TIDMCEY 
 
RNS Number : 6550W 
Centamin Egypt Limited 
31 July 2009 
 

+---------------------------------------+---------------------------------------+ 
| For Immediate Release                 |                          31 July 2009 | 
+---------------------------------------+---------------------------------------+ 
 
 
 
 
Centamin Egypt Limited ("Centamin" or "the Company") 
(TSX:CEE, ASX:CNT, AIM:CEY) 
 
 
QUARTERLY REPORT FOR THE QUARTER ENDED 30 JUNE 2009 
 
 
Highlights 
 
 
Construction and Development 
 
 
  *  First gold pour achieved from the Sukari Gold Project 
  *  Commissioning activities commenced with good progress on remaining construction 
  activities 
  *  Cummins Power Station commissioned with other mechanical and piping 
  installations well advanced 
  *  
  *  
  *  Final approvals for direct seawater intake achieved during the quarter, further de-risking the projectBore field development for 25km seawater pipeline completed with sound resultsPeak manpower achieved during the quarter with +1,200 personnel on site
 
 
 
 
 
Operations 
 
 
  *  Mineral resource  upgraded to 9.91 Moz Measured and Indicated, plus 3.3 Moz 
  Inferred 
  *  Measured and Indicated increase of 520,000 oz or 6% 
  *  Drilling returned highly encouraging assay results in the northern half of the 
  Sukari Hill 
  *  Open pit mining operations progressing well with owner operator mining fleet 
  *  Underground mining  contractor mobilisation and preliminary works commenced 
  *  
  *  
  *  
  *  14,264m of diamond drill ("DD") completed during the quarterContinued resource definition drilling to target Hapi, Amun Deeps and Pharaoh Zone with 8 drill rigsRegional Exploration continues - Detailed mapping and site preparation completed for Quartz Ridge; more high grade surface samples and shear zones identifiedSignificant intersections received for the quarter include:
 
 
 
D1431 - 17m @ 10.49g/t Au 
D1432 - 97m @ 1.89g/t Au 
D1434 - 19m @ 2.87g/t Au 
D1435 - 43m @ 17.00g/t Au 
D1440 - 14m @ 6.71g/t Au 
D1446 - 70m @ 2.20g/t Au 
D1450 - 25m @ 2.58g/t Au 
 
 
Corporate 
 
 
  *  Private placement raises gross proceeds of C$30M 
 
 
 
 
 
 
 
Commenting on the quarterly report Josef El-Raghy, Managing Director/CEO of 
Centamin, stated: 
 
 
"We are pleased with the success of our first gold pour and remain committed to 
ramping up to full production towards the end of 2009". 
SUKARI GOLD PROJECT CONSTRUCTION 
 
 
The first gold pour was achieved from the Sukari Gold Project on 26 June 2009. 
Stage 1 construction and commissioning activities progressed well within the 
quarter. Stage 1 and Stage 2 construction and commissioning activities will 
continue throughout the next quarter. 
 
 
Construction activities have focused on main power generation systems, plant 
pipe installations, mechanical equipment installation, electrical controls and 
the seawater pipeline. Peak workforce levels were achieved during the second 
quarter with significant scopes of work awarded and progressed.  Workforce 
levels will continue at maximum capacity as Stage 1 construction activities are 
completed and full commissioning of major plant components are achieved. 
 
 
Progress pictures can be viewed on the Company's website - www.centamin.com. 
 
 
Project Engineering and Design 
 
 
As previously reported, MetPlant Engineering Services Pty Ltd, an Australian 
based company, has completed engineering and design work for the Process Plant 
and have handed over documentation in their native formats.  Final arrangements 
are being made to close off the design contract. 
 
 
Piping engineering and design with SENET in South Africa continues to progress 
well with Stage 1 rack piping design complete and all drawings received. Stage 2 
final drawings are currently in progress. 
 
 
Crusher & Conveyor Systems 
 
 
Crusher area structural steel and mechanical installation is now complete with 
commissioning of the crusher and lubrication units continuing. Conveyor belts 
CV-01A and CV-01 have been spliced and installed successfully. PLC systems 
checks are underway and commissioning is due for completion shortly. 
 
 
Reclaim and Grinding Systems 
 
 
Mill assembly progressed well through the quarter with all shell and head 
segments installed and the Ball and SAG Mill ring gear, pinion and motors in 
place with final alignment checks ongoing and continued commissioning in the 
coming quarter. The apron feeders have been fully installed and commissioned 
successfully. 
 
 
All major steel requirements have been delivered to site. Installation of the 
pebble crushing and handling facilities is now being focussed upon and is due 
for completion in the middle of the next quarter. 
 
 
CIL Circuit & Gold Recovery 
 
 
CIL top of tank steel erection is well advanced and interconnecting launder 
installation was finalised during the quarter. Tank agitators have been 
assembled and installed. 
 
