May 9, 2024
NEWS RELEASE
LUCARA ANNOUNCES Q1 2024 RESULTS;
PROGRESS ON UNDERGROUND EXPANSION
VANCOUVER, May 9, 2024 /CNW/ (LUC -
TSX, LUC - BSE, LUC - Nasdaq Stockholm)
Lucara Diamond Corp. ("Lucara" or
the "Company") today reports its results for the quarter ended
March 31, 2024. All amounts are in U.S. dollars unless otherwise
noted.
Q1 2024 HIGHLIGHTS:
· The
Karowe Mine has operated continuously for over three years without
a lost time injury.
· The
recovery of a 320-carat top light brown gem quality diamond, a
166-carat Type IIa diamond, followed by the recovery of a 111-carat
Type IIa diamond in Q1 2024.
· In
January 2024, the successful execution of an amended project
financing debt package of $220 million (the "Rebase Amendments") to
amend the repayment profile in line with the rebase schedule
released in July 2023 for the Karowe Underground Project ("Karowe
UGP").
· On
February 18, 2024, the Company announced the signing of a new
ten-year diamond sales agreement ("NDSA") with HB Trading BV ("HB")
in respect of all qualifying diamonds produced in excess of 10.8
carats from the Karowe Mine.
· Total
revenue of $41.1 million (Q1 2023: $42.8 million) was achieved in
the quarter which is reflective of a combination of the timing of
production and quantity of large goods recovered and delivered to
HB.
· During
Q1 2024, a total of 93,560 carats of rough diamonds (Q1 2023:
83,374) from Karowe were sold through the Company's three sales
channels, generating revenue of $36.2 million before top-up
payments of $4.9 million (Q1 2023: $34.7 million before top-up
payments of $6.6 million).
· Operating cost per tonne processed(1) was $26.00, a
decrease of 2% over the Q1 2023 cost per tonne processed of $26.65.
The continued impact of inflationary pressures, particularly
labour, has been well managed by the operation. A strong US dollar
(+5%) continues to offset a small increase in costs over the
comparable period.
(1) See "Non-IFRS Financial Performance
Measures"
William Lamb, President & CEO
commented: "Our Karowe diamond mine
delivered another solid operational quarter, continuing its track
record of sustainable diamond production from this world-class
asset. The Company's high-value diamond production forecast remains
robust, underpinned by our focus on operating practices aligned
with leading environmental, social and governance
standards.
Work on the underground expansion
project at Karowe also progressed well during the quarter. This key
growth initiative remains on track with the rebase schedule and
budget, positioning us to access the higher-value ore from the
underground portion of the ore body, early in 2028.
While the diamond market remained
relatively stable in Q1, we observed some cautious sentiment due to
the broader macroeconomic climate of high inflation and interest
rates impacting consumer demand in certain regions. However, the
fundamental supply and demand dynamics continue to favour natural
diamonds over the long-term as new mine supply remains
constrained.
Lucara is well-positioned with our
exceptional diamond production profile and our innovative process
facilities and sales mechanisms to navigate this environment. We
will continue executing our growth strategy while maintaining
financial discipline to create sustained value for all our
stakeholders."
REVIEW FOR THE QUARTER ENDED MARCH
31, 2024
· Operational highlights from the Karowe Mine for Q1 2024
included:
o Ore
and waste mined of 0.8 million tonnes ("Mt") (Q1 2023: 0.5Mt) and
0.2 million tonnes (Q1 2023: 0.8Mt), respectively.
o 0.7
million tonnes (Q1 2023: 0.7Mt) of ore processed.
o A
total of 89,145 carats recovered, including 7,534 carats from the
processing of historic recovery tailings, (Q1 2023: 89,640 carats)
at a recovered grade of 11.7 carats per hundred tonnes ("cpht") of
direct milled ore (Q1 2023: 12.8 cpht).
§ A total of
160 Specials (defined as stones larger than 10.8 carats) were
recovered, with three diamonds greater than 100 carats including
one diamond greater than 300 carats.
