Ero Copper Corp. (TSX: ERO, NYSE: ERO) (the
“Company”) is pleased to provide a construction update for the
Tucumã Project (the "Project"), highlighting significant progress
since October 2023. With physical completion now at over 85% and
production of copper concentrate scheduled to commence in H2 2024,
the Company has initiated the transition from construction to
commissioning, as outlined below in the 2024 Commissioning Plan.
HIGHLIGHTS
- Construction: Physical construction of the
Project is now over 85% complete
- Main substation and e-houses installed and commissioned with
16-kilometer power line tie-in to the national grid completed ahead
of schedule; line expected to be fully energized by the 20th of
January
- Pre-stripping activities are tracking approximately 10% ahead
of schedule with completion now expected at the end of Q1 2024. To
date, approximately 3,200 tonnes of sulphide ore have been placed
on the run-of-mine stockpile for process plant commissioning
- Mechanical completion testing and sub-component commissioning
have commenced for key pieces of processing equipment including the
primary crusher, ball mill, secondary and tertiary crushers,
vibrating screen decks and flotation cells
- Remaining steel structures, plate work and mechanical equipment
installations are tracking on or ahead of schedule. Construction
activities through the remainder of Q1 2024 will focus on
completing piping, electric cabling, automation and instrumentation
system installations
- 2024 Commissioning Plan: Expected
commissioning milestones in advance of first concentrate production
in H2 2024, include:
- End of Q1 2024: mechanical completion and sub-component
commissioning (lubrication, hydraulic, electrical, instrumentation
and automation systems)
- March 2024: First ore through the crushing circuit comprised of
primary and secondary crushers as well as screening and conveyance
systems
- April 2024: First ore through the milling circuit
- May 2024: First ore through regrind mill circuit, concentrate
and tailings filtering systems
- June 2024: Integrated commissioning with flotation circuit and
Project ramp-up
- People & Safety: Opportunistic increase in
construction workforce mobilization
- Recent demobilization of a Brazilian mining project has allowed
the Company to add approximately 500 trained contractors on site,
increasing the total workforce of employees and contractors to
approximately 2,220 people
- To date, there have been no lost-time injuries on the Project,
with over three million hours of work completed since 2022
- Project Capital Estimate: Remaining
construction expenditures hedged through expanded foreign exchange
hedge program
- Direct Project capital expenditures have been updated to
approximately $310 million (compared to the previous estimate of
$305 million) to reflect the impact of a stronger Brazilian Real
("BRL") against the U.S. dollar ("USD") in Q4 2023, which was
partially offset by reduced stripping costs
- Following the opportunistic expansion of the Company's foreign
exchange hedge program in late 2023, the Project's remaining
construction expenditures are hedged at a weighted average floor
and ceiling of 5.10 and 5.23 BRL per USD, respectively
"As we transition from construction to
commissioning, the paramount achievement at Tucumã is the
outstanding safety performance of our construction team. Marking a
significant milestone, we have surpassed three million hours of
work without a lost time incident. I extend my heartfelt
congratulations to our Project leadership team, as well as the
2,200 employees and contractors on site, for their continued
diligence and thoughtful execution in advancing Tucumã towards
production," said David Strang, Chief Executive Officer.
"This is an exciting phase for Ero Copper as we
prepare to bring Tucumã into operation later this year and
anticipate consolidated copper production reaching over 100,000
tonnes in 2025. With the recent shift in copper supply-demand
fundamentals signaling supply deficits in 2024 and 2025, the timing
of our growth trajectory couldn't be better."
Figure 1: January 2024 aerial
view of advanced pre-stripping activities, which are 10% ahead of
schedule and tracking towards completion at the end of Q1 2024.
Figure 2: Ball mill and
hydrocyclone battery as of January 2024.
Figure 3: Flotation cells and
tailings thickener as of January 2024.
Figure 4: Primary and secondary
crushing, screening and conveyance systems.
Figure 5: Completed primary
sub-station and power line with tie-in to the national grid as of
January 2024.
ABOUT ERO COPPER CORP
Ero is a high-margin, high-growth, low
carbon-intensity copper producer with operations in Brazil and
corporate headquarters in Vancouver, B.C. The Company's primary
asset is a 99.6% interest in the Brazilian copper mining company,
Mineração Caraíba S.A. ("MCSA"), 100% owner of the Company's
Caraíba Operations (formerly known as the MCSA Mining Complex),
which are located in the Curaçá Valley, Bahia State, Brazil and
include the Pilar and Vermelhos underground mines and the Surubim
open pit mine, and the Tucumã Project (formerly known as Boa
Esperança), an IOCG-type copper project located in Pará, Brazil.