 
Construction of the gold room has progressed well with the majority of 
mechanical installations now in place on the first and ground floors. Partial 
commissioning of the elution and strip areas of the gold room took place and 
further commissioning activities are scheduled to occur in the forthcoming 
quarter. 
 
 
Reagents, Air & Water Services 
 
 
Cyanide and caustic soda build continues and is due for completion in the 
forthcoming quarter. 
 
 
The air services building is approaching completion and all compressors and air 
blowers have been installed mechanically. The RO plant is fully installed and 
ready for commissioning. 
 
Power Plant 
 
 
Installation and commissioning of the Cummins (7MW) power station was finalised 
following mechanical fit out of the generator sets and installation of cable 
ladder. 
 
 
Mechanical and piping installation has progressed in the MAK (28MW) power 
station with mechanical installations practically complete for the diesel 
systems. The focus at present is on engines 3 and 4 for the lube oil, cooling 
water, air and diesel piping systems. Installation and commissioning of the 
various systems for these engines to run on diesel is expected to take place in 
the next quarter. 
 
 
Building installation works are approaching completion with minor works and 
external cladding in progress.Engine overhauls are well advanced and will be 
completed early next quarter. 
 
 
Fuel Farm tank installation is progressing well with three major tanks completed 
and commissioned for use. The remaining tanks shall be completed early in the 
next quarter.  Piping of the tanks to the pump skids and pipe racks is 
progressing well. 
 
 
Site Buildings and Infrastructure 
 
 
The major plant 20MVA power transformers were installed during the quarter. MCC 
buildings have been established and completed at various locations. 
 
 
Civil works and steel erection on the main pipe racks for Stage 1 were completed 
during the quarter and services for underground piping installation were 
finalised. Erection of steel framing and offices for the main warehouse building 
were completed with minor works and fencing to be finalised. Commissioning of 
the site laboratory is scheduled for early in the next quarter. 
 
 
Tailings and Tailings Storage Facility ("TSF") 
 
 
The thickener and cyanide process water tanks are fully installed, with steel 
work and pump systems approaching completion. 
 
 
Stage 1 of the TSF construction is approaching completion with minor works to be 
finalised in the next quarter. The underdrainage and decant riser pipes have 
been installed along with the final sections of high density polyethylene 
("HDPE") Civil works for Stage 2 construction, which will provide two-years' 
storage capacity, have also progressed well. 
 
 
Seawater Supply System 
 
 
During the quarter, the company received the final government approval for the 
direct seawater intake pipeline. Mobilisation and installation works are 
expected to commence in the next quarter with a targeted completion date toward 
the end of 2009. 
 
 
Water bore development, which was established whilst the approval process for 
direct seawater intake was ongoing, is now complete, with sufficient successful 
bores. 
 
 
Mechanical installation of the 25km seawater supply system is complete with 
testing of the tanks having taken place during the quarter. Electrical 
installation of the overhead power lines along the length of the pipeline is now 
in place. Transformers and MCC installation will be completed in the next 
quarter to fully commission the pump stations. 
 
 
(please refer to attached pdf to view picture) 
Progress Picture 1: First Gold Pour 
 
 
RESOURCE DEFINITION 
 
 
Resource definition drilling continues to be successful in both conversion of 
Inferred resources to Measured and Indicated and in global growth. Measured and 
Indicated resources grew by 520,000 or approximately 6% to 9.91Moz, with 3.3Moz 
of Inferred category at a 0.5g/t Au cut off grade (Table 1 & Figure 1). 
 
 
Table 1 - Total Resource (July 2009) 
 
 
+---------+---------+-------+--------+-------+--------+-------+-------+--------+-------+-------+ 
|         |         |       |        |       |         Total          |        |       |       | 
+---------+---------+-------+--------+-------+------------------------+--------+-------+-------+ 
|         |    Measured     |   Indicated    |      Measured +        |        Inferred        | 
|         |                 |                |       Indicated        |                        | 
+---------+-----------------+----------------+------------------------+------------------------+ 
|Cut-off  | Tonnes  |Grade  |Tonnes  |Grade  |Tonnes  |Grade  | Gold  |Tonnes  |Grade  | Gold  | 
+---------+---------+-------+--------+-------+--------+-------+-------+--------+-------+-------+ 
|  g/t    |  (Mt)   | (g/t  |  (Mt)  | (g/t  |  (Mt)  | (g/t  |(Moz)  |  (Mt)  | (g/t  |(Moz)  | 
|   Au    |         |  Au)  |        |  Au)  |        |  Au)  |       |        |  Au)  |       | 
+---------+---------+-------+--------+-------+--------+-------+-------+--------+-------+-------+ 
|  0.5    |  75.65  | 1.48  |125.77  | 1.56  |201.41  | 1.53  | 9.91  |  61.3  |  1.7  |  3.3  | 
+---------+---------+-------+--------+-------+--------+-------+-------+--------+-------+-------+ 
|  0.7    |  54.48  | 1.82  | 91.50  | 1.93  |145.97  | 1.89  | 8.85  |  43.9  |  2.1  |  2.9  | 
+---------+---------+-------+--------+-------+--------+-------+-------+--------+-------+-------+ 
|    1    |  35.50  | 2.35  | 60.89  | 2.47  | 96.39  | 2.43  | 7.52  |  29.3  |  2.7  |  2.5  | 
+---------+---------+-------+--------+-------+--------+-------+-------+--------+-------+-------+ 
Note to Table: Figures in table may not add correctly due to rounding 
 
