Turquoise Hill Resources Ltd. (TSX: TRQ) (NYSE: TRQ) (Turquoise
Hill or the Company) today announced its financial results for the
period ended September 30, 2022. All figures are in U.S. dollars
unless otherwise stated.
Turquoise Hill’s Interim CEO, Steve Thibeault stated, “During
the third quarter, Turquoise Hill management remained focused on
maintaining a safe and efficient operation at the Oyu Tolgoi mine
and on advancing the Oyu Tolgoi underground project. I am pleased,
that thanks to the commitment of our people, we were able to
deliver good results on both fronts.
Safety has always been and will remain our top priority, so it
is gratifying to report that our Oyu Tolgoi team turned in a very
solid health and safety performance achieving an all injury
frequency rate of 0.19 for 200,000 hours worked for the first three
quarters of the year.
From a production perspective, we increased our gold production
guidance for the year and are on track to meet our revised copper
production guidance.
During the quarter we made excellent progress on the underground
project as we fired the 7th drawbell and started commissioning the
second truck chute. By early November subsequent to the quarter
end, we had fired another four drawbells, all ahead of schedule.
Given progress to date, and considering natural caving conditions,
we continue to expect to achieve sustainable production from Panel
0 in the first quarter of 2023 which is earlier than originally
anticipated.
We believe that our third quarter has put us in a good position
to end the year with a robust operation and with the project poised
to reach a major milestone in the first quarter of 2023.
Regarding the transaction with Rio Tinto and its impact on the
future of the Company.
If our minority shareholders approve the transaction we will
proceed with the orderly wind-up and delisting of the Company and
will ensure that our employees are treated fairly and respectfully
throughout that process.
If the transaction does not proceed, we will continue to manage
the Company on a standalone basis. Our immediate priority will be
to address our liquidity requirements by implementing all elements
of the binding funding Heads of Agreement with Rio Tinto.
Oyu Tolgoi is a tier one, low cost, high grade operation with a
long life of mine that will deliver value for Turquoise Hill
stakeholders for decades to come.”
FINANCIAL AND OPERATIONAL HIGHLIGHTS
- Oyu Tolgoi surface operations1 and underground workforce posted
an AIFR of 0.19 per 200,000 hours worked for the nine months ended
September 30, 2022.
- In Q3’22, Oyu Tolgoi produced 36.3 thousand tonnes of copper in
concentrate and 42.7 thousand ounces of gold in concentrate.
- Mill throughput of 10.68 million tonnes in Q3’22 was 14% higher
than Q3’21 and 10% higher than Q2’22, which is in line with
expectations due to higher mill availability.
- Copper production guidance for 2022 remains within the range of
110,000 to 150,000 tonnes while 2022 gold production guidance has
been revised from a range of 150,000 – 170,000 ounces to 165,000 –
185,000 ounces.
- Continued progress in underground on-footprint construction and
blasting saw firing of the 7th drawbell during Q3’22 and
commencement of commissioning of the second truck chute. Four
further drawbells were blasted during October and early November
bringing the total number fired to 11, and sustainable production,
which is anticipated once between 16 and 21 drawbells have been
blasted, subject to the natural caving conditions encountered, is
now anticipated in Q1’23.
- Turquoise Hill currently estimates its base case incremental
funding requirement to be in the range of $3.7 billion to $4.0
billion (June 30, 2022: base case estimate of $3.6 billion).
Contributing factors to this increase include updated commodity
pricing and other market-based assumptions, including LIBOR and
inflation, and a draft operating plan for 2023 received from OT
LLC.
- As at September 30, 2022, Turquoise Hill had $0.2 billion of
available liquidity in the form of cash and cash equivalents, which
under current projections would be sufficient to meet the Company’s
requirements, including funding of underground capital
expenditures, into December 2022. Thereafter, the Company plans to
rely on the various sources of funding available under the Amended
HoA2 (see the section “Funding of OT LLC by Turquoise Hill” of this
press release) to provide it with sufficient liquidity and
resources to meet its minimum obligations for a period of at least
12 months from the balance sheet date of September 30, 2022. The
risks inherent in delivery of the Amended HoA funding plan, some of
which are outside of the Company’s control, result in the existence
of a material uncertainty that casts a significant doubt about the
Company’s ability to continue as a going concern.
- Revenue of $391.1 million in Q3’22 decreased by $271.0 million
or 40.9% from $662.1 million in Q3’21 due to 13.4% and 67.2%
decreases in copper and gold production, respectively, which were
driven by lower head grades from the planned transition of mining
to the next phase of operations earlier in 2022 and processing of
lower grade stockpile material. Revenue was also impacted by 17.4%
and 3.4% decreases in average copper and gold prices, respectively,
from Q3’21.
_____________________________
1Surface operations denotes
open-pit operations plus on surface infrastructure benefitting both
the open pit and underground including, but not limited to, the
concentrator, tailings storage facility and central heating plant.
Of the 10,685 thousand tonnes of material processed by the mill in
Q3’22, approximately 543 thousand tonnes was underground
development material.
2The Amended HoA is the third
amended and restated heads of agreement dated September 5, 2022
entered into between the Company and Rio Tinto. Please refer to the
Section titled “Funding of OT LLC by Turquoise Hill” on page 11 of
this press release for further information.
- Income for the period was $40.0 million in Q3’22 versus $54.4
million in Q3’21. This decrease was mainly the result of $271.0
million lower revenue and $44.0 million higher cost of sales,
partially offset by $301.9 million lower income and other tax
charges. Cost of sales was impacted by inflationary pressures,
including higher input prices. A $6.7 million tax charge was
recorded in Q3’22 versus $308.5 million in Q3’21. Income
attributable to owners of Turquoise Hill in Q3’22 was $46.6 million
($0.23 per share) versus $55.7 million ($0.28 per share) in
Q3’21.
- Cost of sales in Q3’22 was $2.76 per pound of copper sold3 and
C1 cash costs were $1.72 per pound of copper produced4. All-in
sustaining costs were $2.60 per pound of copper produced 4 .
- Total operating cash costs5 of $228.0 million in Q3’22
increased 1.7% from $224.1 million in Q3’21, which is largely due
to inflationary pressures on prices for critical supplies including
fuel, power and explosives, partially offset by higher deferred
stripping due to the planned transition of mining from Phase 4B to
Phase 5A and lower royalty costs due to lower revenue.
