Completion of Transmission
& Grid Interconnection Study for Proposed Renewable Power
Plant
Oracle Power PLC (AIM:ORCP), an
international project developer, together with its joint venture
company, Oracle Energy Limited ("Oracle Energy"), a developer of
green energy projects, is pleased to announce completion of the
Transmission & Grid Interconnection Study (the "Study") in
respect of its proposed 1.3GW hybrid renewable energy power plant
in Jhimpir, Sindh Province, Pakistan. Oracle Energy, in
collaboration with its joint development partner, China Electric
Power Equipment and Technology Co., Ltd. ("CET"), a subsidiary of
State Grid Corporation of China ("State Grid China"), engaged Power
Planners International (Pvt.) Ltd ("PPI"), to undertake the
Study. PPI is a distinguished company renowned for its
expertise in power system analysis and planning, particularly in
the domain of grid interconnection studies for renewable energy
projects.
The Study, entirely funded by State
Grid China, assessed the technical feasibility of interconnecting
the proposed 1.3GW Hybrid Renewable Energy Power Plant (the "Hybrid
RE PP"), which consists of 800MW solar power, 500MW wind power
generation and a suitable battery energy storage system, to provide
renewable power to the National Grid. Based on the updated
transmission plan and load forecast provided by the National
Transmission and Dispatch Company ("NTDC"), the Study proposes
interconnecting the plant to the 220kV Jhimpir-II Grid Station via
a direct 220kV double circuit transmission line of 35km in length,
using a quad bundle rail conductor. The Study outlines the
generation voltage for the Hybrid RE PP, which will be increased to
33kV using transformers at each inverter and collector group. The
net maximum output of the plant is expected to be 1,155MW.
Additionally, a 260MW battery energy storage system (BESS) is
proposed to enhance system reliability, and a static var
compensator (SVC) will be installed to maintain the required power
factor, thereby fulfilling NTDC Grid Code requirements.
Comprehensive load flow studies were
performed for peak and off-peak conditions during both summer and
winter periods, demonstrating the reliability of the proposed
transmission scheme under normal and contingency (N-1) conditions.
Short circuit and dynamic stability analyses confirmed that fault
currents are within rated capacities, and the system successfully
passed dynamic stability checks, ensuring resilience under fault
conditions.
The completed Study has now been
submitted to NTDC for review and approval by the Pakistan
Government. This approval process will be critical in advancing the
project towards implementation and the Company looks forward to
providing further updates in due course.
Oracle's CEO, Naheed Memon,
commented: "We are pleased to confirm the completion of
this key Study for our proposed hybrid renewable energy power plant
in Jhimpir. This milestone marks the culmination of extensive
investigative studies and sets the stage for the next phase of
detailed engineering design (FEED). The findings of the Study
provide a solid foundation for securing potential off-take
agreements for power. Our strategic focus remains on ultimately
seamlessly integrating renewable energy into the National Grid,
thereby enhancing energy security and promoting sustainable
development in Pakistan."
-ENDS-
For
further information contact:
Oracle Power PLC
Naheed Memon -
CEO
|
+44 (0) 20
7236 1177
|
Strand Hanson Limited (Nominated Adviser &
Broker)
Rory Murphy, Matthew Chandler, Rob
Patrick
|
+44 (0) 20
7409 3494
|
St
Brides Partners Limited (Financial PR)
Isabel de Salis, Susie
Geliher
|
oracle@stbridespartners.co.uk
|
About PPI
Power Planners International (Pvt.) Ltd is registered with the
Pakistan Engineering Council and accredited with registrations in
England and Wales, the Saudi Electricity Company (SEC), and the
Alternative Energy Development Board. PPI comprises a group of
professionals who possess highly specialised skills, vast and
profound experience, and expertise in the advanced and latest
state-of-the-art software prevailing in the contemporary power
system industry. Having a long background in power system analysis
and planning with WAPDA and other electric utilities, they were
ideally placed to efficiently and promptly undertake the requisite
Study.