 
Resource growth at Sukari occurred in the south from 10450N to 10700N, testing 
the Hapi Zone and Amun Deeps porphyry block. Mineralisation remains open greater 
than 1.1km below wadi level and along strike to the north of 10700N where 
drilling is currently focussed. In the Pharaoh Zone, significant resource 
addition and conversion occurred from 11200N to 12000N where the Hapi, deeper 
and west dipping Cleopatra style zones has been defined further along strike. 
Mineralisation remains open and is also the target of intensive drilling (Figure 
2). 
 
 
High grade intersections in the estimate are primarily related to the Hapi and 
deeper zones of mineralisation including (from the southern Amun Zone); 97m @ 
1.89g/t Au from 314m in hole RCD1432 on section 10475N and 19m @ 2.87g/t Au from 
452m in D1434 on 10650N.In the Pharaoh Zone; 43m @ 17.00g/t Au from 499m in hole 
RCD1435* (11250N), 79m @ 4.48g/t Au from 662m in hole D1420* (11275N) and 17m @ 
10.49g/t Au from 610m and 55m @ 3.48g/t Au from 641m in hole D1431* (11400N). 
Details on these and other significant intersections are shown in Table 2 and 
Figure 3. 
 
 
(please refer to attached pdf to view figure 1) 
Figure 1 - Sukari resource growth graph from April 1997 to July 2009 
 
 
(please refer to attached pdf to view figure 2) 
Figure 2 - Plan View of Porphyry with Upgraded Resource distribution and current 
work areas 
 
 
 
 
Table 2 - Significant high grade samples included in July 2009 Resource 
 
 
+--------+--------+-------+-----+-----+--------+---------+------------+---------+ 
|  HOLE  | NORTH  | EAST  |DIP  |AZI  |  EOH   |  FROM   |  INTERVAL  |  GOLD   | 
|        |        |       |     |     |  (m)   |  (m)    |    (m)     |  (g/t)  | 
+--------+--------+-------+-----+-----+--------+---------+------------+---------+ 
|D1420*  | 11275  |10835  |-80  |270  | 763.5  |  662    |    79      |  4.48   | 
+--------+--------+-------+-----+-----+--------+---------+------------+---------+ 
|D1423*  | 11350  |10866  |-88  |270  | 644.8  |  542    |    47      |  2.85   | 
+--------+--------+-------+-----+-----+--------+---------+------------+---------+ 
|D1431*  | 11400  |10850  |-83  |270  | 786.1  |  610    |    17      |  10.49  | 
+--------+--------+-------+-----+-----+--------+---------+------------+---------+ 
| D1431  | 11400  |10850  |-83  |270  | 786.1  |  641    |    55      |  3.48   | 
+--------+--------+-------+-----+-----+--------+---------+------------+---------+ 
| D1432  | 10475  |10784  |-73  |270  | 692.7  |  314    |    97      |  1.89   | 
+--------+--------+-------+-----+-----+--------+---------+------------+---------+ 
|D1435*  | 11250  |10950  |-84  |270  |  584   |  499    |    43      |  17.00  | 
+--------+--------+-------+-----+-----+--------+---------+------------+---------+ 
| D1440  | 11300  |10883  |-83  |270  | 683.3  |  569    |    14      |  6.71   | 
+--------+--------+-------+-----+-----+--------+---------+------------+---------+ 
| D1446  | 11550  |10787  |-87  |270  |  753   |  636    |    70      |  2.20   | 
+--------+--------+-------+-----+-----+--------+---------+------------+---------+ 
Intervals shown in the table are down hole intercepts, drilled at high angles 
relative to the internal mineralized structures and the Sukari Porphyry. 
(*Denotes previously announced 20 May 2009 & 14 July 2009) 
 
 
(please refer to attached pdf to view figure 3) 
Figure 3 - Long Section of Sukari Porphyry showing key intersections, 
mineralised zones and drilling targets 
 
 
 
 
EXPLORATION 
 
 
During the quarter, resource definition drilling was concentrated in the 
northern Pharaoh Zone, primarily targeting the Hapi Zone and deeper 
mineralisation, but also upper parts of the porphyry; and in the far north; near 
surface west dipping Cleopatra style zones (Figure 3). Some drilling also 
occurred in the south of the Sukari porphyry from Wadi Fault, targeting the 
Downthrust extension of the Amun Deeps porphyry block, and down dip and along 
strike extensions of the Hapi Zone. Drilling will continue with eight rigs in 
all of the above areas for the foreseeable future. 
 