- Expenditures on property, plant and equipment6 in Q3’22 were
$267.6 million, which included $236.0 million of capital
expenditures on the underground project7. Capital expenditures on
the underground project7 included $109.9 million of underground
sustaining capital expenditures7. At September 30, 2022, total
capital expenditures on the underground project7 since January 1,
2016 were $6.0 billion, including $0.6 billion of underground
sustaining capital expenditures7.
- Cash used in operating activities before interest and tax was
$8.4 million versus cash generated from operating activities before
interest and tax of $382.5 million in Q3’21. This change was
primarily due to $271.0 million lower revenue, $44.0 million higher
cost of sales and $3.9 million higher other operating cash costs.
These higher costs were largely due to inflationary pressures on
prices for critical supplies including fuel, power and explosives.
Net cash used in operating activities was $33.6 million versus net
cash generated from operating activities of $382.0 million in
Q3’21. In addition to the factors discussed above, this change was
also impacted by $26.1 million higher interest paid in Q3’22 due to
a timing difference on payment of certain completion support fees
to Rio Tinto.
- The special meeting of Turquoise Hill shareholders, previously
scheduled for November 15, 2022 at 10:30 a.m. (Eastern time), (the
Special Meeting) has been adjourned to a date to be determined (see
the section “Privatisation Proposal Received from Rio Tinto” of
this press release).
_____________________________
3 Cost of sales per pound of copper sold
is a supplementary financial measure. Please refer to the Section
titled “Non-GAAP and Other Financial Measures” on page 23 of this
press release for further information. 4 C1 cash costs per pound of
copper produced and all-in sustaining costs per pound of copper
produced are non-GAAP ratios. Please refer to the Section titled
“Non-GAAP and Other Financial Measures” on page 23 of this press
release for further information. 5 Total operating cash costs is a
non-GAAP financial measure. Please refer to the Section titled
“Non-GAAP and Other Financial Measures” on page 23 of this press
release for further information. 6 In this press release,
expenditures on property, plant and equipment are sometimes
alternatively referred to as “capital expenditures on a cash
basis”. 7 Capital expenditures on the underground project and
underground sustaining capital expenditures are supplementary
financial measures. Please refer to the Section titled “Non-GAAP
and Other Financial Measures” on page 23 of this press release for
further information.
OPERATIONAL OUTLOOK FOR 2022
Oyu Tolgoi is expected to produce 110 to 150 thousand tonnes of
copper and 165 to 185 thousand ounces of gold in concentrates in
2022 from processing ore from the open pit, underground and
stockpiles. Gold production guidance has been revised upward from a
previous forecast range of 150 to 170 thousand ounces. The higher
gold guidance reflects more reliable grade performance from mining
of Phase 5 during Q3’22 with related higher recoveries. This builds
on the higher gold production from completion of Phase 4B in
H1’22.
Total operating cash costs8 for 2022 are now expected to be in
the range of $855 million to $910 million compared to previous
guidance of $850 million to $925 million, which is largely due to
deferral of non-critical activities to contain inflationary
pressures for key inputs, including fuel and ammonium nitrate.
Capital expenditures on surface operations9 for 2022 are
expected to remain within the previously disclosed guidance range
of $140 million to $170 million. Capital expenditures on the
underground project9 are now expected to be lower at $1.0 billion
to $1.1 billion for 2022 compared to original guidance of $1.1
billion to $1.3 billion, resulting from improvements to
construction productivity and the slower ramp-up and onboarding of
on-site construction resources throughout 2022. Capital
expenditures on the underground project9 are expected to be
comprised of $600 million to $700 million of underground
development capital expenditures9 and $400 million to $500 million
of underground sustaining capital expenditures9.
Capital expenditures on surface operations9 is mainly comprised
of deferred stripping, equipment purchases, tailings storage
facility construction and maintenance componentisation. Capital
expenditures on the underground project9 is inclusive of VAT and
capitalised management services payments but excludes capitalised
interest.
2022 C1 cash costs are expected to be in the range of positive
$1.55 to positive $2.05 per pound of copper produced10, which
compares to previous guidance of positive $1.95 to positive $2.35
per pound of copper produced. 2022 is higher than 2021 due to lower
gold production in 2022. The reduction in C1 cash costs from
previous guidance is due to improved grade performance for gold and
cost optimisations helping to offset the inflationary pressures
noted above. Unit cost guidance assumes the midpoint of the
expected 2022 copper and gold production ranges and a gold
commodity price assumption of $1,808 per ounce.
Estimates of future production, expenditures on property, plant
and equipment, total operating cash costs and C1 cash costs per
pound of copper produced presented in this press release are based
on mine plans that reflect the expected method by which the Company
will mine reserves at Oyu Tolgoi. Actual gold and copper production
and associated costs may vary from these estimates due to a number
of operational and non-operational risk factors (see the section
“Forward-Looking Statements and Forward-Looking Information” of the
Company’s Q3 2022 MD&A for a description of certain risk
factors that could cause actual results to differ materially from
these estimates).
_____________________________
8 Total operating cash costs is a non-GAAP
measure that is forward-looking information. Please refer to the
Section titled “Non-GAAP and Other Financial Measures” on page 23
of this press release for further information. 9 Underground
development capital expenditures, underground sustaining capital
expenditures, capital expenditures on surface operations and
capital expenditures on the underground project are all
supplementary financial measures. Please refer to the Section
titled “Non-GAAP and Other Financial Measures” on page 23 of this
press release for further information. 10 C1 cash costs per pound
of copper produced is a non-GAAP ratio. Please refer to the Section
titled “Non-GAAP and Other Financial Measures” on page 23 of this
press release for further information.
OUR BUSINESS
Turquoise Hill is an international mining company focused on the
operation and continued development of the Oyu Tolgoi copper-gold
mine in Mongolia, which is the Company’s principal and only
material mineral resource property. The Company’s ownership of the
Oyu Tolgoi mine is held through a 66% interest in Oyu Tolgoi LLC
(OT LLC); the remaining 34% interest is held by Erdenes Oyu Tolgoi
LLC (Erdenes or EOT), a Mongolian state-owned entity.
The Oyu Tolgoi property is located approximately 550 kilometres
south of Ulaanbaatar, Mongolia’s capital city, and 80 kilometres
north of the Mongolia-China border. The property is cut by the Oyu
Tolgoi trend, a 12 kilometres north-south orientated corridor which
is host to the known deposits, Hugo North, Hugo South, Oyut and
Heruga. Open-pit mining operations commenced at Oyut in 2013. The
Hugo North deposit (Lift 1) is currently being developed as an
underground operation with sustainable production expected to
commence in Q1’23.
