(All amounts in CDN$ unless otherwise
indicated)
VANCOUVER, BC, March 21, 2022 /PRNewswire/ - Alexco Resource
Corp. (NYSE: AXU) (TSX: AXU) ("Alexco" or the
"Company") today reports financial results for quarter and year
ended December 31, 2021 ("Q4
2021" and "FY 2021", respectively). The Company also
provides an update on the scale-up of mining operations at Keno
Hill and discusses anticipated mining and exploration activities in
2022.
- Ramp-up of mining and milling operations continued
throughout Q4 2021 and into 2022 in anticipation of reaching
sustainable design capacity (400 tonnes per operating day
("tpd")):
-
- Initial ore production from Bermingham was achieved in August
and continued throughout Q4 2021 with long-hole production from the
1150 level continuing into Q1 2022. At Flame & Moth, the
primary ramp reached the first two ore access levels with initial
ore production commencing in the first quarter of 2022 ("Q1
2022"). Additionally, in March
2022 the vent and secondary escape raise at Flame & Moth
broke through to surface, a key deliverable for establishing the
final ventilation infrastructure necessary for increased ore
production.
- Current mining operations in the first half of 2022 are focused
on extracting the remaining ore from the initial longhole stope(s)
at Bermingham, while also reaching the high grade 1120 level at
Bermingham early in the second quarter of 2022 ("Q2 2022")
as well as extracting ore from both the 815 and 835 levels at Flame
& Moth where several ore faces are now available.
- Metallurgical performance in Q4 2021 continued to meet design
expectations, despite a reduction in available ore to process.
Several mill operating campaigns have demonstrated mill throughput
capacity at and above a 400 tpd run rate.
- As a result of operational delays in Q4 2021, which continued
into the first two months of 2022, the overall ramp-up plan is
running approximately three to four months behind schedule with
design capacity expected to be reached in the third quarter of
2022.
- Updated Bermingham Resource Estimate
-
- On January 18, 2022, the Company
reported an updated and expanded mineral resource estimate for the
Company's Bermingham deposit, increasing the indicated mineral
resource estimate from 33.0 million ounces to 47.2 million ounces
of contained silver at an average grade of 939 grams per tonne
("g/t") silver ("Ag"). In addition, the inferred
mineral resource estimate increased from 11.7 million ounces to
19.9 million ounces at and average grade of 735 g/t Ag.
"Our recent progress on ramp-up of production has certainly not
been up to our expectations," said Clynton
Nauman, Chairman and CEO of Alexco, "but considering the
environment we have been operating in, and the challenges our team
has overcome to get us to this point, I am excited for what the
next few months will look like. The early part of 2022 was a very
challenging time for us at site, primarily due to a significant
reduction in our available workforce from COVID isolation
requirements following routine testing and equipment availability
issues resulting in a considerable reduction in productivity. I
believe much of that is behind us now, and we are close to finally
achieving what we have been working towards for the past 18
months. We are in the ore at both of our new mines, our
capital improvements at the mill and across the district have been
completed, and our silver production is just now starting to ramp
up. In 2022 we will also be undertaking a 15,000 meter surface
drilling program focused on identifying and testing new prospective
areas adjacent to the Bermingham deposit, especially areas
projected to contain structural characteristics and architecture
similar our discovery at Bermingham. As I have said numerous times
before, we still have work ahead of us at Keno Hill, but I am
optimistic now that we can see the finish line and that we will
reach our objective of reaching cash flow self sufficiency, and
operating a safe, sustainable, and profitable operation in the
second half of this year."