§ Recovered
Specials equated to 5.1% of the total recovered carats from direct
milling ore processed during Q1 2024 (Q1 2023: 4%).
o The Karowe
Mine has operated continuously for over three years without a lost
time injury.
o The
twelve-month Total Recordable Injury Frequency Rate of 0.30 (Q1
2023: 0.36) at the end of Q1 2024 reflects a continued focus on
leading indicators and safe performance.
· Financial highlights for the three
months ended March 31, 2024 included:
o Revenues
of $41.1 million (Q1 2023: $42.8 million) were achieved despite a
weaker rough diamond market. First quarter pricing stabilized in
smaller goods and increases of 4% were observed compared to the
fourth quarter of 2023. Revenue reflects the weighting of Lucara's
revenue towards larger goods where pricing is heavily impacted by
the individual goods delivered in a period. A 33% increase in the
average price of larger goods sold was observed from the fourth
quarter of 2023 and 18% from the first quarter of 2023. The price
of goods in this size category are significantly impacted by the
natural variability in quality of the recovered goods in any
individual period. Revenue against plan was impacted by the
quantity of larger goods delivered in Q1 2024.
o Operating
margins of 51% were achieved (Q1 2023: 57%). A strong operating
margin continues to be achieved through cost reduction initiatives
assisted by a strong U.S. dollar.
o Adjusted
EBITDA(1) was $12.7 million (Q1 2023: $15.3 million),
with the decrease attributable to the changes in revenue and
operating expenses.
o Net loss
was $7.9 million (Q1 2023: net income of $1.0 million), resulting
in a loss per share of $0.02 (Q1 2023: earnings of $0.00). The
significant change to a net loss is due to the loss on
extinguishment of debt of $10.5 million incurred in Q1 2024 in
conjunction with recognizing the amendments to the debt
package.
o Cash
outflows from operating activities was $4.2 million (Q1 2023: cash
flow generated of $20.4 million). Operating cash flow per
share(1) generated, before working capital adjustments,
was consistent at $0.03 (Q1 2023: $0.03)
· Cash
position and liquidity at March 31, 2024:
o Cash and
cash equivalents of $13.2 million.
o Working
capital deficit (current assets less current liabilities) of $0.3
million.
o Cost
overrun account balance ("CORA") of $37.0 million.
o $140.0
million drawn on the $190.0 million Project Loan ("Project Loan")
for the Karowe UGP.
o $25.0
million drawn on the $30.0 million working capital facility
("WCF").
o The total
debt drawn at the end of Q1 2024 was $165.0 million compared to
$125.0 million at December 31, 2023. The increase in debt
drawn during Q1 2024 largely resulted as the Company did not have
access to the Project Loan and WCF from June 2023 until January
2024 when the project finance debt package was
finalized.
(1) See "Non-IFRS Financial Performance
Measures"
DIAMOND MARKET
The long-term outlook for natural
diamond prices remains positive, anchored on improving fundamentals
around supply and demand as many of the world's largest mines reach
their end of life. In the short-term, De Beers, the largest
diamond producer by value reduced their production guidance by up
to 3.0 million carats, for 2024, to assist with stabilizing the
diamond market. During the quarter, the G7 sanctions on the
importation of Russian diamonds greater than one carat went into
effect at the beginning of March and some trade delays were noted
in the industry. The new procedures require all rough diamonds
larger than 1.0 carat to be processed through the Antwerp World
Diamond Centre for validation of point of origin. The Company
sees this as short-term support for diamond pricing as this,
together with the reduction in production volumes from De Beers,
will result in lower volumes of higher value goods being available
in the market.
Sales of lab-grown diamonds
increased steadily through 2023 and into Q1 2024 with many smaller
retail outlets increasingly adopting these diamonds as a product.
In Q1 2024, this market underwent further change with a number of
major brands confirming that they would not market lab-grown
stones. The overall long-term impact will support the natural
diamond market as the Company expects a division between the
natural and lab-grown diamond market. The longer-term market
fundamentals for natural diamonds remain positive, pointing to
continued price growth as demand is expected to outstrip future
supply, which is now declining globally.
2024 OUTLOOK
This section of the press release
provides management's production and cost estimates for 2024.