The copper concentrator plant, with related facilities and
necessary infrastructure, was originally designed to process
approximately 100,000 tonnes of ore per day from the Oyut open pit.
Since 2014, the concentrator has consistently achieved a throughput
of over 105,000 tonnes per day due to improvements in operating
practices. Concentrator throughput for 2022 is targeted at over
110,000 tonnes per day and expected to be approximately 40 million
tonnes for the year due to improvements in concentrator performance
and more favourable ore characteristics.
As at September 30, 2022, Oyu Tolgoi had a total workforce
(employees and contractors), including for underground project
construction, of approximately 19,100 workers, of which over 97%
were Mongolian.
SELECTED FINANCIAL METRICS (1)
Three months ended Nine months ended ($ in millions,
unless otherwise noted)
3Q
3Q
Change
3Q
3Q
Change
2022
2021
%
2022
2021
%
Restated (6)
Restated (6)
Revenue
391.1
662.1
(40.9%)
1,195.8
1,518.5
(21.3%)
Income for the period
40.0
54.4
(26.5%)
527.7
514.4
2.6%
Income attributable to owners of Turquoise Hill Resources Ltd
46.6
55.7
(16.3%)
404.4
395.3
2.3%
Basic and diluted earnings per share attributable to owners of
Turquoise Hill Resources Ltd
0.23
0.28
(17.9%)
2.01
1.96
2.6%
Revenue by metals in concentrates Copper
288.9
395.8
(27.0%)
845.7
926.4
(8.7%)
Gold
96.8
260.0
(62.8%)
335.4
578.0
(42.0%)
Silver
5.4
6.3
(14.3%)
14.7
14.1
4.3%
Cost of sales
254.6
210.6
20.9%
649.1
451.8
43.7%
Production and delivery costs
205.6
160.5
28.1%
515.9
328.2
57.2%
Depreciation and depletion
49.1
50.1
(2.0%)
133.1
123.5
7.8%
Capital expenditure on cash basis (2)
267.6
209.0
28.0%
758.4
686.6
10.5%
Underground development capital expenditures
126.1
129.0
(2.2%)
377.4
468.7
(19.5%)
Underground sustaining capital expenditures
109.9
63.7
72.5%
280.6
174.5
60.8%
Capital expenditures on surface operations
31.6
16.3
93.9%
100.4
43.4
131.3%
Royalty expenses
16.8
37.6
(55.3%)
70.2
82.8
(15.2%)
Total operating cash costs (3)
228.0
224.1
1.7%
686.5
638.7
7.5%
Unit costs ($) . Cost of sales (per pound of copper sold) (4)
2.76
2.06
34.0%
2.75
1.95
41.0%
C1 (per pound of copper produced) (5)
1.72
(0.60)
(386.7%)
1.57
0.08
1,862.5%
All-in sustaining (per pound of copper produced) (5)
2.60
0.08
3,150.0%
2.65
0.65
307.7%
Mining costs (per tonne of material mined) (5)
2.53
2.08
21.6%
2.40
2.20
9.1%
Milling costs (per tonne of ore treated) (5)
6.91
8.01
(13.7%)
6.86
7.10
(3.4%)
G&A costs (per tonne of ore treated) (4)
3.28
3.63
(9.6%)
4.41
4.02
9.7%
Net cash generated from (used in) operating activities
(33.6)
382.0
(108.8%)
317.8
467.2
(32.0%)
Cash generated from (used in) operating activities before interest
and tax
(8.4)
382.5
(102.2%)
429.7
935.5
(54.1%)
Interest paid
27.0
0.9
2,900.0%
112.6
111.9
0.6%
Total assets
14,773
13,969
5.8%
14,773
13,969
5.8%
Total non-current financial liabilities
3,791
4,422
(14.3%)
3,791
4,422
(14.3%)
(1)
All financial information in this press
release should be reviewed in conjunction with the Company‘s
consolidated financial statements for the reporting periods
indicated.
(2)
Capital expenditures on a cash basis is
split between underground development capital expenditures and
underground sustaining capital expenditures and capital
expenditures on surface operations, all supplementary financial
measures. Please refer to the Section titled – “Non-GAAP and Other
Financial Measures” on page 23 of this press release for further
information.
(3)
Total operating cash costs is a non-GAAP
financial measure. Please refer to the Section titled – “Non-GAAP
and Other Financial Measures” on page 23 of this press release for
further information.
(4)
Cost of sales per pound of copper sold and
General & Administrative (G&A) costs per tonne of ore
treated are supplementary financial measures. Please refer to the
Section titled – “Non-GAAP and Other Financial Measures” on page 23
of this press release for further information.
(5)
C1 cash costs per pound of copper
produced, all-in sustaining costs per pound of copper produced,
mining costs per tonne of material mined, and milling costs per
tonne of ore treated are non-GAAP ratios which are not standardised
financial measures and are not intended to replace measures
prepared in accordance with IFRS. Please refer to the Section
titled – “Non-GAAP and Other Financial Measures” on page 23 of this
press release for further information.
(6)
Prior year comparatives have been restated
for adoption of the IAS16 amendment to Property, Plant and
Equipment: Proceeds before intended use. Please refer to the
Section titled “Recent Accounting Pronouncements” on page 25 of the
Company’s Q3 2022 MD&A for further information.
Q3’22 versus Q3’21
- Revenue of $391.1 million in Q3’22 decreased by $271.0 million
or 40.9% from $662.1 million in Q3’21 due to 13.4% and 67.2%
decreases in copper and gold production, respectively, which were
driven by lower head grades from the planned transition of mining
to the next phase of operations earlier in 2022 and processing of
lower grade stockpile material. Revenue was also impacted by
decreases of 17.4% and 3.4% in average copper and gold prices,
respectively, from Q3’21.
- Income for the period was $40.0 million in Q3’22 versus $54.4
million in Q3’21. This decrease was mainly the result of $271.0
million lower revenue and $44.0 million higher cost of sales,
partially offset by $301.9 million lower income and other tax
charges. Cost of sales was impacted by inflationary pressures,
including higher input prices. A $6.7 million tax charge was
recorded in Q3’22 versus $308.5 million in Q3’21. Income
attributable to owners of Turquoise Hill in Q3’22 was $46.6 million
($0.23 per share) versus $55.7 million ($0.28 per share) in
Q3’21.