 
Amun and Ra Zones (10000 - 11200N) 
 
 
Hole D1432 was drilled to infill the main porphyry block and Hapi Zone, test the 
extent of the Amun Deeps porphyry block and the Downthrust Zone and successfully 
intersected high grade mineralisation (97m @ 1.89g/t Au; 22m @ 1.11g/t and 6m @ 
2.73g/t). Hole D1434 was drilled further north on 10650N to infill around high 
grade zones in previously reported holes D1416, RCD1417 and D1415 (March Quarter 
2009) and successfully intersected the Amun Deeps (19m @ 2.87g/t Au) and 
Downthrust Zones, in areas with little previous drilling (Figure 4). This has 
provided encouragement to continue testing along strike north of 10700N where 
current holes D1455 and 1463 (assays awaited) have recently intersected 
significant blocks of mineralised porphyry. 
 
 
 
 
(please refer to attached pdf to view figure 4) 
Figure 4 - Section 10625N - Amun Zone 
 
 
 
 
Pharaoh Zone (11200N - 12100N) 
 
 
Most of the drilling during the quarter was focussed in the Pharaoh Zone, 
targeting infill and along strike extension of the high grade Hapi Zone 
mineralisation, deeper high grade zones at the base and contact of the main 
porphyry to the sedimentary country rock package and more west-dipping 
mineralisation in the far north (Figure 3). 
 
 
Drilling continued to return strong intersections at the base of the porphyry 
intrusion in the Hapi and deeper zones (Table 4). This correlated strongly with 
previously recorded results along strike and up and down dip; and infilled 
previously untested areas of the porphyry (Figure 5). 
 
 
(please refer to attached pdf to view figure 5) 
Figure 5: Section 11275 - D1420 has successfully tested to the footwall, 
extending the porphyry dimensions and resource blocks and returned a high grade 
intersection of 79m @ 4.48g/t Au from 662m 
 
 
 
 
Holes such as D1435 (11250N - 43m @ 17.00g/t Au from 499m), D1440 (11300N - 14m 
@ 6.71g/t Au from 569m), D1431 (11400N - 17m @ 10.49g/t Au from 610m and 55m @ 
3.48g/t Au from 641m), D1450 (11500N - 25m @ 2.58g/t Au from 655m) and D1446 
(11550N - 25m @ 2.58g/t Au from 636m) prove the continuity and significance of 
the Hapi and deeper zones (Figure 3 & 5), with the northwards continuation the 
subject of ongoing drilling. 
 
 
The coming quarter will see drilling continuing in the Pharaoh Zone north of 
11600N to define the Hapi and deeper Zones along strike. In the Amun Zone, 
drilling will continue to test the Amun Deeps, Downthrust and Hapi Zones north 
of 10700N. Drilling access tracks are underway using drill and blast and 
rock breakers to unlock the strong resource potential of the steepest parts of 
the North West part of the hill, previously sparsely drilled due to the 
challenging topography. 
 
 
 
 
REGIONAL EXPLORATION 
 
 
Regional exploration work focussed on detailed mapping and understanding the 
Quartz Ridge prospect before drilling commences early in the coming quarter. 
Drilling will target the sheared and mineralised south east dipping sheared and 
altered contacts and east-west to NE striking Au mineralised quartz veins of an 
altered, sheared felsic granodiorite intrusive body (Figure 6). 
 
 
Wide spaced regional work continued to increase coverage of the mapping and 
geochemistry. 
 
 
(please refer to attached pdf to view figure 6) 
Figure 6 - Quartz Ridge Prospect - Mapped Geology, surface Au Assays and 
proposed drill holes 
 
 
 
 
GRADE CONTROL 
 
 
35,223m of reverse circulation ("RC") grade control ("GC") drilling from 2,310 
holes was completed during the quarter in Stage 1 (Amun Zone) and 2 (Ra Zone) of 
the "open pit" area (Figure 3) with a total of 28,302 samples being processed. 
 
 
Drilling and mapping has shown high grade Au is associated with strongly sheared 
and sericite-hematite altered porphyry; with stock works of extensional quartz 
veins and sheared contacts with the hanging wall rocks. Correlations between the 
resource model and grade control are strong, with mineralised controlling 
structures showing up in the grade control and mapping well. 
 
OPEN PIT MINING 
 
 
Centamin conducts its open pit mining operations on an 'owner operator' basis. 
Primary mining fleet includes ten CAT785C rear dump trucks and two O&K RH120E 
excavators with additional mine support equipment in place.  Atlas Copco 
equipment is used to supply grade control and blast hole drilling equipment. 
 