These are "forward-looking statements" and subject to the
cautionary note regarding the risks associated with forward-looking
statements. Diamond revenue guidance does not include revenue
related to the sale of exceptional stones (an individual rough
diamond which sells for more than $10.0 million), or the Sethunya.
No changes have been made to the guidance released in November
2023.
Karowe Diamond Mine
|
Full Year -
2024
|
In
millions of U.S. dollars unless otherwise noted
|
|
Diamond revenue
(millions)
|
$220 to $250
|
Diamond sales (thousands of
carats)
|
345 to 375
|
Diamonds recovered (thousands of
carats)
|
345 to 375
|
Ore tonnes mined
(millions)
|
2.8 to 3.2
|
Waste tonnes mined
(millions)
|
0.8 to 1.4
|
Ore tonnes processed
(millions)
|
2.6 to 2.9
|
Total operating cash
costs(1) including waste mined (per tonne
processed)
|
$28.50 to $35.50
|
Underground Project
|
Up to $100 million
|
Sustaining capital
|
Up to $10 million
|
Average exchange rate -
USD/Pula
|
12.5
|
(1) Operating cash costs are a
non-IFRS measure. See "Non-IFRS Financial Performance
Measures".
The Company had expected higher
diamond recoveries and diamond quality during Q4 2023 and Q1
2024. This reflects the natural variability in the resource
production in both recovery and diamond quality and were it to
continue, this may impact revenue guidance for 2024. The Company
has seen diamond recoveries and quality improve during April
2024.
DIAMOND SALES
Karowe diamonds are sold through
three sales channels: through the HB sales agreement, on the Clara
digital sales platform and through quarterly tenders.
HB SALES AGREEMENT FOR +10.8 CARAT
DIAMOND PRODUCTION FROM KAROWE
For the three months ended March 31,
2024, the Company recorded revenue of $23.2 million from the HB
arrangements (inclusive of top-up payments of $4.9 million), as
compared to revenue of $24.5 million (inclusive of top-up payments
of $6.6 million) for the three months ended March 31, 2023. The
volume of carats delivered to HB was lower in the first quarter of
2024 than planned. The volume recognized as revenue in Q1 2024 was
impacted by the timing of goods delivered as well as the number of
stones greater than +10.8 carats recovered in the period. The plant
performance remained strong with a 97% recovery factor achieved in
Q1 2024; however, the weight percentage of recovered specials was
lower than plan.
Recovered Specials for the quarter
equated to 5.1% by weight of total recovered carats from ore
processed during Q1 2024, with 89% of carats recovered coming from
the South Lobe, 7% recovered from the Centre Lobe, and 4% recovered
from mixed ore (Q1 2023: 4.0%; 64% Centre and North, 36% South Lobe
ore). Natural variability in the quality profile of the +10.8ct
stones in any production period or fiscal quarter results in
fluctuations in recorded revenue and associated
top-ups.
The average price of goods delivered
in the first quarter of 2024 remained strong and is directly
comparable to the value delivered in the first quarter of 2023.
Top-ups in the first quarter continue to be received from goods
delivered in prior periods under the November 2022 diamond sales
agreement with HB. As a result of these factors, revenue to HB was
consistent at 57% of total revenue recognized in the first quarter
of 2024 (Q1 2023: 57%). The product mix in Q1 2024 was
predominantly from the South Lobe ore body, with some contribution
from the Centre Lobe.
The Company had expected higher
diamond recoveries and diamond quality during Q4 2023 and Q1
2024. This decrease in both recovery and diamond quality
contributed to the Company's additional working capital facility
draw during the quarter. Under the HB agreement payment for
diamonds delivered under a value of $2.0 million is 60 days and for
diamonds of value greater than $2.0 million is 120 days. The
Company has seen diamond recoveries and quality improve during Q2
2024, however due to the payment terms of the HB agreement these
funds will not be received until Q3 2024 which has strained cash
flows during Q2. As a result, the Company drew $25.0 million
from the project loan to fund its underground
development.
The large stone diamond market
fundamentals continued to support healthy prices from the
multi-year highs observed at the peak in Q1 2022, despite an
overall softening of demand in the market.
