African Gold Group, Inc., (TSX VENTURE:AGG) ("AGG" or the "Company") is pleased
to report the analytical results for 20 near surface (oxide), reverse
circulation (RC) step out drill holes, from the Company's Kobada, Mali gold
project. 


Near Surface (Oxide) Drill Highlights From Northern Step Out RC Holes Include:



KBRC12-010: 52 m @ 1.28 g/t Au, ended in mineralization                     
KBRC12-012: 41 m @ 1.04 g/t Au, ended in mineralization                     
KBRC12-013: 85 m @ 1.13 g/t Au                                              
KBRC12-014: 107 m @ 1.21 g/t Au, ended in mineralization                    
KBRC12-015: 43 m @ 1.39 g/t Au, ended in mineralization                     
KBRC12-016: 75 m @ 1.92 g/t Au & 68 m @ 0.96 g/t Au, ended in mineralization
KBRC12-017: 109 m @ 0.81 g/t Au                                             
KBRC12-018: 56 m @ 1.21 g/t Au, ended in mineralization                     
KBRC12-020: 146 m @ 1.13 g/t Au, ended in mineralization                    



The assay results detailing mineralized intercepts for the 20 near surface
(oxide) northern step out RC holes are listed in Table 1 below:




TABLE 1                                                                     
                                                                            
----------------------------------------------------------------------------
Section    Hole ID    From     To  Length     Au EOH Degrees  Hole Objective
                       (m)    (m)     (m)  (g/t) (m)    (tn)                
----------------------------------------------------------------------------
850S    KBRC12-009   15.00  39.00   24.00   1.20               Infill Zone 1
                                                                       North
                                                                   extension
850S     including   20.00  21.00    1.00  10.51                            
850S    KBRC12-009   48.00  66.00   18.00   1.02                            
850S    KBRC12-009  104.00 153.00   49.00   0.51                 Hole end in
                                                              mineralization
----------------------------------------------------------------------------
850S    KBRC12-010    2.00  19.00   17.00   0.58 147     200   Infill Zone 1
                                                                       North
                                                                   extension
850S    KBRC12-010   28.00  48.00   20.00   0.68                            
850S    KBRC12-010   95.00 147.00   52.00   1.28                 Hole end in
                                                              mineralization
----------------------------------------------------------------------------
850S    KBRC12-011    0.00   5.00    5.00   0.51 128     200   Infill Zone 1
                                                                       North
                                                                   extension
850S    KBRC12-011   15.00  18.00    3.00   0.32                            
850S    KBRC12-011   28.00  39.00   11.00   0.57                            
850S    KBRC12-011   49.00  52.00    3.00   0.75                            
850S    KBRC12-011   86.00  89.00    3.00   0.30                            
850S    KBRC12-011   97.00 108.00   11.00   0.36                            
850S    KBRC12-011  115.00 121.00    6.00   0.51                 Hole end in
                                                              mineralization
----------------------------------------------------------------------------
800S    KBRC12-012    2.00   5.00    3.00   0.62 153     200   Infill Zone 1
                                                                       North
                                                                   extension
800S    KBRC12-012   59.00  63.00    4.00   2.51                            
800S    KBRC12-012   97.00 101.00    4.00   0.38                            
800S    KBRC12-012  110.00 151.00   41.00   1.04                            
800S     Including  130.00 131.00    1.00  10.56                 Hole end in
                                                              mineralization
----------------------------------------------------------------------------
800S    KBRC12-013    2.00  21.00   19.00   0.68 135     200   Infill Zone 1
                                                                       North
                                                                   extension
800S    KBRC12-013   30.00  33.00    3.00   0.30                            
800S    KBRC12-013   45.00 130.00   85.00   1.13                            
800S     Including   55.00  56.00    1.00  10.15                            
800S     Including   81.00  82.00    1.00  18.11                            
----------------------------------------------------------------------------
800S    KBRC12-014    2.00  18.00   16.00   0.32 153     200   Infill Zone 1
                                                                       North
                                                                   extension
800S    KBRC12-014   27.00  37.00   10.00   0.30                            
800S    KBRC12-014   46.00 153.00  107.00   1.21                            
800S     Including   58.00  59.00    1.00  56.10                 Hole end in
                                                              mineralization
----------------------------------------------------------------------------
800S    KBRC12-015   15.00  58.00   43.00   1.39 141     200   Infill Zone 1
                                                                       North
                                                                   extension
800S     Including   16.00  17.00    1.00  10.60                            
800S     Including   19.00  20.00    1.00  11.73                            
800S    KBRC12-015   81.00  84.00    3.00   0.43                            
800S    KBRC12-015   99.00 102.00    3.00   0.62                            
800S    KBRC12-015  126.00 141.00   15.00   2.15                            
800S     Including  134.00 135.00    1.00  22.93                 Hole end in
                                                              mineralization
----------------------------------------------------------------------------
750S    KBRC12-016    1.00  76.00   75.00   1.92 153     200   Infill Zone 1
                                                                       North
                                                                   extension
750S     Including   15.00  16.00    1.00  22.12                            
750S     Including   27.00  28.00    1.00  17.60                            
750S     Including   54.00  55.00    1.00  12.94                            
750S    KBRC12-016   85.00 153.00   68.00   0.96                 Hole end in
                                                              mineralization
----------------------------------------------------------------------------