- Cost of sales of $254.6 million in Q3’22 increased from $210.6
million in Q3’21 due to higher costs from inflationary pressures on
input prices as well as higher unit costs from lower production.
These were offset by a 5.9% decrease in sold concentrate volumes.
Onsite concentrate inventory levels have remained at target levels
since Q2’22.
- Expenditures on property, plant and equipment were $267.6
million in Q3’22 versus $209.0 million in Q3’21, comprised of
$236.0 million (Q3’21: $192.7 million) in capital expenditures on
the underground project11, including $109.9 million (Q3’21: $63.7
million) in underground sustaining capital expenditures11, as well
as $31.6 million (Q3’21: $16.3 million) in capital expenditures on
surface operations11.
_____________________________
11 Capital expenditures on the underground
project, underground sustaining capital expenditures and capital
expenditures on surface operations are supplementary financial
measures. Please refer to the Section titled “Non-GAAP and Other
Financial Measures” on page 23 of this press release for further
information.
- Total operating cash costs12 of $228.0 million in Q3’22
increased 1.7% from $224.1 million in Q3’21, largely due to
inflationary pressures on prices for critical supplies including
fuel, power and explosives, partially offset by higher deferred
stripping due to the planned transition of mining from Phase 4B to
Phase 5A and lower royalty costs from lower revenue.
- Cost of sales of $2.76 per pound of copper sold13 in Q3’22
increased 34.0% from $2.06 per pound of copper sold in Q3’21,
reflecting higher operating cash costs and an increase in unit
fixed costs from lower metal production and copper head
grades.
- Oyu Tolgoi’s C1 cash costs of $1.72 per pound of copper
produced14 in Q3’22 increased from negative $0.60 per pound of
copper produced in Q3’21, primarily reflecting the impact of a
$163.2 million decrease in gold revenue following the planned
transition of mining to the next phase of operations earlier in
2022. Additionally, total operating cash costs12 were higher and
copper produced was lower compared to Q3’21.
- All-in sustaining costs of $2.60 per pound of copper produced14
in Q3’22 increased from $0.08 per pound of copper produced in
Q3’21. All-in sustaining costs were impacted by the same factors as
C1 cash costs as well as a $15.3 million increase in capital
expenditures on surface operations due to higher spend on
maintenance componentisation and the tailings storage facility,
higher deferred stripping from the planned change in mine sequence
and commencement of the Gashuun Sukhait (GSK) road in 2022.
- Mining costs of $2.53 per tonne of material mined14 in Q3’22
increased 21.6% from $2.08 per tonne of material mined in Q3’21.
The increase was mainly driven by inflationary pressures on prices
including fuel, explosives and tires. The increase in mining costs,
on a unit cost basis, was offset by a 15.6% increase in open pit
material mined from 22.6Mt in Q3’21 to 26.1Mt in Q3’22.
- Milling costs of $6.91 per tonne of ore treated14 in Q3’22
decreased 13.7% from $8.01 per tonne of ore treated in Q3’21 due to
the higher mill throughput due to higher mill availability and
slightly lower milling costs.
- G&A costs of $3.28 per tonne of ore treated15 in Q3’22
decreased 9.6% from $3.63 per tonne of ore treated in Q3’21. The
decrease is mainly due to higher mill throughput due from higher
mill availability.
- Cash used in operating activities before interest and tax was
$8.4 million versus cash generated from operating activities before
interest and tax of $382.5 million in Q3’21. This change was
primarily due to $271.0 million lower revenue, $44.0 million higher
cost of sales and $3.9 million higher other operating cash costs.
These higher costs were largely due to inflationary pressures on
prices for critical supplies including fuel, power and explosives.
Net cash used in operating activities was $33.6 million versus net
cash generated from operating activities of $382.0 million in
Q3’21. In addition to the factors discussed above, this change was
also impacted by $26.1 million higher interests paid in Q3’22 due
to a timing difference of payments of certain completion support
fees to Rio Tinto.
_____________________________
12 Total operating cash costs is a
non-GAAP financial measure. Please refer to the Section titled
“Non-GAAP and Other Financial Measures” on page 23 of this press
release for further information. 13 Cost of sales per pound of
copper sold is a supplementary financial measure. Please refer to
the Section titled “Non-GAAP and Other Financial Measures” on page
23 of this press release for further information. 14 C1 cash costs
per pound of copper produced, all-in sustaining costs per pound of
copper produced, mining costs per tonne of material mined and
milling costs per tonne of ore treated are non-GAAP ratios. Please
refer to the Section titled “Non-GAAP and Other Financial Measures”
on page 23 of this press release for further information. 15
G&A costs per tonne of ore treated is a supplementary financial
measure. Please refer to the Section titled “Non-GAAP and Other
Financial Measures” on page 23 of this press release for further
information.
OYU TOLGOI
Operations, People, Safety Performance and COVID-19
Update
The safety and wellbeing of our workers continues to be our
major focus. The Oyu Tolgoi surface operations and underground
workforce posted an AIFR of 0.19 per 200,000 hours worked for the
nine months ended September 30, 2022.
During Q3’22, COVID-19 cases identified at Oyu Tolgoi have
continued at low levels and the testing regime has been eased.
Following the recent relaxation of COVID-19 government-initiated
restrictions in Mongolia, Oyu Tolgoi has progressively restarted
work on project facilities with workforce numbers now at full
capacity.
During Q3’22, COVID-related controls remained a factor in
cross-border shipping rates into China; however, concentrate
inventory levels on site remained at or near target levels.
The global supply chain impacts relating to the Russia-Ukraine
conflict continue and, in response, the business continues to
closely monitor and hold greater inventory levels of certain
critical supplies.