Key Financial Metrics
(expressed in
thousands of Canadian dollars,
except per share and share amounts)
|
|
|
Q4
2021
|
Q4
2020
|
FY
2021
|
FY
2020
|
Revenues – Mining
operations
|
2,814
|
-
|
19,007
|
-
|
Revenues – Reclamation
management
|
453
|
633
|
2,495
|
2,866
|
Operating
Loss
|
(10,646)
|
(11,605)
|
(19,421)
|
(22,333)
|
Adjusted Loss Before
Taxes1
|
(10,771)
|
(11,676)
|
(15,301)
|
(22,359)
|
Cash and cash
equivalents
|
9,933
|
23,742
|
9,933
|
23,742
|
Net Working
Capital1
|
1,389
|
15,353
|
1,389
|
15,353
|
Adjusted Net Loss from
Continuing Operations1
|
(6,976)
|
(9,547)
|
(12,605)
|
(16,842)
|
Net Loss from
Continuing Operations2
|
(9,069)
|
(15,817)
|
(3,146)
|
(38,570)
|
Shareholders
|
|
|
|
|
Basic and diluted net
loss from Continuing Operations per common
share2
|
(0.06)
|
(0.12)
|
(0.02)
|
(0.30)
|
Adjusted basic net loss
from Continuing Operations per common
share1
|
(0.05)
|
(0.07)
|
(0.09)
|
(0.13)
|
Adjusted diluted net
loss from Continuing Operations per common
share1
|
(0.04)
|
(0.07)
|
(0.08)
|
(0.13)
|
Total
assets3
|
210,362
|
171,667
|
210,362
|
171,667
|
Total non-current
liabilities
|
7,437
|
10,949
|
7,437
|
10,949
|
1.
|
See "Non-GAAP
Measures" in the MD&A for the year ended December 31,
2021.
|
2.
|
Net loss from
Continuing Operations for Q4 2021 includes a non-cash fair value
loss related to the embedded derivative asset totaling $2,093,000
(2020 – $6,270,000). Net loss from Continuing Operations for FY
2021 includes a non-cash fair value gain related to the embedded
derivative asset totaling $9,459,000 (2020 - loss of
$21,728,000).
|
3.
|
Total assets
increased primarily due to expenditures on mineral properties,
plant and equipment.
|
Key Performance Metrics
|
Q4
2021
|
Q3
2021
|
Q2
2021
|
Q1
2021
|
FY
2021
|
|
|
|
|
|
|
Ore tonnes
mined
|
4,996
|
11,101
|
6,464
|
4,427
|
26,988
|
Ore tonnes
milled
|
7,091
|
7,275
|
10,896
|
3,850
|
29,112
|
Mill throughput (tonnes
per operating day)1
|
253
|
162
|
176
|
107
|
170
|
Ore tonnes
stockpiled
|
1,366
|
3,809
|
635
|
5,067
|
1,366
|
Underground development
meters
|
195
|
288
|
228
|
172
|
883
|
|
|
|
|
|
|
Head
grade
|
|
|
|
|
|
Silver
(g/t)
|
547
|
778
|
703
|
985
|
720
|
Lead
|
3.1%
|
11.3%
|
9.3%
|
11.9%
|
8.5%
|
Zinc
|
2.7%
|
6.5%
|
3.1%
|
3.3%
|
3.9%
|
|
|
|
|
|
|
Recoveries
|
|
|
|
|
|
Silver
|
96%
|
95%
|
93%
|
83%
|
92%
|
Lead in lead
concentrate
|
90%
|
93%
|
83%
|
85%
|
87%
|
Zinc in zinc
concentrate
|
62%
|
65%
|
85%
|
31%
|
67%
|
|
|
|
|
|
|
Concentrate
production and grades
|
|
|
|
|
|
Lead concentrate
produced (tonnes)
|
351
|
1,039
|
1,174
|
539
|
3,103
|
Silver grade
(g/t)
|
10,179
|
5,089
|
5,729
|
5,664
|
5,996
|
Lead grade
|
57%
|
74%
|
70%
|
72%
|
70%
|
Zinc concentrate
produced (tonnes)
|
240
|
588
|
635
|
105
|
1,568
|
Silver grade
(g/t)
|
568
|
203
|
715
|
775
|
464
|
Zinc grade
|
50%
|
52%
|
53%
|
37%
|
48%
|
|
|
|
|
|
|
Contained metal in
concentrate produced
|
|
|
|
|
|
Silver
(ounces)
|
119,177
|
173,757
|
227,683
|
100,984
|
621,601
|
Lead
(pounds)
|
436,877
|
1,683,571
|
1,799,959
|
854,346
|
4,774,753
|
Zinc
(pounds)
|
262,897
|
671,606
|
637,780
|
86,494
|
1,658,777
|
|
|
|
|
|
|
Sales volumes by
payable metal2
|
|
|
|
|
|
Silver
(ounces)
|
118,924
|
167,184
|
207,876
|
88,523
|
582,507
|
Lead
(pounds)
|
453,709
|
1,650,654
