26 July 2024
QUARTERLY ACTIVITIES
REPORT
For the quarter ended 30 June
2024
88 Energy Limited (ASX:88E, AIM:88E,
OTC:EEENF) (88 Energy, 88E
or the Company) provides
the following report for the quarter ended 30 June
2024.
Highlights
Project Phoenix (~75% WI)
· Dual
success at the 2024 Hickory-1 flow test program. Upper Slope Fan
System (USFS) and Shelf
Margin Deltaic (SMD)
reservoirs both flowed light oil:
Ø USFS: produced at a peak flow
rate of over 70 barrels of oil per day
(bopd) of light
oil1;
Ø SMD: produced at a peak flow rate of ~50 bopd of light
oil2; and
Ø Quality
and deliverability of both reservoirs demonstrated via oil
production to surface with the USFS reservoir producing under
natural flow.
· Hickory-1 advancement activities are currently focused
on:
Ø Post-well
testing and analysis, expected to be completed in Q3
2024;
Ø Securing
an independent Contingent Resource for the SFS and SMD reservoirs,
based on the production of hydrocarbons to surface, targeting Q4
2024 delivery;
Ø Undertaking a formal farm-out process to attract a quality
partner to fund the next stage of the appraisal and development at
Project Phoenix; and
Ø Planning
and design for a potential horizontal flow test and early stage
production system.
· Successful outcomes from the Hickory-1 flow test delivered a
platform for monetisation of Project Phoenix, justifying further
advancement, with key benefits including:
Ø Potential
capital-light modular Early Production System;
Ø Expected
production from analagous long horizontal wells typically produce 6
to 12 times higher flow rates than vertical wells; and
Ø An ability
to produce concurrently from multiple reservoirs in a single
development scenario.
Project Leonis (100% WI)
· Maiden
prospective resource estimate for Upper Schrader Bluff (USB) of net mean 381 million barrels
of oil, completed in June 20243,4.
· Permitting and planning commenced for the newly named Tiri-1
exploration well, designed to test the Tiri prospect in the USB
formation.
· Farm-out process underway to secure a funding partner ahead of
potential drilling of the Tiri-1 well in 2026.
Namibia PEL 93 (20% WI)
· Fully
funded 2D seismic acquisition program completed in July 2024,
successfully acquiring 203-line km of 2D seismic data on time and
within budget.
· Data
processing is ongoing, both in the field and at Earth Signal
Processing in Calgary, with final interpretation expected by Q4
2024.
· Program outcomes are set to include:
Ø Validation
of up to 10 independent structural closures;
Ø Delivery
of a maiden certified Prospective Resource estimate; and
Ø Identification of future potential drilling locations
targeting the Damara play.
Project Longhorn (~65% WI)
· Four
planned workovers successfully completed in line with budget and
production underway:
Ø Delivered
increase in production from 328 BOE per day (average Q1 2024, ~62%
oil) to Q2 2024 average of 395 BOE per day (~63% oil), with
production for June averaging 456 BOE per day.
Ø Workover
production declines currently lower than initially
forecast.
· Company received June 2024 cash flow distribution of A$0.5M,
post-workover expenditure.
Corporate
·
Cash balance of A$7.9 million, with ~90% of
Hickory-1 flow test payments made and the remainder expected to be
paid in July 2024.
·
Successful oversubscribed share placement raising
A$9 million (after costs) to support the Hickory-1 flow test,
post-flow test studies, advancement and commercialisation
activities at Project Phoenix, exploration activities across
Namibia and Alaska (including permitting and planning for Project
Leonis' Tiri-1 exploration well) and farmout costs.
· Budget
for the forward twelve-month activity schedule fully funded for
delivery.
1. Refer announcement released
to ASX on 2 April 2024 for further details
2. Refer announcement released
to ASX on 15 April 2024 for further details
3. Refer announcement released
to ASX on 4 June 2024 for further details including cautionary
statement
4. Cautionary
Statement: The estimated quantities of
petroleum that may be potentially recovered by the application of a
future development project relate to undiscovered accumulations.