750S    KBRC12-017    2.00 111.00  109.00   0.81 123     200   Infill Zone 1
                                                                       North
                                                                   extension
750S     Including   31.00  32.00    1.00  10.99                            
----------------------------------------------------------------------------
750S    KBRC12-018   11.00  67.00   56.00   1.21 105     200                
750S     Including   17.00  18.00    1.00  13.13                            
750S    KBRC12-018   78.00 105.00   27.00   0.58                 Hole end in
                                                              mineralization
----------------------------------------------------------------------------
700S    KBRC12-019    4.00   9.00    5.00   0.36 147     200   Infill Zone 1
                                                                       North
                                                                   extension
700S    KBRC12-019   71.00 131.00   60.00   0.42                            
700S    KBRC12-019  140.00 143.00    3.00   0.35                            
----------------------------------------------------------------------------
700S    KBRC12-020    2.00 148.00  146.00   1.13 153     200   Infill Zone 1
                                                                       North
                                                                   extension
700S     Including   42.00  43.00    1.00  10.07                            
700S     Including  103.00 104.00    1.00  10.61                            
700S     Including  126.00 127.00    1.00  18.52                            
700S     Including  128.00 129.00    1.00  10.29                 Hole end in
                                                              mineralization
----------------------------------------------------------------------------
700S    KBRC12-021   10.00  15.00    5.00   0.51 111     200   Infill Zone 1
                                                                       North
                                                                   extension
700S    KBRC12-021   38.00  75.00   37.00   0.46                            
----------------------------------------------------------------------------
700S    KBRC12-022   10.00  15.00    5.00   0.55 147     200   Infill Zone 1
                                                                       North
                                                                   extension
700S    KBRC12-022   49.00  54.00    5.00   1.09                            
700S    KBRC12-022   74.00  97.00   23.00   0.58                            
700S    KBRC12-022  110.00 147.00   37.00   0.67                 Hole end in
                                                              mineralization
----------------------------------------------------------------------------
650S    KBRC12-023    2.00  39.00   37.00   0.47 135     200   Infill Zone 1
                                                                       North
                                                                   extension
650S    KBRC12-023   72.00  75.00    3.00   0.30                            
650S    KBRC12-023  118.00 134.00   16.00   0.41                            
----------------------------------------------------------------------------
650S    KBRC12-024    4.00   7.00    3.00   0.35 147     200   Infill Zone 1
                                                                       North
                                                                   extension
650S    KBRC12-024   25.00  53.00   28.00   0.67                            
650S    KBRC12-024   67.00 143.00   76.00   0.48                            
----------------------------------------------------------------------------
650S    KBRC12-025    7.00  19.00   12.00   0.41 139     200   Infill Zone 1
                                                                       North
                                                                   extension
650S    KBRC12-025   33.00 103.00   70.00   0.47                            
650S    KBRC12-025  114.00 117.00    3.00   0.50                            
650S    KBRC12-025  134.00 138.00    4.00   0.51                            
----------------------------------------------------------------------------
650S    KBRC12-026    2.00  11.00    9.00   0.78 147     200   Infill Zone 1
                                                                       North
                                                                   extension
650S    KBRC12-026   24.00  97.00   73.00   0.40                            
650S    KBRC12-026  127.00 130.00    3.00   0.95                            
----------------------------------------------------------------------------
600S    KBRC12-027   10.00  13.00    3.00   0.85 153     200   Infill Zone 1
                                                                       North
                                                                   extension
600S    KBRC12-027   59.00  62.00    3.00   0.30                            
600S    KBRC12-027   75.00 139.00   64.00   0.53                            
----------------------------------------------------------------------------
600S    KBRC12-028    9.00  17.00    8.00   0.54 153     200   Infill Zone 1
                                                                       North
                                                                   extension
600S    KBRC12-028   25.00  71.00   46.00   0.66                            
600S    KBRC12-028   84.00 136.00   52.00   0.66                            
600S    KBRC12-028  145.00 153.00    8.00   0.52                 Hole end in
                                                              mineralization
----------------------------------------------------------------------------
600S    KBRC12-029    5.00  12.00    7.00   0.43 150     200   Infill Zone 1
                                                                       North
                                                                   extension
600S    KBRC12-029   55.00  62.00    7.00   0.91                            
600S    KBRC12-029   78.00 148.00   70.00   0.70               Infill Zone 1
                                                                       North
                                                                   extension
600S     including  135.00 136.00    1.00 11.720               Infill Zone 1
                                                                       North
                                                                   extension
----------------------------------------------------------------------------
1. Significant drilled intercepts have a minimum length of 3m at 0.3 g/t or
   the product "Length X Grade" greater than 0.9 g.m/t. Intercepts are     
   drilled lengths and may not be true width within a structure dipping 70 
  degrees to 80 degrees                                                  
2. Up to 7 m of horizontal "waste" included within mineralized intercept   