|
1,725,757
|
719,178
|
4,549,298
|
Zinc
(pounds)
|
275,848
|
539,458
|
439,850
|
60,247
|
1,315,403
|
|
|
|
|
|
|
Recognized metal
prices3
|
|
|
|
|
|
Silver (per
ounce)
|
US$23.29
|
US$25.46
|
US$27.14
|
US$26.48
|
US$25.17
|
Lead (per
pound)
|
US$1.05
|
US$1.09
|
US$0.99
|
US$0.92
|
US$1.00
|
Zinc (per
pound)
|
US$1.62
|
US$1.36
|
US$1.34
|
US$1.24
|
US$1.37
|
|
|
|
|
|
|
Exploration
|
|
|
|
|
|
Meters drilled
(m)
|
1,393
|
7,209
|
8,403
|
507
|
17,512
|
Exploration
expenditures incurred – direct and indirect ($)
|
1,612,000
|
3,811,000
|
4,696,000
|
1,233,000
|
11,352,000
|
|
|
|
|
|
|
1.
|
Mill throughput
(tonnes per operating day) is based on the number of days that the
mill was operational during the period. The mill was operational
for 28 days, 45 days, 62 days and 36 days during Q4, 2021, Q3 2021,
Q2 2021 and Q1 2021, respectively.
|
2.
|
Sales volumes by
payable metal represents the volumes of each payable metal sold to
the Offtaker, and prior to the 25% of silver that is delivered to
Wheaton under the Wheaton SPA. Silver is the only metal deliverable
to Wheaton under the Wheaton SPA.
|
3.
|
Recognized metal
prices represent average metal prices for concentrate sales revenue
recognized over the period, weighted by dollar of concentrate sales
revenue recognized.
|
2022 Outlook
Activities at Keno Hill in early 2022 were meaningfully impacted
by the occurrence of numerous COVID-19 cases on site following
routine testing, which necessitated mandatory self-isolation
periods for affected employees and contractors. In addition, supply
chain interruptions had a negative impact on maintenance activities
at site, which reduced the availability of key underground
equipment. Taken together, these challenges reduced development
rates, ore extraction, and ultimately silver production in the
early parts of 2022, with Bermingham and Flame & Moth producing
a combined 4,454 tonnes through February
2022. Alexco now estimates that Q1 2022 silver production
will be approximately 75,000 to 100,000 ounces with the vast
majority of that production occurring in March 2022. With the mill now demonstrating that
it is more than capable of operating at, and even above, its design
capacity of 400 tpd, the delivery of ore from underground is the
key driver for increasing production levels. To that end, longhole
ore extraction is continuing at the Bermingham 1150 level, and in
March 2022 the Corporation reached
the ore at both the 815 and 835 levels at Flame & Moth. With
multiple ore faces in two mines operating it is anticipated that
ore deliveries in the second quarter of 2022 will improve
significantly, which should result in a significant increase to Q2
2022 silver production levels. While risks to our outlook
remain elevated, the Corporation estimates that Q2 2022 silver
production will range between 450,000 and 550,000 ounces; before
targeting an increase to effective "run-rate" levels in the second
half of the year. Management intends to provide 2022 silver
production guidance on May 12, 2022
when it announces its results for the quarter ended March 31, 2022.
Conference Call for FY 2021 Results
Alexco management will discuss the results during an audio
webcast conference call on Monday, March 21,
2022 at 11:00 am Eastern Time
(8:00 am Pacific Time).