CLARA SALES PLATFORM
Total volume transacted on the
platform was $4.9 million in Q1 2024 (Q1 2023: $5.3 million), with
non-Karowe goods representing 33% of the total sales volume
transacted. Prices trended flat during the first quarter of 2024
following a small uptick in pricing in December 2023 with a
resumption of purchasing across most size categories. The number of
buyers on the platform reached 106 as of March 31, 2024.
QUARTERLY TENDER
A total of 88,275 carats were sold
in the Q1 2024 tender, generating revenues of $13.0 million or $147
per carat (Q1 2023 tender: $12.9 million from the sale of 77,750
carats or $166 per carat). Following a rebound in the fourth
quarter of 2023, prices trended mostly flat across most size
categories at tender. Like-for-like, prices were up 4% from
December 2023 on all goods sold less than 10.8 carats, including on
Clara.
KAROWE UNDERGROUND EXPANSION
UPDATE
The Karowe UGP is designed to access
the highest value portion of the Karowe orebody, with initial
underground carat production predominantly from the highest value
eastern magmatic/pyroclastic kimberlite (south) ("EM/PK(S)") unit.
The Karowe UGP is expected to extend mine life to at least
2040.
On July 16, 2023, an update to the
Karowe UGP schedule and budget was announced (link
to news release). The anticipated
commencement of production from the underground is H1 2028. The
revised forecast of costs at completion is $683.0 million
(including contingency). As at March 31, 2024, capital expenditures
of $332.5 million had been incurred and further capital commitments
of $64.4 million had been made.
With the update, the Karowe Mine
production and cash flow models were updated for the revised
project schedule and cost estimate. Open pit mining will continue
until mid-2025 and provide mill feed during this time. Stockpiled
material (North, Centre, South Lobe) from working stocks and life
of mine stockpiles will provide uninterrupted mill feed until late
2026 when Karowe UGP development ore will begin to offset
stockpiles with high-grade ore from the underground production feed
planned for H1 2028. The long-term outlook for diamond prices,
combined with the potential for exceptional stone recoveries and
the continued strong performance of the open pit could mitigate the
modelled impact on project cash flows due to the changes in
schedule. The Company continues to explore opportunities to further
mitigate the modelled impact.
During the three months ended March
31, 2024, a total of $17.9 million was spent on the Karowe UGP
development, surface infrastructure and ongoing shaft sinking
activities. The following activities were completed during Q1 2024,
including:
· Main
sinking in the production and ventilation shafts:
o The
ventilation shaft reached 426 metres below collar, with a planned
final depth of 731 metres. The shaft is approximately 19 days ahead
of the July 2023 schedule update (combined vertical and lateral
metres).
o The
production shaft reached 449 metres below collar, with a planned
final depth of 765 metres. The production shaft is approximately 15
days behind the July 2023 schedule update (combined vertical and
lateral), with 9 days gained during the first quarter of 2024. The
production shaft is not a critical path schedule item.
o During Q1 2024, the first shaft stations at the 670-level were
engaged in lateral development at 348 metres below collar (666
masl). The first lateral connection between the two shafts (670
level) was completed. Electrical and dewatering sump excavation was
completed, and construction of equipment was carried out as a
concurrent activity during shaft sinking.
o During Q1 2024, the ventilation shaft sank 78 metres,
completed three probe hole covers, continued the 670-level station
development and replaced the initial winder kibble ropes. Total
lateral development in Q1 2024 was 141 metres.
o Production shaft activities included sinking a total of 101
metres, completion of four probe hole covers, lateral development
on the 670-level station and replacement of the initial winder
kibble ropes. A total of 26 metres of lateral development was
completed.
o Sinking and lateral development during the first quarter took
place in the Thalbala mudstone and the Tlapana carbonaceous
material. Water encountered in the core holes was derived from
Granites. A mini grout cover was completed in the production shaft
and sinking continued.
· Construction of the permanent bulk air coolers at the
production shaft continued with completion expected in Q2 2024.
Planning for a surface dam for the water during production
commenced.
· Detailed engineering and fabrication of the permanent men and
materials winder continued during the quarter, representing the
last major component for the permanent winders.