The Company also owns 97.6% of NX Gold S.A. ("NX Gold") which owns
the Xavantina Operations (formerly known as the NX Gold Mine),
comprised of an operating gold and silver mine located in Mato
Grosso, Brazil. Additional information on the Company and its
operations, including technical reports on the Caraíba Operations,
Xavantina Operations and Tucumã Project, can be found on SEDAR+ at
www.sedarplus.ca/landingpage/ and on EDGAR (www.sec.gov). The
Company’s shares are publicly traded on the Toronto Stock Exchange
and the New York Stock Exchange under the symbol “ERO”.
FOR MORE INFORMATION, PLEASE CONTACT
Courtney Lynn, SVP, Corporate Development,
Investor Relations & Sustainability(604)
335-7504info@erocopper.com
CAUTION REGARDING FORWARD LOOKING INFORMATION
AND STATEMENTS
This press release contains “forward-looking
statements” within the meaning of the United States Private
Securities Litigation Reform Act of 1995 and “forward-looking
information” within the meaning of applicable Canadian securities
legislation (collectively, “forward-looking statements”).
Forward-looking statements include statements that use
forward-looking terminology such as “may”, “could”, “would”,
“will”, “should”, “intend”, “target”, “plan”, “expect”, “budget”,
“estimate”, “forecast”, “schedule”, “anticipate”, “believe”,
“continue”, “potential”, “view” or the negative or grammatical
variation thereof or other variations thereof or comparable
terminology. Forward-looking statements may include, but are not
limited to, statements with respect to the timing of energizing the
power line at the Project, the expected timing of completion of
pre-stripping activities, the expected completion of construction
activities and transition to commissioning as detailed in the 2024
Commissioning Plan, the timing of initial copper concentrate
production, estimated Project capital to be spent, the projected
copper supply deficit in 2024, and any other statement that may
predict, forecast, indicate or imply future plans, intentions,
levels of activity, results, performance or achievements.
Forward-looking statements are not a guarantee
of future performance. There can be no assurance that
forward-looking statements will prove to be accurate, as actual
results and future events could differ materially from those
anticipated in such statements. Forward-looking statements involve
statements about the future and are inherently uncertain, and the
Company’s actual results, achievements or other future events or
conditions may differ materially from those reflected in the
forward-looking statements due to a variety of risks, uncertainties
and other factors, including, without limitation, those referred to
herein and in the AIF under the heading “Risk Factors”.
The Company’s forward-looking statements are
based on the assumptions, beliefs, expectations and opinions of
management on the date the statements are made, many of which may
be difficult to predict and beyond the Company’s control. In
connection with the forward-looking statements contained in this
press release and in the AIF, the Company has made certain
assumptions about, among other things: continued effectiveness of
the measures taken by the Company to mitigate the possible impact
of COVID-19 on its workforce and operations; favourable equity and
debt capital markets; the ability to raise any necessary additional
capital on reasonable terms to advance the production, development
and exploration of the Company’s properties and assets; future
prices of copper, gold and other metal prices; the timing and
results of exploration and drilling programs; the accuracy of any
mineral reserve and mineral resource estimates; the geology of the
Caraíba Operations, the Xavantina Operations and the Tucumã Project
being as described in the respective technical report for each
property; production costs; the accuracy of budgeted exploration,
development and construction costs and expenditures; the price of
other commodities such as fuel; future currency exchange rates and
interest rates; operating conditions being favourable such that the
Company is able to operate in a safe, efficient and effective
manner; work force continuing to remain healthy in the face of
prevailing epidemics, pandemics or other health risks (including
COVID-19), political and regulatory stability; the receipt of
governmental, regulatory and third party approvals, licenses and
permits on favourable terms; obtaining required renewals for
existing approvals, licenses and permits on favourable terms;
requirements under applicable laws; sustained labour stability;
stability in financial and capital goods markets; availability of
equipment; positive relations with local groups and the Company’s
ability to meet its obligations under its agreements with such
groups; and satisfying the terms and conditions of the Company’s
current loan arrangements. Although the Company believes that the
assumptions inherent in forward-looking statements are reasonable
as of the date of this press release, these assumptions are subject
to significant business, social, economic, political, regulatory,
competitive and other risks and uncertainties, contingencies and
other factors that could cause actual actions, events, conditions,
results, performance or achievements to be materially different
from those projected in the forward-looking statements. The Company
cautions that the foregoing list of assumptions is not exhaustive.
Other events or circumstances could cause actual results to differ
materially from those estimated or projected and expressed in, or
implied by, the forward-looking statements contained in this press
release. There can be no assurance that forward-looking statements
will prove to be accurate, as actual results and future events
could differ materially from those anticipated in such statements.