To participate in the live call, please use one of the following
methods:
Dial toll free from Canada or the
US: 1-800-319-4610
Dial from outside Canada or the
US: 1-604-638-5340
Confirmation
Code#: Ask
to join the Alexco conference call
Live audio
webcast:
https://services.choruscall.ca/links/alexco20220315.html
Participants should connect five to ten minutes before the call.
The conference call will be recorded, and an archived audio webcast
will be available at www.alexcoresource.com shortly after the
call.
Qualified Persons
The disclosure in this news release of scientific and technical
information regarding exploration projects on Alexco's mineral
properties has been reviewed and approved by Alan McOnie, FAusIMM, while that regarding mine
development and operations has been reviewed and approved by
Sebastien D. Tolgyesi, P.Eng.,
P.Geo., Keno Hill Operations Manager, both of whom are Qualified
Persons as defined by National Instrument 43-101
– Standards of Disclosure for Mineral Projects.
About Alexco
Alexco is a Canadian primary silver company that owns and
operates the majority of the historic Keno Hill Silver District, in
Canada's Yukon Territory, one of the highest-grade
silver deposits in the world. Alexco is currently advancing Keno
Hill to commercial production and commenced concentrate production
and shipments in the first quarter of 2021. Keno Hill is
expected to produce an average of approximately 4.4 million ounces
of silver per year contained in high quality lead/silver and zinc
concentrates. Keno Hill retains significant potential to grow and
Alexco has a long history of expanding the operation's mineral
resources through successful exploration.
Website: www.alexcoresource.com
Forward-Looking Statements
Some statements ("forward-looking statements") in this news
release contain forward-looking information concerning Alexco's
anticipated results and developments in Alexco's operations in
future periods, planned exploration and development of its
properties, plans related to its business and other matters that
may occur in the future, made as of the date of this news release.
Forward-looking statements may include, but are not limited to,
statements with respect to the future remediation and reclamation
activities, future mineral exploration, the estimation of mineral
reserves and mineral resources, the realization of mineral reserve
and mineral resource estimates, future mine construction and
development activities, future mine operation and production, the
timing of activities and reports, the amount of estimated revenues
and expenses, the success of exploration activities, permitting
time lines, requirements for additional capital and sources and
uses of funds. Forward-looking statements are subject to a variety
of known and unknown risks, uncertainties and other factors, which
could cause actual events or results to differ from those expressed
or implied by the forward-looking statements. Such factors include,
among others, risks related to actual results and timing of
exploration and development activities; actual results and timing
of mining activities; actual results and timing of environmental
services activities; actual results and timing of remediation and
reclamation activities; conclusions of economic evaluations;
changes in project parameters as plans continue to be refined;
future prices of silver, gold, lead, zinc and other commodities;
possible variations in mineable resources, grade or recovery rates;
failure of plant, equipment or processes to operate as anticipated;
accidents, labour disputes and other risks of the mining industry;
First Nation rights and title; continued capitalization and
commercial viability; global economic conditions; competition; and
delays in obtaining governmental approvals or financing or in the
completion of development activities. Forward-looking
statements are based on certain assumptions that management
believes are reasonable at the time they are made. In making the
forward-looking statements included in this news release, Alexco
has applied several material assumptions, including, but not
limited to, the assumption that Alexco will be able to raise
additional capital as necessary, that the proposed exploration and
development will proceed as planned, and that market fundamentals
will result in sustained silver, gold, lead and zinc demand and
prices. There can be no assurance that forward-looking statements
will prove to be accurate and actual results and future events
could differ materially from those anticipated in such statements.
Alexco expressly disclaims any intention or obligation to update or
revise any forward-looking statements whether as a result of new
information, future events or otherwise, except as otherwise
required by applicable securities legislation.
View original
content:https://www.prnewswire.com/news-releases/alexco-announces-full-2021-results-and-2022-outlook-301506189.html
SOURCE Alexco Resource Corp.