 
Mining and blasting operations have performed well since commencement of 
blasting on 01 February 2009. 
 
 
During the quarter, Stage 1 was advanced 21m vertically from the 1166mRL to the 
1145RL; and the Stage 2 vertical advance was 24m from the 1208mRL with 50% of 
the 1184mRL remaining at the end of the quarter. 
 
 
A total of 1,157,305 bank cubic metre ("BCM") of material was mined during the 
quarter with 352,885 tonnes of ore mined and delivered to the ROM pad for 
processing. For the financial year, a total of 2,574,020 BCM of material has 
been mined. 
 
 
UNDERGROUND MINE DEVELOPMENT 
 
 
Centamin announced on 03 April 2009 that it had issued a Letter of Intent to 
Barminco for the immediate mobilisation of personnel and equipment, and 
subsequent commencement of underground mining activities at the Sukari Gold 
Project in Egypt. 
 
 
Mobilisation of initial underground mining fleet and contractor personnel was 
completed in June. Site works have commenced with electrical power line and 
other support services being finalised ahead of portal construction and decline 
development in the September 2009 quarter. 
 
An initial underground mining rate of 500,000 tonnes per annum at a grade 
between 5-10g/t Au is being targeted thus bringing higher grade ore feed into 
production earlier than otherwise would have been scheduled through surface 
mining at circa 2g/t. Full production from the underground is scheduled to be 
achieved approximately 18 months after commencement of the decline. 
 
 
 
 
PROCESSING & TREATMENT 
 
 
First gold production was achieved at Sukari on 26 June 2009. The gold pour 
produced an estimated 130 gold ounces (subject to final assay) and represents a 
significant milestone for the Company and for Egypt, with the establishment of 
the first modern gold mine in Egyptian history. 
 
 
 
 
CORPORATE 
 
 
On 02 April 2009, the Company announced it had entered into an agreement with 
Macquarie Bank Limited ("MBL") to provide a corporate loan facility of up to 
US$25 million. It is the Company's intention that development of the Sukari Gold 
Project will be funded out of existing cash resources and internally generated 
cash flow however the loan facility provides the Company with access to 
additional funds at a low cost for future use, if required. The loan facility is 
subject to final documentation and remains undrawn to date. 
 
 
On 03 July 2009, the Company announced that it had attained subscriptions from 
various North American resource focussed funds for a private placement of 19 
million ordinary shares at an offering price of C$1.56 per share raising gross 
proceeds of C$29.6M.  Centamin Egypt Limited intends to use the net proceeds of 
the offering for the continued exploration activities and general corporate 
purposes. 
 
 
 The Company is currently debt free, unhedged and able to aggressively pursue 
further exploration and development activities, including the underground 
development of the high grade Amun Deeps zone. 
 
 
 
 
SUKARI GOLD PROJECT (BACKGROUND) 
 
 
Centamin is a mineral exploration and development company that has been actively 
exploring in Egypt since 1995. The principal asset of Centamin is its interest 
in the Sukari Gold Project, located in the Eastern Desert of Egypt. The Sukari 
Gold Project is at an advanced stage of development, with construction having 
commenced in the second quarter of 2007 and first gold bar having been poured on 
26 June 2009. This milestone marked the commencement of production and 
commissioning at the Sukari gold mine ahead of the commercial ramp up of 
production, which is anticipated over the coming months. 
 
 
A definitive feasibility study ("DFS") for the development to commercial 
production of the Sukari Gold Project was completed in February 2007. 
 
 
A summary of the findings of the DFS were:- 
 
 
  *  the DFS concluded that a 4mpta plant producing on average 200,000 ounces per 
  annum, over 15 years of mining, is economically robust; and 
  *  total Capital Construction costs are estimated at US$216m with average cash 
  operating costs of US$290/oz (inclusive of 3% royalty) over the 15 year mining 
  period. As at 30 June 2008, the Company is of the opinion that due to increased 
  commodities prices, project delays and currency movements since finalisation of 
  the DFS that the capital estimate is at risk by 20%. Average cash operating 
  costs have also been revalidated as at 30 June 2008 due the higher cost of 
  consumables, and are forecast to be US$365/oz. 
 
 
 
The Sukari Gold Project will be the first large-scale modern gold mine to be 
developed in Egypt. Centamin's operating experience in Egypt gives it a 
significant first-mover advantage in acquiring and developing other gold 
projects in the prospective Arabian-Nubian Shield. 
 