Accordingly, readers should not place undue reliance on
forward-looking statements.
Forward-looking statements contained herein are
made as of the date of this press release and the Company disclaims
any obligation to update or revise any forward-looking statement,
whether as a result of new information, future events or results or
otherwise, except as and to the extent required by applicable
securities laws.
CAUTIONARY NOTES REGARDING MINERAL RESOURCE AND
MINERAL RESERVE ESTIMATES
Unless otherwise indicated, all reserve and
resource estimates included in this presentation and the documents
incorporated by reference herein have been prepared in accordance
with National Instrument 43-101, Standards of Disclosure for
Mineral Projects (“NI 43-101") and the Canadian Institute of
Mining, Metallurgy and Petroleum (the “CIM”) — CIM Definition
Standards on Mineral Resources and Mineral Reserves, adopted by the
CIM Council, as amended (the “CIM Standards”). NI 43-101 is a rule
developed by the Canadian Securities Administrators that
establishes standards for all public disclosure an issuer makes of
scientific and technical information concerning mineral projects.
Canadian standards, including NI 43-101, differ significantly from
the requirements of the United States Securities and Exchange
Commission (the “SEC”), and reserve and resource information
included herein may not be comparable to similar information
disclosed by U.S. companies. In particular, and without limiting
the generality of the foregoing, this presentation and the
documents incorporated by reference herein use the terms “measured
resources,” “indicated resources” and “inferred resources” as
defined in accordance with NI 43-101 and the CIM Standards.
Further to recent amendments, mineral property
disclosure requirements in the United States (the “U.S. Rules”) are
governed by subpart 1300 of Regulation S-K of the U.S. Securities
Act of 1933, as amended (the “U.S. Securities Act”) which differ
from the CIM Standards. As a foreign private issuer that is
eligible to file reports with the SEC pursuant to the
multi-jurisdictional disclosure system (the “MJDS”), Ero is not
required to provide disclosure on its mineral properties under the
U.S. Rules and will continue to provide disclosure under NI 43-101
and the CIM Standards. If Ero ceases to be a foreign private issuer
or loses its eligibility to file its annual report on Form 40-F
pursuant to the MJDS, then Ero will be subject to the U.S. Rules,
which differ from the requirements of NI 43-101 and the CIM
Standards.
Pursuant to the new U.S. Rules, the SEC
recognizes estimates of “measured mineral resources”, “indicated
mineral resources” and “inferred mineral resources.” In addition,
the definitions of “proven mineral reserves” and “probable mineral
reserves” under the U.S. Rules are now “substantially similar” to
the corresponding standards under NI 43-101. Mineralization
described using these terms has a greater amount of uncertainty as
to its existence and feasibility than mineralization that has been
characterized as reserves. Accordingly, U.S. investors are
cautioned not to assume that any measured mineral resources,
indicated mineral resources, or inferred mineral resources that Ero
reports are or will be economically or legally mineable. Further,
“inferred mineral resources” have a greater amount of uncertainty
as to their existence and as to whether they can be mined legally
or economically. Under Canadian securities laws, estimates of
“inferred mineral resources” may not form the basis of feasibility
or pre-feasibility studies, except in rare cases. While the above
terms under the U.S. Rules are “substantially similar” to the
standards under NI 43-101 and CIM Standards, there are differences
in the definitions under the U.S. Rules and CIM Standards.
Accordingly, there is no assurance any mineral reserves or mineral
resources that Ero may report as “proven mineral reserves”,
“probable mineral reserves”, “measured mineral resources”,
“indicated mineral resources” and “inferred mineral resources”
under NI 43-101 would be the same had Ero prepared the reserve or
resource estimates under the standards adopted under the U.S.
Rules.
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/8ed591aa-32fd-47c8-a3a2-9b52a8222224
https://www.globenewswire.com/NewsRoom/AttachmentNg/e15e3d59-7bc9-492e-80db-0e0dcc787847
https://www.globenewswire.com/NewsRoom/AttachmentNg/3f0adfa3-08c6-4c75-8d71-3a5a06ac2127
https://www.globenewswire.com/NewsRoom/AttachmentNg/033f84fa-85f4-4c75-955c-d5847342b047
https://www.globenewswire.com/NewsRoom/AttachmentNg/3e4a5d29-c94d-46c1-ab64-721221b89879
Ero Copper (TSX:ERO)
Gráfica de Acción Histórica
De Ene 2025 a Feb 2025
Ero Copper (TSX:ERO)
Gráfica de Acción Histórica
De Feb 2024 a Feb 2025