These estimates have both an associated risk of discovery and a
risk of development. Further exploration, appraisal and evaluation
are required to determine the existence of a significant quantity
of potentially recoverable hydrocarbons. 88E is not aware of any
new information or data that materially affects the information
included in the relevant market announcement and that all material
assumptions and technical parameters underpinning the estimates
continue to apply and have not materially
changed.
Project Phoenix (~75% WI)
Project Phoenix is an oil-bearing
conventional reservoir play identified during the drilling and
logging of Icewine-1 and Hickory-1 and adjacent offset drilling and
testing. Project Phoenix is strategically located on the Dalton
Highway with the Trans-Alaskan Pipeline System bisecting the
acreage.
The Hickory-1 discovery well was
drilled in February 2023 and flow tested the following Alaskan
winter season in Q1/Q2 2024. The testing operations focussed on the
two shallower primary targets, the SFS and SMD reservoirs. Of the
SFS series of reservoirs, the Upper SFS (USFS) reservoir was
targeted to be flow tested as it had not been previously tested,
whereas the Lower SFS has previously been flow tested and therefore
the producibility of that reservoir was confirmed on adjacent
acreage. The USFS was followed by a targeted testing of the SMD-B
reservoir. Each zone was independently isolated, stimulated and
flowed to surface using nitrogen lift to assist in an efficient
clean-up of the well.
Upper SFS (USFS) flow test results
The
USFS produced at a peak flow rate of ~70 bopd. Oil cuts increased
throughout the flow back period as the well cleaned up, reaching a
maximum of 15% oil cut. The Company expects that oil rates and cut
would have likely increased further had the test period been
extended. The well produced at an average oil flow rate of ~42 bopd
during the natural flow back period, with instantaneous rates
ranging from ~10-77 bopd and average rates increasing through the
test period.
Importantly, the USFS zone flowed
oil to surface under natural flow, with flow back from other
reservoirs in adjacent offset wells only producing under nitrogen
assisted lift.
Multiple oil samples were recovered
with measured oil gravities of 39.9 to 41.4 API (representing a
light crude oil). For full details of the USFS test results please
refer to the ASX announcement dated 2 April 2024.
SMD-B flow test results
The
SMD-B produced at a peak flow rate of ~50 bopd. Oil cuts varied
throughout the flow back period, reaching a maximum of 10% oil cut.
The well produced at an average oil cut of 4% following initial oil
to surface, with instantaneous rates observed during the 16-hour
period as the well continued to clean up. Unlike flow tests on
adjacent acreage where multiple gas lift mandrels and valves were
used in completions designs, and nitrogen was unloaded in the
tubing in stages up the well bore, Hickory-1 utilised a single gas
lift mandrel where nitrogen was introduced via one valve at the
deepest section. This is viewed as positive indication for future
potential rates and performance.
Multiple oil samples were recovered,
with measured oil gravities of 38.5 to 39.5 API, representing a
light crude oil.
Importantly, the SMD-B zone flowed
oil to surface with little to no measurable gas, representing a
production rate with a low gas to oil ratio. For full details in
relation to the SMD-B test results please refer to the ASX
announcement dated 15 April 2024.
Post-flow testing and next steps
Pressurised oil samples collected
during both the USFS and SMD tests were transported to laboratories
for further analysis. The analyses are expected to verify the
reservoir fluid characteristics.
Following completion of the lab
analyses, 88E will commission an Independent Contingent Resource
assessment for the Upper SFS, Lower SFS and SMD-B. This
assessment is expected to be completed in Q4 2024.
Results from the post-flow test
analyses will assist 88E in the optimisation and design of the next
phase of advancement at Project Phoenix. The Company, together with
its Project Phoenix Joint Venture partner, are currently assessing
locations for the drilling of a horizontal well, including the
Franklin Bluffs gravel pad location (previously utilised for the
Icewine 1 and 2 unconventional test wells), where a long-term flow
test of either the SFS or SMD reservoirs may be
undertaken.