AGG's management is most encouraged with the drill results being reported today.
More specifically, today's results demonstrate the continuation of significant
gold mineralization being intercepted as far as 500 meters north of the
Company's current 43-101 resource estimate, reported in July, 2011. This 500
meter northern extension, contained between sections 1100S thru section 600S,
will be incorporated into a revised resource estimate that forms part of the
Company's ongoing Feasibility Study for the Kobada, Mali gold project. It is
anticipated that a revised resource estimate will be published on or before
April 30, 2013.


Drill intercepts from section 1000S, located 100 meters north of AGG's 43-101
resource estimate, were previously reported in a press release dated November
15, 2011 and included the following near surface drill intercept highlights:


Near Surface (Oxide) Drill Highlights From Northern Step-Out Holes On Section
1000S Include:




--  KBRC11-189: 112 m @ 2.14 g/t Au, incl, 1 m @ 90.19 g/t Au, ended in
    mineralization 
--  KBRC11-192: 88 m @ 1.66 g/t Au, incl 2 m @ 25.60 g/t Au 
--  KBRC11-191: 55 m @ 0.79 g/t Au, incl 1 m @ 15.06 g/t Au 
--  KBRC11-190: 42 m @ 0.96 g/t Au, incl 1 m @ 12.42 g/t Au 
--  KBRC11-193: 12m @ 0.89 g/t Au, ended in mineralization 



Drill intercepts from Section 950S and 900S, located up to 200 meters north of
AGG's 43-101 resource estimate, were previously reported in a press release
dated March 20, 2012 and included the following near surface drill intercept
highlights:


Near Surface (Oxide) Drill Highlights From Northern Step-Out Holes On Section
950S & 900S Include:




--  KBRC12-006: 70 m @ 1.83 g/t Au & 45 m @ 1.79 g/t Au, ended in
    mineralization 
--  KBRC12-003: 27 m @ 0.47 g/t Au & 84 m @ 1.26 g/t Au, ended in
    mineralization 
--  KBRC12-004: 21 m @ 1.07 g/t & 9 m @ 1.80 Au 
--  KBRC12-005: 21 m @ 1.15 g/t Au 



"Today's drill results, detailing holes collared on sections 850S thru to 600S,
clearly show the continuing presence of robust gold mineralization extending as
far as 500 meters north of our current Zone 1, 43-101 resource. Kobada obviously
remains open to the north along strike and our depth potential is clearly
visible with 11 of 20 holes (being reported in this release) ending in
mineralization. 


"In addition to demonstrating a strike extension of at least 500 meters north of
our current 43-101 resource estimate, the holes that comprise northern extension
also define a mineralized corridor that exceeds 100 meters in lateral width that
are also associated with an oxidation depth in the magnitude of 100 vertical
meters. The mineralization contained within these northern step out holes is
well distributed down several of the holes, and is as strong as any gold
mineralization encountered in the Zone 1 resource to date," states AGG
President, Michael A. Nikiforuk.


To view the map associated with this press release, please visit
http://media3.marketwire.com/docs/AGG226MAP.jpg.