 
The Sukari Gold Project is hosted by a large, sheeted vein-type and 
brittle-ductile shear zone hosted gold deposit developed in a granitoid 
intrusive complex. Gold mineralization is hosted exclusively by a granitoid body 
of granodiorite - tonalite composition referred to as the Sukari Porphyry. The 
Company has entered into a Concession Agreement with the Egyptian Government 
that provides for exploration and exploitation rights at the Sukari Gold Project 
and whereby the Operating Company, owned 50% by the Company's wholly owned 
subsidiary, Pharaoh Gold Mines NL and 50% by Egyptian Mineral Resource Authority 
("EMRA"), has been established. Centamin is entitled to recover all of its 
exploration, operating and capital costs from operating surpluses of the 
operating company. 
 
 
The Sukari Mining Licence covers an area of 160 km2 and is for a period of 30 
years, with an option for a further 30 years. 
 
 
The Sukari Gold Project has been scheduled for open pit mining over an initial 
15-year period. During that time 78 Mt ore @ 1.5 g/t Au is expected to be mined, 
producing 3.7Moz gold. A further 374 Mt of waste material is also expected to be 
mined resulting in a waste to ore strip ratio of 4.8:1. 
 
 
Ore and waste will be mined using conventional open pit mining methods. The 
operation is planned to utilize selective mining techniques to separate ore and 
waste. Provision has been made for drilling and blasting all primary and oxide 
materials. Ore will be hauled to the run of mine pad next to the Processing 
Plant and either direct tipped to the crusher or stockpiled for future reclaim 
at the 4 Mtpa Process Plant throughput rate. 
 
 
Mining will be progressed at an increased rate compared to processing; 
approximately 5 Mt of ore is expected to be mined and 4 Mt of ore will be 
processed annually. Operating at an increased mining rate allows the cut off 
grade for feed to the Plant (referred to as "cutover" grade) to be increased in 
the early years of the schedule. This in turn increases the metal output and 
project revenue in these early years, thus increasing the discounted operating 
surplus cashflow. According to current schedules, the low-grade stockpile 
produced as a result of applying a cutover grade, will be processed after mining 
has ceased, extending the current operating life of the project for a further 
six years. As a result, the average milled grade during the mining period is 
forecast to be 1.87 g/t Au, compared to 0.66 g/t Au for the low-grade stockpile. 
 
 
Centamin will own and operate its mining fleet. The production fleet will be 
based on 380 t class excavators and 150 t class rigid body trucks. At full 
production, three production fleets, each comprising a single excavator and 
sharing a maximum of 21 trucks, will be required. The capital cost of the 
initial mining fleet has been estimated at US$49.3 million. 
 
 
The proposed process route entails:- 
 
 
  *  crushing; 
  *  stockpiling crushed ore; 
  *  grinding; 
  *  flotation of a (bulk sulphide) concentrate containing the precious metals; 
  *  thickening of the concentrate; 
  *  fine milling of the concentrate; 
  *  leaching the precious metals from the concentrate in a dilute cyanide solution; 
  *  adsorbing the precious metals onto activated carbon; 
  *  stripping the precious metals from the carbon; 
  *  recovering the precious metals as gold doré; and 
  *  placing the concentrate tailing in the tailings storage facility. 
 
 
 
Tailings from the treatment of weathered oxide ore early in the mining schedule 
contain too much gold to discard. Hence, the bulk flotation tail is further 
treated by:- 
 
 
  *  thickening; 
  *  leaching the precious metals into a dilute cyanide solution; 
  *  adsorbing the precious metals onto activated carbon; 
  *  stripping the precious metals from the carbon; 
  *  recovering the precious metals as gold doré; and 
  *  placing these tailings in the tailings storage facility. 
 
 
 
Process water will be drawn from a bore field located adjacent to the Red Sea. 
The seawater will be pumped approximately 25 km to the mine site to satisfy all 
Process Plant and mining requirements. Most of the seawater will be pumped into 
a raw water pond located near the Processing Plant, whilst around 500m³/day will 
be pumped to a Water Treatment Plant for potable and fresh water supplies. 
 
 
Power will be generated on site by a 28 MW primary power station, operated on 
heavy fuel oil. A modern camp facility was constructed to cater for 
approximately 700 occupants. The camp currently houses approximately 550 
occupants, with another 150 occupants being housed in the old exploration camp. 
 