Selected Operational Metrics
Oyu Tolgoi Production Data
All data represents full production and sales on a 100%
basis
3Q
3Q
Change
9 months
9 months
Change
2022
2021
2022
2021
Open pit material mined (‘000 tonnes)
26,102
22,588
15.6%
76,038
61,005
24.6%
Ore treated (‘000 tonnes)
10,685
9,336
14.4%
29,951
28,550
4.9%
Average mill head grades: Copper (%)
0.42
0.53
(20.8%)
0.41
0.52
(21.2%)
Gold (g/t)
0.22
0.63
(65.1%)
0.27
0.60
(55.0%)
Silver (g/t)
1.32
1.29
2.3%
1.24
1.26
(1.6%)
Concentrates produced (‘000 tonnes)
173.6
191.9
(9.5%)
463.9
567.0
(18.2%)
Average concentrate grade (% Cu)
20.9
21.9
(4.6%)
20.9
21.9
(4.6%)
Production of metals in concentrates: Copper (‘000 tonnes)
36.3
41.9
(13.4%)
97.1
124.1
(21.8%)
Gold (‘000 ounces)
43
131
(67.2%)
150
390
(61.5%)
Silver (‘000 ounces)
256
249
2.8%
668
739
(9.6%)
Concentrate sold (‘000 tonnes)
211.1
224.4
(5.9%)
534.7
503.3
6.2%
Sales of metals in concentrates: Copper (‘000 tonnes)
41.8
46.4
(9.9%)
107.0
105.0
1.9%
Gold (‘000 ounces)
56
149
(62.4%)
181
333
(45.6%)
Silver (‘000 ounces)
282
278
1.4%
684
591
15.7%
Metal recovery* (%) Copper
80.9
83.9
(3.6%)
80.2
83.6
(4.1%)
Gold
56.6
68.7
(17.6%)
58.6
70.3
(16.6%)
Silver
57.0
64.1
(11.1%)
56.4
64.0
(11.9%)
*Metal recovery is a function of head
grade and reflects grades delivered in the quarter.
Open Pit Operations, Underground Project and
Operations
During Q3’22, the combined open pit and underground operations
produced 36.3 thousand tonnes of copper in concentrate and 42.7
thousand ounces of gold in concentrate. Consistent with
expectations, copper and gold production were lower compared with
Q3’21. Mill feed for Q3’22 included approximately 543 thousand
tonnes @ 0.82% Cu and 0.23g/t Au of underground development
material. The remaining 10.1 million tonnes of mill feed was
sourced from Phase 5, Phase 6 and open-pit stockpiles. Mill head
grades will remain low through to the end of 2022 as direct mill
feed will continue to be supplemented by low grade stockpiles.
As previously disclosed, the open-pit optimisation work to
improve near term value has been reflected in an updated mine plan
in Q3’22. The updated mine plan incorporates modest increases in
metal delivery over the next 2 years.
Shaft 3 and Shaft 4 cumulative sinking levels were at 28816
metres and 41016 metres, below ground level, respectively. The
progress rates for these shafts improved during Q3’22 due to an
optimisation programme, which commenced in Q1’22, and continued
progress on these initiatives is necessary to continue to be
aligned with the 2022 Cost and Schedule Reforecast (2022
Reforecast). Shafts 3 and 4 commissionings are expected in
mid-2024, which is consistent with the Company’s previous
disclosure. Construction of the final major stage of the materials
handling infrastructure continues, including civil and underground
works for the conveyor to surface. Undercut blasting and
on-footprint construction work continued to progress. Commissioning
of the second truck chute has commenced, three further drawbells
were blasted during October, in addition to the 11th drawbell being
completed in early November, all ahead of schedule. Sustainable
production, which is anticipated once between 16 and 21 drawbells
have been blasted, subject to the natural caving conditions
encountered, is now anticipated in Q1’23.
Milestone
2020 OTTR
Q2 2022 MD&A
Actual or Currently Projected
Dates (3)
Start Undercut blasting
July 2021
January 2022 (Actual)
January 2022 (Actual)
MHS 1 (including Crusher 1)
commissioning
Q4’21
February 2022 (Actual)
February 2022 (Actual)
First drawbell blasted (1)
May 2022
June 2022 (Actual)
June 2022 (Actual)
Sustainable Production
(sustainable cave propagation)
February 2023
(~30 drawbells active(2))
H1’23
(~21 drawbells active (2))
Q1’23
(~16-21 drawbells active(2))
Shaft 3 commissioned
H1’22
H1’24(3)
H1’24(3)
Shaft 4 commissioned
H1’22
H1’24(3)
H1’24(3)
First drawbell Panel 2
Q4’24
H1’26
H1’26(4)
First drawbell Panel 1
H2’26
H1’27
H1’27(4)
(1)
Despite an approximate 6-month delay to
undercut commencement, first drawbell timing remained broadly in
line with the 2020TR.
(2)
Design refinements identified that a minor
modification to undercut sequence, following additional
geotechnical assessment of cave initiation conditions, changed the
estimated number of drawbells to reach critical hydraulic radius,
which is the point at which sustainable production is anticipated
to commence. Critical hydraulic radius is an estimated factor,
based on the best available data but some variability in the exact
number of drawbells needed to reach critical hydraulic radius could
occur, with the potential for the requirement to be between 16 and
21 drawbells.
(3)
Shaft 3 and 4 progress continues to be
closely monitored against the 2022 Reforecast.
(4)
A preliminary assessment of the impact of
the previously announced shaft delays on the commencement of Panel
1 and Panel 2 has been included in these milestones.
_____________________________
16 As at September 25, 2022
OT LLC spent $267.6 million on capital expenditures on the
underground project17 during Q3’22, including $236.0 million of
underground sustaining capital expenditures17. Total capital
expenditures on the underground project17 from January 1, 2016 to
September 30, 2022 were approximately $6.0 billion, including $0.6
billion of underground sustaining capital expenditures17. Capital
expenditures on the underground project17 includes VAT and
capitalised management services payments but excludes capitalised
interest. In addition, OT LLC had contractual obligations18 of $0.5
billion as at September 30, 2022. From the restart of project
development in 2016 through September 30, 2022, the Oyu Tolgoi
underground project has committed over $4.4 billion to Mongolian
vendors and contractors.
Hugo North Design Refinements
Study work for Panels 1 and 2, which are required to support the
ramp-up to 95,000 tonnes of ore per day, remains on track for
completion in H1’23. During Q2’22, updated designs for Panel 2
North were completed and lateral development has commenced in this
area.
Additional data continues to be collected from the surface and
underground drilling programmes. During Q3’22 and for the remainder
of 2022, the drilling programme continues to target Lift 2 and
future mining areas in the Lift 1 horizon, which are currently
excluded from the Mineral Reserve.
FUNDING OF OT LLC BY TURQUOISE HILL
In accordance with the Amended and Restated Shareholders’
Agreement dated June 8, 2011 (ARSHA), Turquoise Hill has funded OT
LLC’s cash requirements beyond internally generated cash flows by a
combination of equity investment and shareholder debt.
For amounts funded by debt, OT LLC must repay such amounts,
including accrued interest, before it can pay common share
dividends. As at September 30, 2022, the aggregate outstanding
balance of shareholder loans extended by subsidiaries of the
Company to OT LLC was $8.8 billion, including accrued interest of
$2.7 billion. These loans bear interest at an effective annual rate
of LIBOR plus 6.5%.