Kobada Review 

On July 14, 2011 AGG announced the results of a positive NI 43-101 Preliminary
Economic Assessment (the "PEA" or the "Study") that evaluates the potential of
an open pit, bulk mining model, utilizing a gravity recovery process plant, at
the Company's Kobada (Mali) gold project. The PEA incorporates and includes
drill data up to the end of December, 2010. There is no drill data from either
the 2011 or 2012 campaign included in the PEA. More specifically, the PEA does
not incorporate drill data for the northern extension holes that hold potential
to extend Zone 1 up to 2 kilometers north of the Zone 1 deposit, in addition,
the PEA does not incorporate the 2011 southern holes that hold potential to
extend Zone 1 up to 1.55 kilometers south of the Zone 1 deposit, nor does the
Study include any potential from the newly discovered Foroko North deposit, the
newly discovered Termite Zone or the recently announced Gosso discovery zone,
the latter three discovery zones being separate and distinct structures from
Zone 1.


Project Economics - Base Case 

The PEA estimates an after-tax Net Present Value (NPV) of US$216.9 million from
commencement of construction and an after-tax Internal Rate Of Return (IRR) of
90.57% using a base case of US$1,100 per ounce of gold and a discount rate of
5%. 


The Kobada project base case is for processing 20,000 tonnes per day for a total
of 7,000,000 tonnes per year in a gravity process plant that is projected to
recover 87.9% of the gold contained in 41,750,000 tonnes of lateritic material
assaying 0.64 g/t Au, for average annual production of 126,600 ounces of gold
for the first five years of operation. The average annual operating cost is
calculated to be US$8.27/t for the first five years of operation with a CAPEX of
US$122,500,000. The project produces gold at the direct cost of US$470.90 per
ounce. The Study demonstrates that the Kobada gold project is economically
optimized by adopting bulk mining versus selective mining. The direct
implications of bulk mining are demonstrated in a substantial increase in
tonnage and recoverable gold but with an associated decrease in the average gold
grade. Please visit www.africangoldgroup.com to review the entire content of
AGG's July 14, 2011 press release announcing the results of the positive
Preliminary Economic Assessment.


Sampling - QA/QC Program 

RC cuttings are recovered at the bottom outlet of the RC rig cyclone into 50-kg
capacity poly-weave bags to recover the cuttings from each 1 meter of drill
penetration. Each one meter sample weighs an average of approximately 19 to 23
kg. Each sample is passed through a 3-tier Jones Riffler (1 to 8 split), the
samples are riffled twice to obtain from 3 to 5 kg of cuttings which are put in
a numbered sample bag. Each bag is sealed and picked up on site by ALS Chemex
Laboratories for delivery to its Burkina Faso facilities. The remaining 14 to 18
kg of cuttings (field rejects) are stored in camp under tarps to protect the
bags against the elements. 


Original samples are analyzed using Leachwell on 2 kg of pulp. Leachwell is a
bottle roll cyanidation procedure with the addition of a catalyst to speed up
gold dissolution. A QA/QC program is in place and includes: blank (1 in 20
samples), duplicates (1 in 20), standards (1 in 20), external lab checks (1 in
30) and two different analytical procedures checks (1 in 100). 


Under the guidelines of National Instrument 43-101, the qualified person for the
Kobada Gold Project is Mr. Pierre Lalande, P. Geo. Mr. Lalande is a member of
the Association of Professional Geoscientists of Ontario and has reviewed and
approved the contents of this news release. 


African Gold Group, Inc., based in Toronto, Canada, is fully focused on
transitioning from an exploration/development company into a gold producer. In
conjunction with this objective, a full Feasibility Study is currently underway
for AGG's Kobada, Mali gold project. The Company is projecting the Feasibility
Study will be completed in Q4/2013, at which time, the Company will submit an
application to obtain an Exploitation License to the appropriate Malian
authorities.


Mineral resources that are not mineral reserves do not have demonstrated
economic viability. The preliminary assessment includes inferred mineral
resources that are considered too speculative geologically to have the economic
considerations applied to them that would enable them to be categorized as
mineral reserves, and there is no certainty that the preliminary assessment will
be realized.


Additional Information is available on the Company's website at
www.africangoldgroup.com and on www.sedar.com and through the Company's offices
at: Sun Life Financial Tower, Suite 2518, 150 King St. West, Toronto, Canada 

M5H 1J9.

On Behalf of the Board: 

Michael A. J. Nikiforuk, President, Director

FOR FURTHER INFORMATION PLEASE CONTACT: 
African Gold Group, Inc.
Michael A. J. Nikiforuk
(647) 288-0453
majn@africangoldgroup.com
www.africangoldgroup.com

African Gold (TSXV:AGG)
Gráfica de Acción Histórica
De May 2024 a Jun 2024 Haga Click aquí para más Gráficas African Gold.
African Gold (TSXV:AGG)
Gráfica de Acción Histórica
De Jun 2023 a Jun 2024 Haga Click aquí para más Gráficas African Gold.