3rd Quarter Preliminary Production Results (9113P)
11 Octubre 2011 - 1:00AM
UK Regulatory
TIDMCEY
RNS Number : 9113P
Centamin Egypt Limited
11 October 2011
Immediate Release 11(th) October 2011
Centamin Egypt Limited ("Centamin" or "the Company")
(LSE:CEY, TSX:CEE)
3(rd) Quarter Preliminary Production Results
Centamin Egypt Limited is pleased to announce its preliminary
production results from its Sukari Gold Project in Egypt for the
quarter ended 30 September 2011.
Total gold production for the quarter was 50,539 ounces, a 67%
increase from the corresponding quarter last year and a 5% increase
on the previous quarter's production. The resultant gold production
was underpinned by record quarterly throughput in the Sukari
process plant of 964kt (59% higher than the corresponding quarter
last year and 13% higher than the previous quarter), as the ramp up
to higher production rates progressed post-Stage 3
commissioning.
Open pit and underground production rates returned to budgeted
production rates with the resumption of regular delivery and
issuing of blasting products for the mine in late July. The open
pit delivered greater than 2.2Mt per month material movement for
both August and September (compared with 1.2Mt in July) and
underground ore production for the quarter increased to 58,000t (up
35% on Q2 2011). With higher material movements from the open pit,
the run of mine ore stockpile balance increased by 168kt to 456kt
by the end of the quarter.
Centamin remains on track to reach target production of
200-210,000oz at a cash cost of approximately $550/oz in 2011.
September 2011
Quarter September 2010
(estimate) June 2011 Quarter Quarter
-------------------- ------------------- ------------------ ---------------
Total Material
Movement - Open
Pit (kt) 5,747 3,030 4,916
-------------------- ------------------- ------------------ ---------------
Process Plant
Throughput (kt) 964 850 605
-------------------- ------------------- ------------------ ---------------
Underground Ore
Production (kt) 58 43 -
-------------------- ------------------- ------------------ ---------------
Gold Produced (oz) 50,539 47,991 30,243
-------------------- ------------------- ------------------ ---------------
Josef El-Raghy, Chairman of Centamin, said: "The Company is
pleased with the return to normal operations, the rapidly improving
performance of the process plant and the consistent development and
maturing of the underground operation, which positions Sukari well
for a strong and consistent performance in the future."
Notice of Results
Centamin will announce its results for the quarter ended 30
September 2011 (Q3) on Monday, 31 October 2011. The announcement
will be screened via the Regulatory News Service of the London
Stock Exchange at 7am (UK time). A conference call with the
Centamin management team will be held at 11am (UK time) on the day
of the Q3 results announcement. Dial in details for the conference
call will be announced at the time of the Q3 results.
For more information please contact:
Centamin Egypt Limited
Josef El-Raghy,
Executive Chairman
Katharine Sutton, Head
of Investor Relations
(katharine.sutton@centa +61 8 9316 2640 or
min.com) +20 3 5411 259
Buchanan
Bobby Morse
Gabriella Clinkard +44 (0) 20 7466 5000
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCMMBATMBJBBBB
Centamin (LSE:CEY)
Gráfica de Acción Histórica
De Jun 2024 a Jul 2024
Centamin (LSE:CEY)
Gráfica de Acción Histórica
De Jul 2023 a Jul 2024