· Preparation of tender documents for the underground lateral
development work.
· Mining engineering advanced with a focus on supporting shaft
sinking, underground infrastructure engineering and finalizing
level plans.
·
During Q1 2024, the UGP
achieved a twelve-month rolling Total Recordable Injury Frequency
Rate of 0.65. Project to date Total Recordable Injury Frequency
Rate at March 31, 2024 was 0.56.
The capital cost expenditure for the
underground expansion in 2024 is up to $100 million - see "2024
Outlook" below.
Activities planned for the Karowe
UGP in Q2 2024 include the following:
· Sinking within the ventilation and production shafts to the
470-level.
· Sink through the Mea formation into Granites and commence
470-level station development and lateral development.
· Planned cover drill campaigns in the ventilation and
production shafts. Sinking planned for the second quarter will move
through the Mea formation into the Granite lithologies. Probe hole
grouting campaigns are planned in each shaft in the
period.
· Procurement of underground equipment, including an additional
Load, Haul, Dump Aardvark for the production shaft station
development. Major components of the Crusher and sinking pumps will
be delivered to site.
· Commissioning of the permanent bulk air cooler
system.
· Launch
of the tender process for the underground lateral development
work.
· Continuation of detailed design and engineering of the
underground mine infrastructure and layout.
· Finalise engineering of the permanent men and materials
winder. Commence earthworks for winder.
FINANCIAL HIGHLIGHTS - Q1 2024
|
|
|
|
|
|
|
|
|
|
|
Three months ended March
31,
|
|
In millions of U.S. dollars, except
carats or otherwise noted
|
|
2024
|
2023
|
|
|
|
|
|
|
|
|
Revenues
|
|
|
|
$
|
41.1
|
42.8
|
Operating expenses
|
|
|
|
|
(20.2)
|
(18.3)
|
Net (loss) income for the
period
|
|
|
|
|
(7.9)
|
1.0
|
(Loss) earnings per share (basic
and diluted)
|
|
|
|
|
(0.02)
|
0.00
|
Operating cash flow per
share(1)
|
|
|
|
|
0.03
|
0.03
|
Cash on hand
|
|
|
|
|
13.2
|
31.2
|
Cost overrun facility (restricted
cash)
|
|
|
|
|
37.0
|
18.0
|
Amounts drawn on working capital
facility(2)
|
|
|
|
|
25.0
|
23.0
|
Amounts drawn on Project
Loan
|
|
|
|
|
140.0
|
90.0
|
Revenue from the sale of Karowe
diamonds
|
|
|
|
|
39.5
|
41.2
|
Carats sold from Karowe
|
|
|
|
|
93,560
|
83,374
|
|
|
|
|
|
|
|
|
|
QUARTERLY RESULTS OF OPERATIONS - KAROWE MINE
|
UNIT
|
Q1-24
|
Q4-23
|
Q3-23
|
Q2-23
|
Q1-23
|
Sales
|
|
|
|
|
|
|
Revenues from the sale of Karowe
diamonds
|
US$M
|
39.5
|
36.3
|
56.2
|
38.6
|
41.3
|
Karowe carats sold
|
Carats
|
93,560
|
111,523
|
111,673
|
72,717
|
83,374
|
|
|
|
|
|
|
|
Production
|
|
|
|
|
|
|
Tonnes mined (ore)
|
Tonnes
|
809,999
|
607,101
|
869,188
|
682,636
|
541,400
|
Tonnes mined (waste)
|
Tonnes
|
386,849
|
456,880
|
954,226
|
907,051
|
761,295
|
Tonnes processed
|
Tonnes
|
698,870
|
703,472
|
724,640
|
720,345
|
700,678
|
Average grade
processed(1)
|
cpht (*)
|
11.7
|
14.0
|
13.6
|
12.6
|
12.8
|
Carats
recovered(1)
|
Carats
|
81,611
|
98,177
|
98,311
|
90,497
|
89,640
|
|
|
|
|
|
|
|
Costs
|
|
|
|
|
|
|
Operating cost per tonne of ore
processed(2)
|
US$
|
26.00
|
31.96
|
28.62
|
27.97
|
26.65
|
|
|
|
|
|
|
|
Capital Expenditures
|
|
|
|
|
|
|
Sustaining capital
expenditures
|
US$M
|
1.8
|
8.0
|
3.2
|
2.4
|
0.8
|
Underground expansion
project(3)
|
US$M
|
17.9
|
28.0
|
20.3
|
22.5
|
30.5
|
ANNUAL MEETING
INFORMATION
The Company's annual general and
special meeting of shareholders will be held at the office of
Blake, Cassels & Graydon LLP, 1133 Melville Street, Suite 3500,
Vancouver, BC V6E 4E5, Canada on May 10, 2024 at 10:00 a.m.
