Cadence
Minerals Plc
("Cadence
Minerals", "Cadence", or "the Company")
European
Metals Holdings- Cinovec Lithium Project
Update
Cadence Minerals (AIM: KDNC) is
pleased to note the announcement by European Metals Holdings Limited (ASX &
AIM: EMH) ("European
Metals" or the
"Company
regarding the Cinovec Lithium Project (Cinovec).
EMH advises that the timeline for the completion of the Definitive
Feasibility Study ("DFS") and therefore construction of the Cinovec lithium
processing plant continue to be worked on.
Given the change to the location of
the lithium processing plant from Dukla to Prunéřov, additional
geotechnical work is currently underway to confirm the optimal
construction method and layout at the new site. Results from this
geotechnical work are expected to be available at the end of
September. DRA Global is then expected to provide a detailed
timeline and begin the DFS finalisation program of work.
EMH will provide a further update to
the market once it has received a revised timeline for completion
of the DFS.
The Project team continues to
progress several DFS-related programs on the Front-End Comminution
and Beneficiation circuit ("FECAB") and Lithium Chemical
Plant circuit ("LCP") to improve the overall flowsheet which are expected to
positively impact Project economics.
Process Flowsheet Improvements - FECAB
EMH previously announced changes to
the FECAB process flowsheet from beneficiation based entirely on
magnetic separation to a process incorporating both magnetic
separation and flotation. This improvement yielded a total FECAB
lithium recovery of >87%, with 7-8% lost to the fines fraction
and the balance of 5-6% losses due to process inefficiency. By
mass, the proportion of the ore recovered to concentrate achieved
was 30% of the total feed and the grade of the concentrate entering
the LCP was 1.198% lithium (2.58% Li2O).
To improve FECAB performance,
targeting a higher-grade concentrate, additional flotation testwork
has been carried out. Representative ore samples were utilised,
milled to P80<150μm and tested without removing the <20μm
slimes fraction before flotation.
Results, benefits and impacts of
this testwork are:
· Potential for complete elimination of the magnetic separation
step from the FECAB flowsheet;
· Flotation process without desliming has been successfully
optimised, which improves the recovery of zinnwaldite from the
<20μm fraction whilst not impacting reagent consumption or other
process beneficiation performance factors;
· A
capability to deliver overall FECAB lithium recovery improvements
from >87% to >94.7%, proven on a repeated basis;
· Uplift
in concentrate grade from 1.198% Li (2.58% Li2O) to
produce almost pure zinnwaldite concentrate with average grade of
1.46% Li (3.14% Li2O);
· The
grades of concentrate produced in the flotation testwork are the
highest to date, based on the recoveries achieved and mass
rejection (of gangue) of 80% on average;
· The
flotation testwork program was carried out at neutral pH and there
was no need for chemical addition to adjust pH;
· The
above results are from repeated locked cycle testwork;
· The
locked cycle testwork achieved optimisation of recirculation in the
flotation circuit, such that the final circuit contained only a
single recirculation stream;
· The
improved lithium grade and purity of concentrate recovered are
expected to significantly impact both the operating costs per tonne
("Opex/t") of battery-grade
end-product as well as the capital expenditure per tonne
("Capex/t") for the
LCP;
· The
results of this recent testwork have translated into impacts on the
DFS which include re-sizing of kilns for roasting the concentrate
and reagent and energy consumption reductions for the same overall
process outputs, with the intensive magnetic separation plant
Capex/t and Opex/t eliminated;
· Expected economic improvements include a reduction in roasting
reagents (gypsum, limestone and sodium sulphate) required for the
same output;
· The
purity of the flotation concentrate achieved further supports
production of exceptionally clean battery-grade end products for
Cinovec;
· A
flotation-only process simplifies the FECAB operationally (in
addition to reducing Capex/t and Opex/t);
· The
measured Particle Size Distribution ("PSD") of the flotation concentrate is
close to the ideal PSD for kiln feed. As a result, the need
for a concentrate regrind mill currently in the process flowsheet
is being re-assessed.
The flotation testwork has yielded
excellent results and the Project team is now considering the full
ramifications in bulk materials handling, tailings storage and
backfilling, should a positive decision be made to change the FECAB
process flowsheet to 100% flotation beneficiation. EMH will provide
an update when a decision has been made.
Process Flowsheet Improvements - Lithium Chemical
Plant
The principal roasting reagents
mixed with lithium-bearing ore (zinnwaldite) concentrate, as stated
above, are gypsum, limestone and sodium sulphate. The LCP process
produces a waste stream of mixed sulphate, including sodium
sulphate, potassium sulphate, rubidium sulphate, with a residual
component of lithium sulphate derived from lithium which is not
converted into lithium phosphate during its first pass through the
lithium phosphate reactor tank.
EMH has recently managed locked
cycle tests that demonstrate the effects of replacing sodium
sulphate roasting reagent entirely with the mixed sulphate waste
stream, targeting reduced overall reagent consumption.
Nine locked cycles were performed
with fully-representative zinnwaldite concentrate roasted in each
test. This testwork was undertaken at Nagrom Laboratories in Perth,
WA.
These tests have been successful,
with the overall lithium recovery in the LCP circuit remaining in
the previously announced range of 88-93%.
The recycling of this mixed sulphate
waste stream is a key component of the patent pending for the
Cinovec LCP process.
The benefits and impacts of this
optimisation testwork of the LCP circuit are:
· Elimination of sodium sulphate as a roasting reagent, reducing
Opex/t for the project;
· Lithium not recovered in its first pass through the lithium
phosphate reactor tank circuit is reprocessed, enabling higher
overall lithium recovery. Modelling, based on the results of cycles
5 and 6 of the 2022 Locked Cycle Test program assuming fresh, pure
(>98%) sodium sulphate addition upfront, estimates the amount of
lithium lost to the mixed sulphate waste stream as 1.2%. This is
now available for recovery in the revised LCP circuit design;
and
· Reduction in the overall mixed sulphate waste stream required
to be onwards-treated has been achieved, further reducing Opex/t of
the end-product.