The Company also plans to commence a
formal farmout process prior to the future drilling of a horizontal
well and development of the Project Phoenix acreage, with the
aim of attracting a strategic partner for the next stage of
commercialisation. The table is an indicative timeline for Project
Phoenix development;
Joint Venture Partner Update
JV Partner Burgundy Xploration, LLC
(Burgundy) paid its
outstanding 2023 cash calls and signed the flow test authorised for
expenditure (AFE) on 15 February 2024 as part of the standstill
agreement that was entered into at the end of 2023 with the
Company's 100%-owned subsidiary Accumulate Energy Alaska, Inc
(88E-Accumulate).
The standstill agreement allows Burgundy six (6) months to pay its
share of the AFE cost (~US$3m) by 15 August 2024
(flow test cash call). Burgundy will pay its share of the flow test cash call from
either (1) the proceeds of a public listing which Burgundy is
pursuing; (2) the proceeds of a private capital raise; or (3) if
Burgundy has not made payment for its flow test cash call by 15
August 2024, then Burgundy will be required to transfer 50% its
working interest in the Toolik River Unit (TRU) leases to
88E-Accumulate.
At the time of this announcement
Burgundy has paid contributions towards lease rentals in Q2 2024,
with the balance of funds due outstanding. The Company understands
Burgundy is in advanced stages of negotiations to secure funding
under options (1) and (2) noted above. Burgundy is aiming to secure
sufficient funding via its public listing to pay all outstanding
cash call amounts due to 88E-Accumulate, and to secure funds
sufficient to acquire an additional working interest in Project
Phoenix from 88 Energy and potentially Operatorship to take the
project to the next phase of activity which includes a planned
horizontal well test.
Burgundy understands that under the
current standstill agreement, if payment of the flow test cash call
is not made by15 August 2024, this will require Burgundy to
transfer to 88E-Accumulate 50% of Burgundy's working interest
Project Phoenix's Toolik River Unit leases.
The Company maintains its rights
under the joint operating agreement (JOA) should Burgundy not be
able to pay any future cash calls, including exercising the option
to require Burgundy to relinquish its working interests in Project
Phoenix and the Joint Venture.
Project Leonis (100% WI)
The
Company reported a maiden Prospective Resource net mean estimate of
381 million barrels (MMbbls) of recoverable oil in the
newly named Tiri Prospect (Upper Schrader Bluff Formation/USB) for
Project Leonis on 4 June 20241.
The initial total Prospective
Resource estimate follows a review period of an extensive data
suite that included 3D and 2D seismic data, well logs from Hemi
Springs Unit-3 and Hailstorm-1, as well as nearby wells adjacent to
the Project Leonis acreage, along with extensive petrophysical
analysis and mapping.
Importantly, the USB formation is
the same proven producing zone as nearby Polaris, Orion and West
Sak oil fields to the north-west.
These proven USB producers served as
important calibration points for the Leonis petrophysical model.
The Leonis USB prospect has been fully delineated and mapped
following a review of reprocessed 3D seismic data and a 3rd party
dedicated fault mapping study to assist in prospect
definition.
Project Leonis: Forward
Program
88
Energy has engaged Fairweather to assist in commencing the planning
and permitting for the newly named Tiri-1 exploration well. The
well will be designed to drill, log and test the Tiri Prospect in
the USB formation. The company intends to utilise the existing
gravel pad at the Hemi Springs Unit-3 well location, in order to
reduce costs.
Timing for the drilling of the
Tiri-1 exploration well is dependent on securing a successful
farm-out partner.
The Company has secured Stellar
Energy Advisors Limited (Stellar) in London to manage the
farm-out process, who have been engaged with multiple parties in
advancing the assessment of the farm-out opportunity. The process
remained ongoing at the end of the quarter.
1. Refer announcement released
to ASX on 4 June 2024 for further details including cautionary
statement
Namibia PEL 93 (20% WI)
In February 2024, the Company
announced a 20% WI transfer by operator Monitor Exploration Limited
(Monitor) to 88
Energy in relation to PEL 93
located in the Owambo Basin. Monitor holds 55% WI
with 25% shared across local entities, Legend Oil Namibia Pty Ltd
and NAMCOR.
Namibia has been identified as one
of the last remaining under-explored onshore frontier basins and
one of the world's most prospective new exploration zones. PEL 93
is more than 10 times larger in surface area than 88 Energy's
Alaskan portfolio and more than 70 times larger than Project
Phoenix.