Pacific.
CONFERENCE CALL
The Company will host a conference
call and webcast to discuss the results on Friday, May 10, 2024 at
6:00am Pacific, 9:00am Eastern, 2:00pm UK, 3:00pm CET.
To join the conference call please
use the following link https://emportal.ink/4arz7Nw
or the phone numbers listed
below.
Conference ID:
35323198 / Lucara Diamond
Dial-In Numbers:
Toll Free Participant
Dial-In North America
(+1) 888 390 0605
UK Toll
Free
0800
652 2435
Local
Vancouver
(+1) 416 764 8609
Webcast:
To view the live webcast
presentation, please log on using this direct link:
https://app.webinar.net/xMgd9elnpVN
The presentation slideshow will also
be available in PDF format for download from the Lucara website
(Link to
presentation).
Conference Replay:
A replay will be available until May
17, 2024. The pass code for the replay is: 085076 #.
Replay number (Toll
Free North
America)
(+1) 888 390 0541
Replay number
(Local)
(+1) 416 764 8677
On
behalf of the Board,
William Lamb
President and Chief Executive
Officer
Follow Lucara Diamond on
Facebook,
Instagram,
and LinkedIn
For further information, please
contact:
ABOUT LUCARA
Lucara is a leading independent
producer of large exceptional quality Type IIa diamonds from its
100% owned Karowe Diamond Mine in Botswana. The Karowe Mine has
been in production since 2012 and is the focus of the Company's
operations and development activities. Clara Diamond Solutions
Limited Partnership ("Clara"), a wholly-owned subsidiary of Lucara,
has developed a secure, digital sales that ensures diamond
provenance from mine to finger. Lucara has an experienced
board and management team with extensive diamond development and
operations expertise. Lucara and its subsidiaries operate
transparently and in accordance with international best practices
in the areas of sustainability, health and safety, environment, and
community relations. Lucara has adopted the IFC Performance
Standards and the World Bank Group's Environmental, Health and
Safety Guidelines for Mining (2007). Accordingly, the
development of the Karowe UGP adheres to the Equator Principles.
Lucara is committed to upholding high standards while striving to
deliver long-term economic benefits to Botswana and the communities
in which the Company operates.
The information is information that
Lucara is obliged to make public pursuant to the EU Market Abuse
Regulation and the Swedish Securities Markets Act. This information
was submitted for publication, through the agency of the contact
person set out above, on May 9, 2024 at 6:00pm Pacific
Time.
NON-IFRS FINANCIAL PERFORMANCE
MEASURES
This news release refers to certain
financial measures, such as adjusted EBITDA, adjusted operating
earnings, operating cash flow per share, operating margin per carat
sold and operating cost per tonne of ore processed, which are not
measures recognized under IFRS and do not have a standardized
meaning prescribed by IFRS. These measures may differ from those
made by other corporations and accordingly may not be comparable to
such measures as reported by other corporations. These measures
have been derived from the Company's financial statements, and
applied on a consistent basis, because the Company believes they
are of assistance in the understanding of the results of operations
and financial position. Please refer to the Company's MD&A for
the quarter ended March 31, 2024 for an explanation of non-IFRS
measures used.