In accordance with the ARSHA, a subsidiary of the Company had
previously funded the common share investments in OT LLC on behalf
of state-owned Erdenes. These funded amounts, also referred to as
carry account loans, earned interest at an effective annual rate of
LIBOR plus 6.5% and were expected to be repayable by Erdenes to a
subsidiary of the Company via a pledge over Erdenes’ share of OT
LLC common share dividends. Erdenes also had the right to reduce
the outstanding balance by making cash payments at any time. As
announced on January 24, 2022, the Company waived in full the
cumulative $2.4 billion in non-recourse carry account loans to
Erdenes. The loans comprised $1.4 billion of equity invested in OT
LLC by the Company on behalf of Erdenes plus $1.0 billion of
unrecognised interest as at January 25, 2022, the date that the
waiver was formally granted to and acknowledged by Erdenes.
_____________________________
17 Capital expenditures on the underground
project and underground sustaining capital expenditures are
supplementary financial measures. Please refer to the Section
titled “Non-GAAP and Other Financial Measures” on page 23 of this
press release for further information. 18 Contractual obligations
is a non-GAAP financial measure. Please refer to the Section titled
“Non-GAAP and Other Financial Measures” on page 23 of this press
release for further information.
On December 30, 2021, the Parliament of Mongolia passed
Resolution 103 to resolve the outstanding issues among the Company,
Rio Tinto and the Government of Mongolia in relation to the
implementation of Resolution 92 (see the section “Government
Relations – Renewed Partnership with Government of Mongolia” of
this press release). Resolution 103 placed financing debt
restrictions that limit the Company’s ability to fund OT LLC with
shareholder debt or to carry common share investments in OT LLC on
behalf of Erdenes until sustainable production is achieved.
As at September 30, 2022, Turquoise Hill had $0.2 billion of
available liquidity in the form of cash and cash equivalents, which
under current projections would be sufficient to meet the Company’s
requirements, including funding of underground capital
expenditures, into December 2022. Thereafter, the Company plans to
rely on the various sources of funding available under the Amended
HoA to provide it with sufficient liquidity and resources to meet
its minimum obligations for a period of at least 12 months from the
balance sheet date of September 30, 2022. The risks inherent in
delivery of the Amended HoA funding plan, some of which are outside
of the Company’s control, result in the existence of a material
uncertainty that casts a significant doubt about the Company’s
ability to continue as a going concern.
The Amended HoA amends, restates and supersedes the previous
versions of this agreement between the Company and Rio Tinto. It is
the fourth iteration of this agreement. The previous versions are
as follows with each amending, restating and superseding its
respective predecessor version:
- Amended and Restated Heads of Agreement dated May 18,
2022;
- Amended and Restated Heads of Agreement dated January 24,
2022;
- Heads of Agreement entered into on April 9, 2021; and
- the non-binding Memorandum of Understanding dated September 9,
2020.
The key elements of the Amended HoA include:
- A commitment by Rio Tinto to make available to Turquoise Hill
by way of one or more secured advances (the Early Advance) up to
$650 million, which shall be made to the extent there are no funds
available to the Company and its subsidiaries (after allowing for
the need for cash reserves for working capital purposes of $200
million in the aggregate). If it is anticipated that the funding
shortfall, if any, for March 2023, will exceed the remaining funds
available under the Early Advance, the Company and Rio Tinto will
in good faith discuss increasing the Early Advance by the lesser of
such shortfall and $100 million;
- A commitment by Rio Tinto to provide additional bridge
financing to the Company on the same terms as the Early Advance in
the event that the Company is required to provide additional
funding for Oyu Tolgoi in respect of the December 2022 scheduled
principal repayment of $362 million under the Oyu Tolgoi project
finance facility;
- The Early Advance shall be repaid from the proceeds of the
Initial Equity Offering (as defined below);
- A commitment by the Company to conduct one or more equity
offerings for aggregate proceeds of no less than the greater of
$650 million and the amount then drawn and outstanding under the
Early Advance (the Initial Equity Offering) by an extended deadline
to be determined in accordance with the applicable provisions of
the Amended HoA, as a result of the indefinite postponement of the
Special Meeting (as hereinafter defined) from its originally
scheduled date of November 1, 2022. The maturity date of the Early
Advance may be extended up to, but no later than, May 31,
2023;
- A commitment by Rio Tinto to participate pro rata in the
Initial Equity Offering subject to certain preconditions in
consideration for payment of a 0.5% commitment fee;
- Rio Tinto committing to provide additional short-term secured
advances directly to the Company up to a maximum of $300 million
(the RT Advance), which would be available in an event where there
are no funds available to the Company (after allowing for the need
for cash reserves for working capital purposes of $200 million in
the aggregate and taking account of any remaining availability
under the Early Advance);
- A commitment by Rio Tinto to provide a co-lending facility
(Co-Lending Facility). With the aggregate amount drawn under the RT
Advance and the Co-Lending Facility not to exceed $750 million, to
be made available once sustainable production has been achieved;
and
- Rio Tinto (in its role as manager of Oyu Tolgoi, with the
assistance of the treasury group of Rio Tinto) is tasked with
leading the process of rescheduling of principal repayments of
existing debt (Re-profiling) to potentially reduce the base case
incremental funding requirement by up to approximately $1.7 billion
and seeking to raise up to $500 million of additional senior
supplemental debt (SSD) and use all reasonable commercial efforts
to complete the Re-profiling by no later than December 31,
2022.
Further, the Amended HoA provides that, if necessary, Turquoise
Hill would be required to raise up to a total of $1.5 billion (less
the amount raised in the Initial Equity Offering) via equity in a
form of its choosing.
The requirement of Rio Tinto to advance funds under the
Co-Lending Facility is subject to a number of conditions precedent
set out in the Amended HoA, including, among others: that certain
undertakings provided by the Company in favour of the Oyu Tolgoi
project finance lenders be amended to cover the Co-Lending
Facility; that terms of the Oyu Tolgoi project finance agreements
with respect to a “Sponsor Senior Loan” not be amended in any
material respect; the absence of new material claims and
proceedings against Turquoise Hill or Rio Tinto that could
adversely impact the funding elements of the Amended HoA; the
absence of a material adverse change and of a “Suspensive Event” as
defined under the Oyu Tolgoi project finance agreements, and
operations at Oyu Tolgoi not having been suspended for certain
defined periods of time; and all relevant third party approvals and
consents having been obtained. The requirement of Rio Tinto to
advance funds under the RT Advance is also subject to a number of
conditions precedent set out in the Amended HoA substantially
similar to those applicable to the Co-Lending Facility. The
foregoing list of conditions does not purport to be exhaustive, and
investors should refer to a copy of the Amended HoA as filed on the
SEDAR and EDGAR profiles of the Company.