 
 
 
On behalf of Centamin Egypt Limited 
 
 
 
 
 
 
 
 
Josef El-Raghy 
Managing Director/CEO 
31 July 2009 
 
 
 
 
For more information please contact: 
 
 
+-------------------+---------------------------------------+--------------------+ 
| Centamin Egypt    |    Buchanan Communications Limited    |   Ambrian Partners | 
| Limited           |        + 44 (0) 207 7466 5000         |            Limited | 
| + 61 (8) 9316     |              Ben Willey               |  + 44 (0) 207 7634 | 
| 2640              |              Bobby Morse              |               4700 | 
| Josef El-Raghy    |                                       |      Richard Brown | 
| www.centamin.com  |                                       | Richard Greenfield | 
+-------------------+---------------------------------------+--------------------+ 
 
 
Quality Assurance and Control and Qualified Person 
 
 
The information in this report that relates to ore reserves has been compiled by 
Mr Tadek Wojtowicz and internally reviewed by Mr Andrew Pardey. Mr Pardey is a 
Member of the Australasian Institute of Mining and Metallurgy and is a full time 
employee of the Company. He has sufficient experience which is relevant to the 
style of mineralisation and type of deposit under consideration and to the 
activity he is undertaking, to qualify as a "Competent Person" as defined in the 
2004 Edition of the "Australasian Code for Reporting of Exploration Results, 
Mineral Resources and Ore Reserves" and is a "Qualified Person" as defined in 
the "National Instrument 43-101 of the Canadian Securities Administrators" and 
"CIM Definition Standards For Mineral Resources and Mineral Reserves" of 
December 2005 as prepared by the CIM Standing Committee on Reserve Definitions 
of the Canadian Institute of Mining. Mr Pardey's written consent has been 
received by the Company for this information to be included in this report in 
the form and context which it appears. 
 
The information in this report that relates to ore reserves has also been 
independently verified by Mr Pieter Doelman, an employee of Coffey Mining Pty 
Ltd Perth. Mr Doelman is a Member of the Australasian Institute of Mining and 
Metallurgy and has sufficient experience, relevant to the style of 
mineralisation and type of deposit under consideration and to the activity he is 
undertaking, to qualify as a  "Competent Person" as defined in the 2004 Edition 
of the "Australasian Code for Reporting of Exploration Results, Mineral 
Resources and Ore Reserves" and is a "Qualified Person" as defined in the 
"National Instrument 43-101 of the Canadian Securities Administrators" and the 
"CIM Definition Standards For Mineral Resources and Mineral Reserves" of 
December 2005 as prepared by the CIM Standing Committee on Reserve Definitions 
of the Canadian Institute of Mining. Mr Doelman consents to the inclusion of 
this estimate in reports. 
 
Information in this report which relates to exploration, geology, sampling and 
drilling is based on information compiled by geologist Mr Richard Osman who is a 
full time employee of the Company, and is a member of the Australasian Institute 
of Mining and Metallurgy with more than five years experience in the fields of 
activity being reported on, and is a 'Competent Person' for this purpose and is 
a "Qualified Person" as defined in "National Instrument 43-101 of the Canadian 
Securities Administrators". His written consent has been received by the Company 
for this information to be included in this report in the form and context which 
it appears. 
 
The assay samples were analysed by Ultra Trace Pty Ltd, Canning Vale, Western 
Australia. 
 
The information in this report that relates to mineral resources is based on 
work completed independently by Mr Nicolas Johnson, who is a Member of the 
Australian Institute of Geoscientists.  Mr Johnson is a full time employee of 
Hellman and Schofield Pty Ltd and has sufficient experience which is relevant to 
the style of mineralisation and type of deposit under consideration and to the 
activity which he is undertaking to qualify as a "Competent Person" as defined 
in the 2004 edition of the "Australasian Code for Reporting of Exploration 
Results, Mineral Resources and Ore Reserves" and is a "Qualified Person" as 
defined in "National Instrument 43-101 of the Canadian Securities 
Administrators".  Mr Johnson consents to the inclusion in the report of the 
matters based on his information in the form and context in which it appears. 
 
Refer to the Technical Report which was filed in May 2009 for further discussion 
of the extent to which the estimate of mineral resources/reserves may be 
materially affected by any known environmental, permitting, legal, title, 
taxation, socio-political, marketing or other relevant issue. 
. 
 