Recent drilling results on nearby
acreage have highlighted the potential of a new and underexplored
conventional oil and gas play in the Damara Fold belt, referred to
as the Damara Play. Historical assessment utilised a combination of
techniques and interpretation of legacy data to identify the Owambo
Basin as having significant exploration potential. Monitor utilised
a range of geophysical and geochemical techniques to assess and
validate the significant potential of the acreage since award of
PEL 93 in 2018, identifying ten (10) independent structural
closures from airborne geophysical methods and partly verified
these using existing 2D seismic coverage.
In
May 2024, the Company announced that Polaris Natural Resources
Development Ltd (Polaris) was awarded the next stage for PEL 93, the 2D seismic
acquisition program contract. Polaris mobilised vibroseis units and
recording equipment to location in late June 2024 and successfully
acquired 203-line km of 2D seismic data in July 2024 with data
processing ongoing, both in-field and at Earth Signal Processing in
Calgary with final interpretation anticipated to be finalised in Q4
2024.
Results of the new 2D seismic
acquisition will be integrated with existing historical exploration
data to refine current prospect interpretation. Expected program
outcomes include:
Ø Validate
up to 10 independent structural closures.
Ø Maiden
certified prospective resource estimate.
Ø Identification of future potential drilling locations
targeting the Damara play.
Project Longhorn (~65% WI)
The Joint Venture
(Bighorn JV), which
comprises Longhorn Energy Investments LLC (LEI) a 100% wholly owned subsidiary of
88 Energy with 75% ownership and Lonestar I, LLC
(Lonestar or
Operator) with remaining
25% ownership, agreed to a development program that included five
(5) workovers in 1H 2024.
During the quarter, the Bighorn JV
successfully executed and commenced production from four of the
planned five workovers in line with Budget. The first workover
production commenced in mid-April, the second and third commenced
in mid-May and the fourth workover production began in the final
week of June 2024. Completion of the workovers increased production
from 328 BOE per day (average Q1 2024, ~62% oil) to Q2 2024 average
of 395 BOE per day (~63% oil), with production for June averaging
456 BOE per day. Workover declines are currently lower than
initially forecast. The final planned workover encountered a tubing
fish not recorded in the well file. The operator tried several
tools but could only clean out 75 feet of the anticipated 1,500
feet of the tubing fish recovered. The Joint Venture decided to
suspend operations and P&A the workover with sunk CAPEX capped
at A$0.5M compared to a budget of A$1.2M.
The Company received a cash flow
distribution of A$0.5M in June 2024 post-workover
expenditure.
Peregrine & Umiat (100% WI)
88 Energy was successful in
receiving a suspension for Project Peregrine on 1 December 2023 for
an initial period of 12 months due to the proposed new regulations
governing the management of surface resources in the National
Petroleum Reserve-A (NPR-A). On 25 June 2024, the Company applied
for suspension to Umiat Unit and leases on the same basis as
Project Peregrine suspension, requesting an initial 1-year
suspension that will be reviewed as required during which time 88
Energy will persist with the refinement of internal geological and
geophysical models/interpretation. If the suspension is approved,
it will also relieve 88 Energy of the obligation to pay Umiat lease
rentals during the suspension period of ~A$0.1 million due in
Q4.
Future exploration efforts in the
Peregrine/Umiat area are subject to a resolution in the current
consultation process concerning future regulations in the NPRA and
the Company securing a farm-out.
Corporate
On 24 April 2024, the Company
successfully completed an oversubscribed share placement to
domestic and international institutional and sophisticated
investors to raise gross A$9.9 million (approx. £5.23 million)
before costs (Placement).
3,291,974,839 new fully paid ordinary shares in the Company (the
New Ordinary Shares) were
issued at an issue price of A$0.003 (£0.0016) per New Ordinary
Share (the Issue Price).
The net proceeds augmented the Company's existing cash balance to
fund:
· Hickory-1 discovery well flow test operations at Project
Phoenix, post-well studies, securing a contingent resource for the
SFS and SMD reservoirs and other costs associated with
commercialising Project Phoenix;
· Exploration activities including lease rentals across Alaska
and Namibia acreage;
· Permit
and planning costs for Tiri-1 exploration well at Project Leonis;
and
· Farmout process to advance projects at Project Phoenix and
Project Leonis.
