Following the decision authorising the
commissioning of the Flamanville EPR by the French Nuclear Safety
Authority (ASN), EDF teams began to load the nuclear fuel
assemblies into the reactor vessel at 2pm on May 8, 2024.
The operation will last several days and 241
fuel assemblies will be loaded into the reactor vessel.
EDF will continue start-up, inspection and
testing operations over the next months, in close collaboration
with and under the supervision of
ASN.
Connection to the national grid is scheduled for
summer 2024.
About EDF The EDF Group is a
key player in the energy transition, as an integrated energy
operator engaged in all aspects of the energy business: power
generation, distribution, trading, energy sales and energy
services. The Group is a world leader in low-carbon energy, with a
low carbon output of 434TWh, a diverse generation mix based mainly
on nuclear and renewable energy (including hydropower). It is also
investing in new technologies to support the energy transition.
EDF’s raison d’être is to build a net zero energy future with
electricity and innovative solutions and services, to help save the
planet and drive well-being and economic development. The Group
supplies energy and services to approximately 40.9 million
customers (1) and generated consolidated sales of €139.7 billion in
2023.
(1) Customers are counted per delivery site. A
customer may have two delivery points.
- 2024-05-08-PR - EDF - Update on the Flamanville EPR
Electricite de France SA... (EU:EDFBP)
Gráfica de Acción Histórica
De Dic 2024 a Ene 2025
Electricite de France SA... (EU:EDFBP)
Gráfica de Acción Histórica
De Ene 2024 a Ene 2025