Sutter Gold Mining Inc. Provides Project Update and Announces It Will Temporarily Suspend Operations at Lincoln Mine Project
04 Marzo 2014 - 4:00PM
Marketwired
Sutter Gold Mining Inc. Provides Project Update and Announces It
Will Temporarily Suspend Operations at Lincoln Mine Project
VANCOUVER, BRITISH COLUMBIA--(Marketwired - Mar 4, 2014) -
Sutter Gold Mining Inc. (TSX-VENTURE:SGM) (OTCQX:SGMNF) ("Sutter or
the "Company") provides the following update on the completion of
current work programs announced December 23, 2013 with respect to
development in the underground and mill at the Lincoln Project in
Sutter Creek, California.
Underground Development
All objectives of the previously announced underground
development program have been completed. Additional development
completed allows for the initiation of production mining from stope
panels between the 900 and 1000 levels and between the 1030 and
1100 levels. This included establishing new secondary egress raises
to allow for commencement of production from the initial stope
panels, the establishment of ore passes to service the initial
stope panel on the 1030 level and stope preparation for mining on
the 1030 level. In addition, work was been completed on a detailed
mine plan for the initial 12 to 18 months of production from the
Comet deposit. The Company is now in the process of costing and
optimizing the detailed mine plane in relation to both selective
underhand cut and fill mining as well as mechanized cut and fill
and/or long hole open stoping methods. This work has put the mine
in a position to be able to initiate production mining as further
development continues.
Mill
Approximately 1,000 tons of stockpiled material from development
has been processed through the mill. Several bottlenecks in the
plant were identified and corrected however weakness in the design
and installation of the plant thickener resulted in its failure and
precluded achievement of the planned processing of the full 3,500
tons of stockpiles. The inability to dewater tailings necessitated
the suspension of milling operations at the end of February.
Limited operation of the mill is planned for the purpose of
collecting the samples required for mass and metallurgical
balances, fines management and tailings characterization for
backfill design. Following a review of the processing operations by
the Company the following items will be required to be addressed in
order for the mill to achieve sustained operations:
- Replacement of the thickener and determination of appropriate
approach to dewatering whole tailings;
- Determination of appropriate process sampling equipment and
instrumentation, purchase and installation;
- Relocation of the existing jaw crusher to allow for service and
sustained operations and installation of a secondary cone crusher
to provide a consistent and appropriate feed to the rod mill;
- Construction of a gold room capable of producing dore on-site,
completion of the gravity circuit, new furnace and associated
items;
- Improved ventilation system for the lab and new ventilation for
the gold room; and
- Design and installation of a backfill plant.
It is estimated that in order to correct these issues that an
additional investment of $1.1 to $1.2 million will be required in
order put the mill in a position to operate on a sustained basis at
planned production rates. Positively, the ability to produce gold
dore has been confirmed from the processing of gravity concentrates
at a local mill, which will be taken into account in completing the
gravity circuit. The processing of stockpiles and production of
both gravity and flotation concentrate has demonstrated total gold
recoveries in line with prior metallurgical test work.
Current Status and Planned Work
Given completion of the planned underground development and the
inability to continue processing stockpiles as planned, the
decision has been made to place the Project on care and maintenance
to conserve resources. As a result, the mining contractor has been
demobilized and non-essential personnel, principally mill labor,
have been laid off. A work program is being finalized for
recommendation and will require approval by the Company's Lender,
RMB Australia Holdings Limited, for continued funding. This program
anticipates continuing work to complete an optimized mine plan for
the initial 12 to 18 months of production from the Comet deposit
and update of the life of mine plan as appropriate. It is planned
that once completed the mine plan will be provided for independent
review and input by a third party engineer. Likewise with the mill,
it will be recommended that a third party review be undertaken of
the Company's assessment and costing of the remaining elements
required to achieve production ready status. Completion of this
work will position the Project to move to commercial production
pending additional funding.