Euroz Hartleys Limited (Euroz Hartleys) acted as Sole Lead
Manager and Bookrunner to the Placement. Cavendish Capital Markets
Ltd (Cavendish) acted as
Nominated Adviser and Sole Broker to the Placement in the United
Kingdom. Inyati Capital Pty Ltd (Inyati) acted as Co-Manager to the
Placement. Commission for the Placement was 6% (plus GST) of total
funds raised across Euroz Hartleys, Inyati and Cavendish. In
addition, and subject to shareholder approval, the Company will
issue a total of 75,000,000 Unlisted Options (exercisable at
A$0.0055 on or before the date which is 3 years from the date of
issue) to Euroz Hartleys, Cavendish and Inyati.
During the quarter, Monitor agreed
to receive 88 Energy shares as settlement for the fourth and final
Stage 1 instalment of the farm-in agreement, as announced to the
ASX on 13 November 2023. This instalment covers the remaining back
costs and the 2024 work program carry of US$0.92 million through
the issuance of 476,634,546 new ordinary 88 Energy Shares (at a
deemed issue price of A$0.003 per share).
The New Ordinary Shares were issued
under the Company's available placement capacity pursuant to
Listing Rule 7.1 and are not subject to shareholder approval. The
Ordinary Shares ranked pari passu with the existing ordinary shares
in the Company and the Ordinary Shares were admitted to trading on
AIM. Following the issue of the New Ordinary Shares pursuant to the
Placement and the final stage 1 shares issued to Monitor, the
Company had 28,892,671,952 ordinary shares on issue, all of which
have voting rights.
The Company held its Annual General
Meeting on 13 May 2024 and all six (6) resolutions were
carried.
Finance
As at 30 June 2024, the Company's
cash balance was A$7.9M.
The ASX Appendix 5B attached to this
quarterly report contains the Company's cash flow statement for the
quarter. The material cash flows for the period were:
· Exploration and evaluation expenditure of A$17.3M (March 2024
quarter: A$3.9M) predominantly related to paying for ~70% of the
Hickory-1 flow test program in Q2. Approximately 90% of Hickory-1
flow test payments have now been made, with the remainder expected
to be paid in July 2024.
· Administration, staff, and other costs of A$1.1M (March 2024
quarter: A$0.8M) which including fees paid to Directors and
consulting fees paid to Directors of A$0.2M. Net of one off annual
costs of ~A$0.3M which included corporate insurance, audit and
taxation services across 88 Energy Group, general and
administration costs were in line with the prior quarter.
· Additional cost reductions identified and implemented across
corporate overheads, including reductions in salary costs, with the
Company already realising the benefits of these reductions in 1H
2024 (HY'24 totalled A$1.91M compared to HY'23 totalled A$2.94M - a
saving of A$1.03M).
Information required by ASX Listing Rule
5.4.3
Project Name
|
Location
|
Net
Area (acres)
|
Interest at beginning of
Quarter
|
Interest at end of
Quarter
|
|
|
|
Phoenix2
|
Onshore, North Slope
Alaska
|
44,562
|
~75%
|
~75%
|
Icewine West2
|
Onshore, North Slope
Alaska
|
83,611
|
~75%
|
~75%
|
Peregrine1
|
Onshore, North Slope Alaska
(NPR-A)
|
125,735
|
100%
|
100%
|
Longhorn
|
Onshore, Permian Basin
Texas
|
2,830
|
~65%
|
~65%
|
Leonis
|
Onshore, North Slope
Alaska
|
25,431
|
100%
|
100%
|
Umiat
|
Onshore, North Slope Alaska
(NPR-A)
|
17,633
|
100%
|
100%
|
PEL 93
|
Onshore, Owambo Basin,
Namibia
|
914,270
|
20%
|
20%
|
1. Refer announcement released
to ASX on 21 December 2023 regarding Project Peregrine 12-month
suspension until 30 November 2024
2. Acreage that was deemed
non-core to 88 Energy was relinquished during the quarter,
providing a reduction in lease costs from a focused strategy that
unlocks value from key acreage positions with strategic locations,
as announced to the ASX on 4 June 2024
Pursuant to the requirements of the
ASX Listing Rules Chapter 5 and the AIM Rules for Companies, the
technical information and resource reporting contained in this
announcement was prepared by, or under the supervision of, Dr
Stephen Staley, who is a Non-Executive Director of the Company. Dr
Staley has more than 40 years' experience in the petroleum
industry, is a Fellow of the Geological Society of London, and a
qualified Geologist / Geophysicist who has sufficient experience
that is relevant to the style and nature of the oil prospects under
consideration and to the activities discussed in this document. Dr
Staley has reviewed the information and supporting documentation
referred to in this announcement and considers the prospective
resource estimates to be fairly represented and consents to its
release in the form and context in which it appears. His academic
qualifications and industry memberships appear on the Company's
website, and both comply with the criteria for "Competence" under
clause 3.1 of the Valmin Code 2015. Terminology and standards
adopted by the Society of Petroleum Engineers "Petroleum Resources
Management System" have been applied in producing this
document.