In light of the financing debt restrictions in Resolution 103,
until sustainable production is achieved, OT LLC's estimated
funding requirements are expected to be addressed by cash on hand
at OT LLC, the Re-profiling (or the commitment by Rio Tinto to
provide additional bridge financing to the Company on the same
terms as the Early Advance in the event that the Company is
required to provide additional funding for Oyu Tolgoi in respect of
the December 2022 scheduled principal repayment of $362 million
under the Oyu Tolgoi project finance facility), the Early Advance
and the RT Advance, with these funds being provided to OT LLC via
the OT LLC board of directors approved pre-paid copper concentrate
sale arrangement between Turquoise Hill and OT LLC.
At September 30, 2022, the Company estimates its base case
incremental funding range to be $3.7 billion to $4.0 billion, an
increase of $0.1 billion to $0.4 billion from its June 30, 2022
estimate of $3.6 billion. Significant contributors to this increase
include updated commodity pricing and other market-based
assumptions, including LIBOR and inflation, and a draft operating
plan for 2023 received from OT LLC. Assuming a fully successful
Re-profiling, raising of SSD and implementation of the other
elements of the Amended HoA, the Company, based on updated
liquidity forecasts, currently estimates it could need to raise
incremental equity proceeds of approximately $0.5 billion to $0.8
billion (June 30, 2022: $0.4B), which would be in addition to an
initial equity offering estimated to be at least $650 million, to
fully address its estimated incremental funding requirement within
the timing framework of the Amended HoA. The Amended HoA sets a
target date for the Re-profiling of no later than December 31, 2022
and an outside date for the SSD and Co-Lending Facility to the
earlier of the three months following the lifting of the debt
restrictions under Resolution 103 and December 31, 2023. Any
changes in key assumptions may impact the incremental funding
requirement and, as a result, the actual amount of incremental
equity required may be greater or less than the estimated range of
$0.5 billion to $0.8 billion referred to above. The issuance of any
incremental equity in addition to the initial equity offering, as
well as the estimated timing of its issuance would take into
account the expected timing and completion of all other funding
elements of the Amended HoA, which would be needed to provide the
Company with sufficient liquidity and resources to meet its minimum
obligations for at least twelve months from the balance sheet date
of September 30, 2022. The risks inherent in delivery of the
Amended HoA funding plan, some of which are outside of the
Company’s control, result in the existence of a material
uncertainty that casts a significant doubt about the Company’s
ability to continue as a going concern. In the event there is a
residual funding requirement after implementing the elements of the
Amended HoA, the Company would consider all funding options
available to it at that time.
Successful implementation of the Amended HoA is subject to
achieving alignment with relevant stakeholders in addition to Rio
Tinto (including existing lenders, any potential new lenders and
the Government of Mongolia), market conditions and other factors.
Non-fulfilment of any of the conditions precedent identified in the
Amended HoA would also adversely affect the ability of the Company
and OT LLC to obtain additional funding or re-profile existing debt
as contemplated within the timeframe set out in the Amended HoA.
The Company is in discussions with Rio Tinto and other relevant
stakeholders regarding implementation of the Amended HoA as well as
its residual funding requirements.
Substantial progress has been made on reaching agreement on the
commercial terms and conditions of the Re-profiling, with the
commercial terms and conditions now substantially agreed. Certain
existing commercial bank lenders under the OT Project Financing
have indicated that they are unable or unwilling to participate in
the Re-profiling. Consequently, Rio Tinto and the Company are
pursuing several potential solutions, including but not limited to:
engaging existing lenders that are currently participating in the
Re-profiling with a view to increasing their current participation
levels, and engaging with new potential commercial bank lenders who
could replace any banks that ultimately decide to exit.
If Rio Tinto and Turquoise Hill are not successful in their
efforts to secure the Re-profiling on or before December 15, 2022,
the Company would be required, in order to address its near-term
liquidity needs, to draw on the $362 million bridge financing that
Rio Tinto has committed to provide to the Company under the Amended
HoA in order to fund the principal repayment of that same amount
under the Oyu Tolgoi project finance facility due on December 15,
2022.
If the Re-profiling and SSD funding contemplated by the Amended
HoA are not wholly successful, or the principal repayment of $362
million under the OT Project Financing is required to be made on
December 15, 2022, Turquoise Hill could require additional equity
financing, which would be in addition to the combined estimated
equity funding requirement range of approximately $1.15 billion to
$1.45 billion.
Turquoise Hill’s liquidity outlook will continue to be impacted,
either positively or negatively, by various factors, many of which
are outside the Company’s control, including:
- Successful implementation of the Amended HoA;
- Changes in commodity prices and other market-based assumptions
(including LIBOR and inflation);
- Surface operations performance as well as the successful
implementation (or otherwise) of ongoing optimisation efforts;
- Any further changes to underground mine cost and schedule in
addition to those identified in the 2022 Reforecast;
- Any re-emergence of COVID-19 related impacts, especially on
border routes, as well as the economic, commercial and financial
consequences thereof;
- Further and/or unanticipated impacts on operations and
underground development related to global supply chain issues;
and
- The outcomes of Turquoise Hill’s and Rio Tinto’s ongoing
engagement with various Mongolian governmental bodies as the
Mongolian Government implements Resolution 103, as discussed in the
“Renewed Partnership with Government of Mongolia” section of this
press release below.
Turquoise Hill continues to monitor its liquidity outlook and
will provide updates as and when circumstances require.
As noted above, Turquoise Hill currently estimates its base case
incremental funding range to be $3.7 billion to $4.0 billion (June
30, 2022: base case estimate of $3.6 billion), taking into
consideration relevant assumptions, including:
- Metal price assumptions for copper and gold over the
incremental funding period, as set out in the table below;
- The 2022 Reforecast;
- The current forecast of sustainable production for Panel
0;
- The current forecasts for Shafts 3 and 4 (for further
information, see the section “Open Pit Operations, Underground
Project and Operations” of this press release);
- The draft operating plan for 2023 received from OT; and
- Any updates or changes to the mine plan of either the open pit
or underground mines as provided in the “Open Pit Operations,
Underground Project and Operations” section of this press release
above.