Rick Winters, interim President and CEO, commented, "It is
unfortunate that despite our best efforts we could not overcome the
design and installation issues that resulted in the failure to
achieve our objective of processing all our stockpiles and
completing the mill commissioning. There is no sense operating the
mill and incurring additional costs until we have addressed the
issues we know preclude efficient commercial processing. This is
even more disappointing in respect of the positive work achieved
underground, the well behaved nature of the orebody with further
development and the positioning of the mine for initial production
mining as development continues. The work program we will propose
to our Lender, we believe, will define to a high degree of
confidence what is needed to put the Project into production. We
are all but there and will continue to pursue all alternatives to
obtain the funding that will be needed to achieve that end."
About Sutter
Sutter has two projects: the Lincoln Project located in Amador
County, on the California Mother Lode Gold Belt, and the Santa
Theresa Project located in the Northern Baja region of Mexico. The
Company has been focused on the mill construction and underground
development of the Lincoln Mine Project, beginning with the shallow
portion of the Lincoln-Comet ore zone. The Lincoln-Comet and
Keystone zones have a NI 43-101 compliant Indicated Resource
estimate (completed in February 2008). Sutter currently controls
approximately 3.6 miles of the Mother Lode of Amador County, with
90% of the property still unexplored.
In Mexico, Sutter holds the rights to the geologically similar,
high-grade El Alamo district of northern Baja.
Forward-Looking Statements
This news release contains "forward-looking information"
under Canadian securities law. Any information that express or
involve discussions with respect to predictions, expectations,
beliefs, plans, projections, objectives, assumptions or future
events or performance (often, but not always, using words such as
"expect", "anticipate", "believe", "plans", "estimate",
"scheduling", "projected" or variations thereof or stating that
certain actions, events or results "may", "could", "would", "might"
or "will" be taken, occur or be achieved, or the negative of any of
these terms and similar expressions) are not statements of
historical fact and may be forward-looking information.
Forward-looking information relates to, among other things:
repayment schedule of SSTFL; use of proceeds; benefits of
restructuring; and; future financial and operating performance
including estimates of the Company's revenues and capital
expenditures and estimated production.
Forward-looking information is subject to a variety of known
and unknown risks, uncertainties and other factors that could cause
actual events or results to differ from those reflected in the
forward-looking information, including, without limitation, risks
relating to: fluctuating commodity prices; calculation of
resources, reserves and mineralization and precious and base metal
recovery; interpretations and assumptions of mineral resource and
mineral reserve estimates; exploration and development programs;
feasibility and engineering reports; permits and licenses; title to
properties; recent market events and conditions; economic factors
affecting the Company; timing, estimated amount, capital and
operating expenditures and economic returns of future production;
operations and political conditions; environmental risks; and risks
and hazards of mining operations. This list is not exhaustive of
the factors that may affect any of the Company's forward-looking
information. Forward-looking information about the future is
inherently uncertain, and actual achievements of the Company or
other future events or conditions may differ materially from those
reflected in the forward-looking information due to a variety of
risks, uncertainties and other factors. Although the Company has
attempted to identify important factors that could cause actual
results to differ materially, there may be other factors that cause
results not to be as anticipated, estimated, described or intended.
Accordingly, readers should not place undue reliance on
forward-looking statements or information. The Company's
forward-looking information is based on the assumptions, beliefs,
expectations and opinions of management as of the date of this
press release, and other than as required by applicable securities
laws, the Company does not assume any obligation to update
forward-looking statements and information if circumstances or
management's assumptions, beliefs, expectations or opinions should
change, or changes in any other events affecting such statements or
information. For the reasons set forth above, investors should not
place undue reliance on forward-looking information.
Neither the TSX Venture Exchange nor its Regulation Services
Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release.
Sutter Gold Mining Inc.Robert HutmacherChief Financial
Officer303 238 1438 ext.
22bhutmacher@suttergoldmining.comwww.suttergoldmining.com
Sutter Gold Mining (CE) (USOTC:SGMNF)
Gráfica de Acción Histórica
De Oct 2024 a Nov 2024
Sutter Gold Mining (CE) (USOTC:SGMNF)
Gráfica de Acción Histórica
De Nov 2023 a Nov 2024