CAUTIONARY NOTE REGARDING FORWARD
LOOKING STATEMENTS
Certain of the statements made and
contained herein and elsewhere constitute "forward-looking
information" and "forward-looking statements" as defined in
applicable securities laws. Generally, any statements that express
or involve discussions with respect to predictions, expectations,
beliefs, plans, budgets, schedules, goals, strategy, projections,
objectives, assumptions or future events or performance and often
(but not always) using forward-looking terminology such as
"expects", "is expected", "anticipates", "believes", "intends",
"estimates", "potential", "possible" and similar expressions, or
statements that certain actions, events, conditions or results
"would", "will", "may", "might", "could" or "should" be taken,
occur or be achieved or the negative of any of these terms and
similar expressions) are not statements of historical fact and may
be forward-looking statements.
Forward-looking statements are based
on the opinions and estimates of management as of the date such
statements are made, and they are subject to a number of known and
unknown risks, uncertainties and other factors which may cause the
actual results, performance or achievements of the Company to be
materially different from any future results, performance or
achievement expressed or implied by such forward-looking
statements, including risks related thereto. The Company believes
that expectations reflected in this forward-looking information are
reasonable, but no assurance can be given that these expectations
will prove to be accurate and such forward-looking information
included herein should not be unduly relied upon.
In particular, forward-looking
information and forward-looking statements in this news release may
include, but are not limited to, information or statements of
projected capital costs associated with the Karowe
UGP and any conditions for
borrowing at the time of a borrowing
request, and that the facilities are not otherwise terminated or
accelerated due to an event of default, the
Company's ability to comply with the terms of the facilities which
are required to construct the Karowe UGP, that expected cash flow
from operations, combined with external financing will be
sufficient to complete construction of the Karowe UGP, economic and
geopolitical risks, including the potential impacts from the
ongoing conflict between Russia and Ukraine and
the resulting indirect economic impacts that strict economic
sanctions have, expectations regarding
longer-term market fundamentals and price growth, the disclosure
under "2024 Outlook", expectations regarding top-up payments,
processing expectations, expectations that the Karowe UGP will
extend mine life, forecasts of additional revenues, estimated
capital costs, production and cost estimates, tax rates,
expectations regarding the scheduling of activities for the Karowe
UGP in 2024 and in future, that the
estimated timelines to achieve mine ramp up and full production
from the Karowe UGP can be achieved, the
economic potential of a mineralized area, the size and tonnage of a
mineralized area, anticipated sample grades or bulk sample diamond
content, future production activity, the future price and demand
for, and supply of, diamonds, future forecasts of revenue and
variable consideration in determining revenue, estimation of
mineral resources, exploration and development plans, cost and
timing of the development of deposits and estimated future
production, currency exchange rates, success of exploration,
requirements for and availability of additional capital, capital
expenditures, operating costs, the completion of transactions, and
the profitability of Clara and the Clara Platform, the benefits to
the Company of diamond supply agreements with HB and the ability to
generate better prices from the sale of the Company's +10.8 carat
production as a polished stone.
There can be no assurance that such
forward looking statements will prove to be accurate, as the
Company's results and future events could differ materially from
those anticipated in this forward-looking information as a result
of those factors discussed in or referred to under the heading
"Risks and Uncertainties" in the Company's most recent MD&A and
in the Company's most recent Annual Information Form, both
available at SEDAR+ at www.sedarplus.ca, as well as changes in
general business and economic conditions, the ability to continue
as a going concern, changes in interest and foreign currency rates,
changes in inflation, the supply and demand for, deliveries of and
the level and volatility of prices of rough diamonds, costs of
power and diesel, impacts of potential disruptions to supply
chains, acts of foreign governments and the outcome of legal
proceedings, inaccurate geological and recoverability assumptions
(including with respect to the size, grade and recoverability of
mineral reserves and resources), and unanticipated operational
difficulties (including failure of plant, equipment or processes to
operate in accordance with specifications or expectations, cost
escalations, unavailability of materials and equipment, government
action or delays in the receipt of government approvals, industrial
disturbances or other job actions, adverse weather conditions, and
unanticipated events relating to health safety and environmental
matters).
Accordingly, readers are cautioned
not to place undue reliance on these forward-looking statements
which speak only as of the date the statements were made, and the
Company does not assume any obligations to update or revise them to
reflect new events or circumstances, except as required by
law.