The updated LCP circuit design with
recycling of mixed sulphate into the roast mix results in recycling
of approximately 50% of the total mixed sulphate produced. The
remaining mixed sulphate will be reprocessed as waste.
Land Acquisition at Dukla Transport Hub
Geomet s.r.o., the Cinovec Project
holding company, has acquired the land and buildings of the disused
Lesní Brana railway station, proximate to the proposed Dukla
transport hub. This site is expected to be cleared and used for the
control room for rail operations in and out of the Dukla transport
hub, which will handle run-of-mine crushed ore (<70mm) onto
trains for transport to the Prunéřov lithium processing plant site
and, in the reverse direction, handle backfill material to then be
transported by conveyor to the mine portal area for use as mine
backfill.
The DFS continues to work towards
optimising and maximising the planned mine production and ore
transfer by rail to the change of Cinovec processing plant site
away from Dukla to Prunéřov. This has enabled the Project team to
review maximising the mine outputs and ore transfer by rail
utilising only a small proportion of the area available at Dukla
and not disturbing existing industrial users at Dukla. This
optimisation is not expected to result in an increase in the rail
fleet as reagent deliveries are no longer required at the Dukla
site.
Just Transition Fund
Representatives of Geomet met with
the Regional Standing Conference ("RSK"), in the Czech Republic
which is one of the bodies that approves and recommends Just
Transition Fund ("JTF") support,
Geomet has submitted an initial
application for funding of a part of the project (called a
"sub-project"), which initially included the preliminary mine
portal area works - a box-cut (mine entrance), an exploration adit,
work on a portal access road. These construction works are able to
take place under the existing exploration licenses and not
requiring an Environmental Impact Assessment ("EIA"). The total initial grant
requested from the JTF has in turn been reduced from CZK 1.12
billion to CZK 0.8 billion (approximately EUR 31
million).
The RSK meeting has recommended the
sub-project for JTF support. The next step will be the final
funding approval by the Ministry of Environment.
Link
here to view the full EMH
announcement
Cinovec Lithium/Tin Project
Geomet s.r.o. controls the mineral
exploration licenses awarded by the Czech State over the Cinovec
Lithium/Tin Project. Geomet has been granted a preliminary mining
permit by the Ministry of Environment and the Ministry of Industry.
The company is owned 49% by EMH and 51% by CEZ a.s. through its
wholly owned subsidiary, SDAS. Cinovec hosts a globally significant
hard rock lithium deposit with a total Measured Mineral Resource of
53.3Mt at 0.48% Li2O and 0.08% Sn, Indicated Mineral Resource of
360.2Mt at 0.44% Li2O and 0.05% Sn and an Inferred Mineral Resource
of 294.7Mt at 0.39% Li2O and 0.05% Sn containing a combined 7.39
million tonnes Lithium Carbonate Equivalent and 335.1kt of
tin.
Cadence Minerals holds approximately
2.52% per cent of the equity in European Metals
Holdings.
For further information
contact:
|
|
Cadence Minerals plc
|
+44
(0) 20 3582 6636
|
Andrew Suckling
|
|
Kiran Morzaria
|
|
|
|
Zeus Capital Limited (NOMAD & Broker)
|
+44
(0) 20 3829 5000
|
James Joyce
|
|
Darshan Patel
Isaac Hooper
|
|
|
|
Fortified Securities - Joint Broker
|
+44
(0) 20 3411 7773
|
Guy Wheatley
|
|
|
|
Brand Communications
|
+44
(0) 7976 431608
|
Public & Investor
Relations
|
|
Alan Green
|
|
Qualified Person
Kiran Morzaria B.Eng. (ACSM), MBA,
has reviewed and approved the information contained in this
announcement. Kiran holds a Bachelor of Engineering (Industrial
Geology) from the Camborne School of Mines and an MBA (Finance)
from CASS Business School.
Cautionary and
Forward-Looking Statements
Certain statements in this
announcement are or may be deemed to be forward-looking statements.
Forward-looking statements are identified by their use of terms and
phrases such as "believe", "could", "should", "envisage",
"estimate", "intend", "may", "plan", "will", or the negative of
those variations or comparable expressions
including references to assumptions. These forward-looking
statements are not based on historical facts but rather on the
Directors' current expectations and assumptions regarding the
company's future growth results of operations
performance, future
capital, and other expenditures (including the
amount, nature, and sources of funding thereof) competitive
advantages business prospects and opportunities. Such
forward-looking statements reflect the Directors' current beliefs
and assumptions and are based on information currently available to
the Directors. Many factors could cause actual results to
differ materially from the results discussed in the forward-looking
statements, including risks associated with vulnerability to
general economic and business conditions, competition,
environmental and other regulatory changes actions by governmental
authorities, the availability of capital markets reliance on key
personnel uninsured and underinsured losses and other factors many
of which are beyond the control of the company. Although any
forward-looking statements contained in this announcement are based
upon what the Directors believe to be reasonable assumptions. The
company cannot assure investors that actual results will be
consistent with such forward-looking statements.
The
information contained within this announcement is deemed by the
company to constitute Inside Information as stipulated under the
Market Abuse Regulation (E.U.) No. 596/2014, as it forms part of
U.K. domestic law under the European Union (Withdrawal) Act 2018,
as amended. Upon the publication of this announcement via a
regulatory information service, this information is considered to
be in the public domain.