This announcement has been authorised by the
Board.
Media and Investor Relations:
88
Energy Ltd
Ashley Gilbert, Managing
Director
Tel: +61 (0)8 9485 0990
Email:investor-relations@88energy.com
|
|
|
|
Fivemark Partners, Investor and
Media Relations
|
|
Michael Vaughan
|
Tel: +61 (0)422 602 720
|
|
|
EurozHartleys Ltd
|
|
Dale Bryan
|
Tel: +61 (0)8 9268 2829
|
|
|
Cavendish Capital Markets Limited
|
Tel: +44 (0)207 220 0500
|
Derrick Lee
|
Tel: +44 (0)131 220 6939
|
Pearl Kellie
|
Tel: +44 (0)131 220 9775
|
|
|
Information required by ASX Listing Rule 5.4.3 - Lease
Schedules as at 30 June 2024
Appendix 5B
Mining exploration entity or oil
and gas exploration entity
quarterly cash flow report
Name of entity
|
88 Energy Limited
|
ABN
|
|
Quarter ended ("current
quarter")
|
80 072 964 179
|
|
30 June 2024
|
Consolidated statement of cash flows
|
Current quarter
$A'000
|
Year
to date (6 months)
$A'000
|
|
1.
|
Cash
flows from operating activities
|
-
|
-
|
|
1.1
|
Receipts from customers
|
|
1.2
|
Payments for
|
-
|
-
|
|
|
(a) exploration &
evaluation
|
|
|
(b) development
|
-
|
-
|
|
|
(c) production
|
-
|
-
|
|
|
(d) staff costs
|
(430)
|
(829)
|
|
|
(e) administration and
corporate costs
|
(751)
|
(1,157)
|
|
1.3
|
Dividends received (see
note 3)
|
-
|
-
|
|
1.4
|
Interest received
|
39
|
76
|
|
1.5
|
Interest and other costs of finance
paid
|
-
|
-
|
|
1.6
|
Income taxes paid
|
-
|
-
|
|
1.7
|
Government grants and tax
incentives
|
-
|
-
|
|
1.8
|
Other
|
-
|
-
|
|
1.9
|
Net
cash from / (used in) operating activities
|
(1,142)
|
(1,910)
|
|
|
|
2.
|
Cash
flows from investing activities
|
-
|
-
|
|
2.1
|
Payments to acquire or
for:
|
|
|
(a)
entities
|
|
|
(b)
tenements
|
(818)
|
(971)
|
|
|
(c)
property, plant and equipment
|
-
|
-
|
|
|
(d)
exploration & evaluation
|
(17,303)
|
(21,154)
|
|
|
(e)
investments
|
-
|
-
|
|
|
(f)
other non-current assets
|
-
|
-
|
|
2.2
|
Proceeds from the disposal
of:
|
-
|
-
|
|
|
(a)
entities
|
|
|
(b)
tenements
|
-
|
-
|
|
|
(c)
property, plant and equipment
|
-
|
-
|
|
|
(d)
investments
|
-
|
-
|
|
|
(e) other
non-current assets
|
-
|
-
|
|
2.3
|
Cash flows from loans to other
entities
|
-
|
-
|
|
2.4
|
Dividends received (see
note 3)
|
-
|
-
|
|
2.5
|
Other - Joint Venture
Contributions
Other - Distribution from Project
Longhorn
Other - Return of Bond
|
107
512
-
|
2,981
1,227
-
|
|
2.6
|
Net
cash from / (used in) investing activities
|
(17,502)
|
(17,917)
|
|
|
|
3.
