Moyle Interconnector (Financing)PLC Moyle Interconnector interim return to service (2996N)
28 Enero 2016 - 4:51AM
UK Regulatory
TIDM84WR
RNS Number : 2996N
Moyle Interconnector (Financing)PLC
28 January 2016
Moyle Interconnector (financing) plc
The Moyle Interconnector returned to full availability on an
interim basis from 0600 on 28/01/2016.
The initial focus of the Moyle Return Cables project has been to
restore the availability of the out of service North cable ("pole
2") so that the interconnector can return to its full capacity. As
of lunchtime on Friday 22/01/2016 pole 2 has been back in service
and carrying the Moyle commercial load, with pole 1 held in reserve
in case of any issues. Since no significant issues have been
identified we are now making Moyle available to the market at full
capacity from the start of SEM trading day 28/01/2016.
The new cable is contractually undergoing its one month
reliability run and consequently the additional capacity will all
be made available in daily auctions for the rest of January and the
whole of February (an additional 200MW GB-NI and 45MW NI-GB).
The replacement South cable ("Pole 1") has already been laid and
protection work is well advanced. Final protection work and cable
jointing is scheduled to take place during the spring and summer
months. Some availability reductions will be required for that
work.
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCBGGDBGUDBGLI
(END) Dow Jones Newswires
January 28, 2016 05:51 ET (10:51 GMT)
Moyle2.9376%33 (LSE:84WR)
Gráfica de Acción Histórica
De Nov 2024 a Dic 2024
Moyle2.9376%33 (LSE:84WR)
Gráfica de Acción Histórica
De Dic 2023 a Dic 2024