Table 4 - Significant Intersections June 2009 Quarter 
 
 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|  HOLE  |NORTH  | EAST  |DIP  |AZI  |  EOH   |FROM  | TO  |INTERVAL  |AUAR1  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|RCD569  |11300  |10883  |-88  |270  | 629.7  | 473  |479  |    6     | 1.52  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 549  |550  |    1     |  128  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1428  |11375  |10880  |-83  |270  |  655   | 251  |283  |    32    | 1.25  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 574  |582  |    8     | 4.10  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 579  |580  |    1     | 22.7  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 592  |634  |    42    | 1.21  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 595  |596  |    1     |  8.3  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 605  |607  |    2     |  7.9  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1429  |11900  |10810  |-68  |270  | 563.7  | 414  |426  |    12    | 1.34  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 425  |426  |    1     | 7.10  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 453  |472  |    19    | 1.33  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 462  |463  |    1     | 6.64  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1430  |10650  |10820  |-74  |270  | 249.5  | 196  |207  |    11    | 1.19  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1431  |11400  |10850  |-83  |270  | 786.1  |  87  | 91  |    4     | 1.53  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 306  |319  |    13    | 1.42  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 311  |312  |    1     |10.40  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 601  |605  |    4     | 8.59  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 602  |603  |    1     | 24.1  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 610  |627  |    17    |10.49  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 624  |625  |    1     |  138  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 641  |696  |    55    | 3.48  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 678  |690  |    12    |10.20  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 680  |681  |    1     |34.90  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1432  |10475  |10784  |-73  |270  | 692.7  | 314  |411  |    97    | 1.89  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 350  |352  |    2     | 7.07  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 378  |380  |    2     | 7.68  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 388  |391  |    3     | 4.52  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 407  |408  |    1     | 8.24  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 417  |421  |    4     | 28.1  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 646  |647  |    1     | 6.36  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1434  |10650  |10820  |-74  |270  | 798.5  |  72  | 80  |    8     | 1.27  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 157  |169  |    12    | 1.83  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 452  |471  |    19    | 2.87  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 454  |458  |    4     | 5.10  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 647  |656  |    9     | 1.16  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1435  |11250  |10950  |-84  |270  |  584   |  73  | 77  |    4     | 3.98  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  |  76  | 77  |    1     | 11.2  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |  85  | 97  |    12    | 1.14  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 246  |249  |    3     | 5.68  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 247  |248  |    1     | 15.8  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 340  |350  |    10    | 3.31  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 340  |341  |    1     | 14.1  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 499  |542  |    43    | 17.0  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 505  |506  |    1     | 22.9  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 525  |526  |    1     | 68.1  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 531  |533  |    2     |  279  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1436  |11950  |10828  |-65  |270  |  400   |  3   | 30  |    27    | 1.16  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 217  |230  |    13    | 1.01  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1438  |11475  |10770  |-80  |270  | 784.3  | 635  |702  |    67    | 1.05  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 635  |636  |    1     | 7.15  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1439  |12000  |10828  |-60  |270  | 463.6  |  2   | 31  |    29    | 1.55  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  |  17  | 18  |    1     | 9.51  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |  52  | 62  |    10    | 1.22  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1440  |11300  |10883  |-83  |270  | 683.3  | 569  |583  |    14    | 6.71  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 575  |579  |    2     | 69.5  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1442  |11925  |10810  |-60  |270  | 563.5  |  3   | 29  |    26    | 1.55  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1443  |11250  |10871  |-80  |270  | 870.1  | 688  |704  |    16    | 1.09  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 734  |758  |    24    | 1.69  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 744  |745  |    1     | 7.78  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 775  |791  |    16    | 1.40  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1445  |11675  |10760  |-82  |270  | 821.5  |  0   | 12  |    12    | 2.01  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1446  |11550  |10787  |-87  |270  |  753   | 339  |346  |    7     | 2.26  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 340  |341  |    1     | 10.6  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 636  |706  |    70    | 2.20  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 642  |643  |    1     | 12.1  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 686  |688  |    2     | 8.55  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1447  |11900  |10816  |-82  |270  |  585   | 362  |372  |    10    | 1.28  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 486  |489  |    3     | 2.14  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1448  |12050  |10798  |-77  |270  |112.18  |  67  | 75  |    8     | 1.34  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  |  73  | 74  |    1     | 5.69  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1450  |11500  |10778  |-70  |270  | 730.4  | 634  |644  |    10    | 1.24  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 655  |680  |    25    | 2.58  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 672  |674  |    2     | 8.43  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1452  |11725  |10800  |-78  |270  | 668.2  | 630  |653  |    23    | 1.23  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 631  |632  |    1     | 5.11  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        |      |     |          |       | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
| D1453  |11500  |10885  |-82  |270  | 729.3  | 581  |591  |    10    | 1.30  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 623  |644  |    21    | 1.73  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     | incl.  | 642  |643  |    1     | 5.81  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
|        |       |       |     |     |        | 672  |687  |    15    | 2.69  | 
+--------+-------+-------+-----+-----+--------+------+-----+----------+-------+ 
Note: Intervals shown in the table are down hole intercepts, drilled at high 
angles relative to the internal mineralized structures and the Sukari Porphyry; 
true widths do not apply or are not used in drilling the stockwork style 
mineralization at Sukari 
 
 
 
 
Please click on link below to see the full copy with pictures and site diagrams: 
(LSE to inset link to PDF) 
 
 
http://www.rns-pdf.londonstockexchange.com/rns/6550W_-2009-7-31.pdf 
 
 
This information is provided by RNS 
            The company news service from the London Stock Exchange 
   END 
 
 MSCILFLIDEILVIA 
 

Centamin (LSE:CEY)
Gráfica de Acción Histórica
De Jun 2024 a Jul 2024 Haga Click aquí para más Gráficas Centamin.
Centamin (LSE:CEY)
Gráfica de Acción Histórica
De Jul 2023 a Jul 2024 Haga Click aquí para más Gráficas Centamin.