|
Cash
flows from financing activities
|
9,696
|
9,696
|
|
3.1
|
Proceeds from issues of equity
securities (excluding convertible debt securities)
|
|
3.2
|
Proceeds from issue of convertible
debt securities
|
-
|
-
|
|
3.3
|
Proceeds from exercise of
options
|
-
|
-
|
|
3.4
|
Transaction costs related to issues
of equity securities or convertible debt securities
|
(670)
|
(670)
|
|
3.5
|
Proceeds from borrowings
|
-
|
-
|
|
3.6
|
Repayment of borrowings
|
-
|
-
|
|
3.7
|
Transaction costs related to loans
and borrowings
|
-
|
-
|
|
3.8
|
Dividends paid
|
-
|
-
|
|
3.9
|
Other (provide details if
material)
|
-
|
-
|
|
3.10
|
Net
cash from / (used in) financing activities
|
9,026
|
9,026
|
|
|
|
4.
|
Net
increase / (decrease) in cash and cash equivalents for the
period
|
|
|
|
4.1
|
Cash and cash equivalents at
beginning of period
|
17,502
|
18,183
|
|
4.2
|
Net cash from / (used in) operating
activities (item 1.9 above)
|
(1,142)
|
(1,910)
|
|
4.3
|
Net cash from / (used in) investing
activities (item 2.6 above)
|
(17,502)
|
(17,917)
|
|
4.4
|
Net cash from / (used in) financing
activities (item 3.10 above)
|
9,026
|
9,026
|
|
4.5
|
Effect of movement in exchange rates
on cash held
|
(2)
|
500
|
|
4.6
|
Cash
and cash equivalents at end of period
|
7,882
|
7,882
|
|
5.
|
Reconciliation of cash and cash equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the related items in the
accounts
|
Current quarter
$A'000
|
Previous quarter
$A'000
|
5.1
|
Bank balances
|
7,882
|
17,502
|
5.2
|
Call deposits
|
-
|
-
|
5.3
|
Bank overdrafts
|
-
|
-
|
5.4
|
Other (provide details)
|
-
|
-
|
5.5
|
Cash
and cash equivalents at end of quarter (should equal item 4.6
above)
|
7,882
|
17,502
|
6.
|
Payments to related parties of the entity and their
associates
|
Current quarter
$A'000
|
6.1
|
Aggregate amount of payments to
related parties and their associates included in
item 1
|
205
|
6.2
|
Aggregate amount of payments to
related parties and their associates included in
item 2
|
-
|
Note: if any amounts are shown in items 6.1 or 6.2, your
quarterly activity report must include a description of, and an
explanation for, such payments.
|
6.1 Payments relate to
remuneration and consulting fees paid to Directors. All
transactions involving directors and associates were on normal
commercial terms.
7.
|
Financing facilities
Note: the term "facility'
includes all forms of financing arrangements available to the
entity.
Add
notes as necessary for an understanding of the sources of finance
available to the entity.
|
Total facility amount at quarter end
$US'000
|
Amount drawn at quarter end
$US'000
|
7.1
|
Loan facilities
|
-
|
-
|
7.2
|
Credit standby
arrangements
|
-
|
-
|
7.3
|
Other (please specify)
|
-
|
-
|
7.4
|
Total financing facilities
|
-
|
-
|
|
|
|
7.5
|
Unused financing facilities available at quarter
end
|
-
|
7.6
|
Include in the box below a
description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any
additional financing facilities have been entered into or are
proposed to be entered into after quarter end, include a note
providing details of those facilities as well.
|
|
8.
|
Estimated cash available for future operating
activities
|
$A'000
|
8.1
|
Net cash from / (used in) operating
activities (item 1.9)
|
(1,142)
|
8.2
|
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
|
(17,303)
|
8.3
|
Total relevant outgoings
(item 8.1 + item 8.2)
|
(18,445)
|
8.4
|
Cash and cash equivalents at quarter
end (item 4.6)
|
7,882
|
8.5
|
Unused finance facilities available
at quarter end (item 7.5)
|
-
|
8.6
|
Total available funding
(item 8.4 + item 8.5)
|
7,882
|
|
|
|
8.7
|
Estimated quarters of funding available (item 8.6 divided
by item 8.3)
|
0.4
|
Note: if the entity has reported positive relevant outgoings
(ie a net cash inflow) in item 8.3, answer item 8.7 as
"N/A". Otherwise, a figure for the estimated quarters of funding
available must be included in item 8.7.
|
8.8
|
If item 8.7 is less than
2 quarters, please provide answers to the following
questions:
|
|
8.8.1
Does the entity expect that it will continue to have the current
level of net operating cash flows for the time being and, if not,
why not?
|
|
Answer:
The total outgoings are higher in Q2
due to final payments associated with the Hickory flow test
program. There is approximately A$1.5 million to pay in Q3. The
entity does not therefore expect the same level of outgoings in Q3
and Q4 and has 9.7 quarters of funding available based upon the
current activity schedule.
|
|
8.8.2
Has the entity taken any steps, or does it propose to take any
steps, to raise further cash to fund its operations and, if so,
what are those steps and how likely does it believe that they will
be successful?
|
|
Answer:
Based on anticipated expenditure
under the current activity schedule and cash distributions from
Project Longhorn, the entity anticipates being funded for 9.7
quarters. If the planned activity schedule should change, then the
entity will take steps to obtain additional funding.
|
|
8.8.3
Does the entity expect to be able to continue its operations and to
meet its business objectives and, if so, on what basis?
|
|
Answer:
Based on anticipated expenditure
under the current activity schedule and cash distributions from
Project Longhorn, the entity anticipates being funded for 9.7
quarters
|
|
Note: where item 8.7 is less than 2 quarters, all of
questions 8.8.1, 8.8.2 and 8.8.3 above must be
answered.
|
Compliance statement
1
This statement has been prepared in accordance with accounting
standards and policies which comply with Listing
Rule 19.11A.
2
This statement gives a true and fair view of the matters
disclosed.
Date:
26 July 2024
Authorised
by: By the Board
(Name of body or officer authorising
release - see note 4)
Notes
1. This quarterly cash flow report
and the accompanying activity report provide a basis for informing
the market about the entity's activities for the past quarter, how
they have been financed and the effect this has had on its cash
position. An entity that wishes to disclose additional information
over and above the minimum required under the Listing Rules is
encouraged to do so.
2. If this quarterly cash flow
report has been prepared in accordance with Australian Accounting
Standards, the definitions in, and provisions of, AASB 6:
Exploration for and Evaluation of Mineral Resources and AASB 107:
Statement of Cash Flows apply to this report. If this quarterly
cash flow report has been prepared in accordance with other
accounting standards agreed by ASX pursuant to Listing
Rule 19.11A, the corresponding equivalent standards apply to
this report.
3. Dividends received may be
classified either as cash flows from operating activities or cash
flows from investing activities, depending on the accounting policy
of the entity.
4. If this report has been
authorised for release to the market by your board of directors,
you can insert here: "By the board". If it has been authorised for
release to the market by a committee of your board of directors,
you can insert here: "By the [name of board committee - eg Audit
and Risk Committee]". If it has been authorised for release to the
market by a disclosure committee, you can insert here: "By the
Disclosure Committee".
5. If this report has been
authorised for release to the market by your board of directors and
you wish to hold yourself out as complying with
recommendation 4.2 of the ASX Corporate Governance Council's
Corporate Governance Principles and Recommendations, the board
should have received a declaration from its CEO and CFO that, in
their opinion, the financial records of the entity have been
properly maintained, that this report complies with the appropriate
accounting standards and gives a true and fair view of the cash
flows of the entity, and that their opinion has been formed on the
basis of a sound system of risk management and internal control
which is operating effectively.