The specific metal price assumptions used in determining the
base case incremental funding range are as follows:
Year
Copper ($ / pound)
Gold ($ / troy ounce)
2022
3.46
1,672
2023
3.64
1,781
2024
3.83
1,754
Within the base case funding requirement are $1.8 billion of
scheduled principal repayments, which the Company is attempting to
re-profile.
Turquoise Hill currently estimates its base case incremental
funding range will continue to be influenced, either positively or
negatively, by various factors over the incremental funding period,
many of which are outside the Company’s control, including:
- Any potential further revisions to the amount of underground
development or sustaining capital required or revisions to schedule
/ plans;
- The timing of sustainable production and ramp-up profile and
their impact on cash flows including any further COVID-19-related
delays (for further information, see the section “Open Pit
Operations, Underground Project and Operations” of this press
release);
- The outcomes of Turquoise Hill’s and Rio Tinto’s ongoing
engagement with various Mongolian governmental bodies to resolve
remaining outstanding items relating to the Government of
Mongolia’s implementation of Resolution 103 as discussed in the
“Renewed Partnership with Government of Mongolia” section of this
press release below;
- Changes to the amount of cash flow expected to be generated
from surface operations, net of underground and surface operations
sustaining capital requirements;
- Further and/or unanticipated impacts on operations and
underground development related to the COVID-19 pandemic as well as
the economic, commercial and financial consequences thereof;
and
- Changes in expected commodity prices, LIBOR, inflation and
other market-based assumptions (upside and downside pricing
sensitivities would have, respectively, a favourable or
unfavourable impact on the base case incremental funding
requirement).
More generally, any changes in the above factors may impact the
incremental funding requirement and, as a result, the actual amount
of incremental funding required may be greater or less than the
$3.7 billion to $4.0 billion estimated range provided, and such
variance may be significant. See the sections “Risks and
Uncertainties” and “Forward-Looking Statements and Forward-Looking
Information” in the Company’s Q3 2022 MD&A.
PRIVATISATION PROPOSAL RECEIVED FROM RIO TINTO
Arrangement Agreement
On September 5, 2022, the Company, based on the unanimous
recommendation of an independent special committee of its board of
directors (the Special Committee), entered into an arrangement
agreement (the Arrangement Agreement) with Rio Tinto plc and Rio
Tinto, a wholly-owned subsidiary of Rio Tinto plc, in respect of a
transaction whereby Rio Tinto would acquire the approximately 49%
of the issued and outstanding common shares of the Company that Rio
Tinto does not currently own for C$43.00 in cash per share (the
Consideration) pursuant to a plan of arrangement under the Business
Corporations Act (Yukon) (the Arrangement).
Completion of the Arrangement is subject to receipt of the
requisite approval of the shareholders of the Company, final
approval of the Arrangement by the Supreme Court of Yukon and the
satisfaction or waiver of the other customary conditions. Following
completion of the Arrangement, it is anticipated that the common
shares of the Company will be delisted from the Toronto Stock
Exchange and the New York Stock Exchange and that the Company will
cease to be a reporting issuer under applicable Canadian securities
laws and that the registration of the common shares under the
United States Securities Exchange Act of 1934 will be
terminated.
The Arrangement Agreement has been filed under the Company’s
profiles at www.sedar.com and www.sec.gov. Additional information
regarding the transaction has been provided in the information
circular for the special meeting of the Company’s shareholders (the
Special Meeting) to be held on a date to be determined in order to
consider and, if thought advisable, pass a resolution to approve
the Arrangement, which circular has been filed under the Company’s
profiles at www.sedar.com and www.sec.gov.
Agreements Between Rio Tinto and Certain Minority
Shareholders
On November 1, 2022, Rio Tinto, Rio Tinto plc and certain
shareholders of the Company related to Pentwater Capital Management
LP and SailingStone Capital Partners LLC (collectively, the Named
Shareholders) holding in aggregate 32,617,578 common shares of the
Company, entered into agreements (the Agreements) in relation to
the Arrangement. The Company is not party to the Agreements and
neither it nor the Special Committee was involved in the
negotiation of the Agreements.
Pursuant to the terms of the Agreements, the parties agreed,
among other things, that:
- the Named Shareholders would withhold their votes in respect of
the special resolution to approve the Arrangement;
- proceedings in respect of the Named Shareholders’ dissent
rights in connection with the Arrangement, as well as certain
oppression claims against Rio Tinto and its affiliates (the
Oppression Claims), will be conducted in accordance with procedures
set out in the Agreements, which include mediation to be completed
within 60 days of closing of the Arrangement and, absent resolution
at mediation, confidential binding arbitration which the parties
agree to use reasonable commercial efforts to complete within 12
months of the conclusion of the mediation;
- the Named Shareholders will receive 80% of the Consideration
within two business days of closing of the Arrangement and 20% of
the Consideration, plus interest thereon, within two business days
of final determination of the dissent proceedings (or settlement
thereof) in accordance with the Agreements;
- the Agreements also provide for the mediation and, if
necessary, confidential binding arbitration of the fair value
amount remaining to be paid, if any, by Rio Tinto to the Named
Shareholders to resolve the dissent proceedings and the damages or
compensation amount, if any, to be paid by Rio Tinto to the Named
Shareholders to resolve the Oppression Claims;
- Rio Tinto agreed to waive the closing condition in the
Arrangement Agreement relating to the exercise of dissent rights to
allow the Arrangement to be completed in circumstances where
holders of up to 17.5% of the common shares of the Company validly
exercise dissent rights; and
- the Named Shareholders also provided covenants related to
non-disparagement, non-interference and a release of all claims
against Rio Tinto plc, Rio Tinto, the Company and their respective
affiliates and past, present or future directors, officers or
employees other than obligations under the Agreements, claims
related to the dissent proceedings and Oppression Claims and claims
related to the U.S. securities law class action proceeding against
Rio Tinto in the Southern District of New York.
The Agreements have been filed under the Company’s profiles at
www.sedar.com and www.sec.gov.
The Special Committee has been working with Rio Tinto to address
the Special Committee’s concerns with respect to the differential
treatment of the Company’s minority shareholders in connection with
the proposed Arrangement as a result of the Agreements. In
addition, the Company and Rio Tinto have been advised by the
Autorité des marchés financiers (the AMF) that, in light of the
announcement of the Agreements on November 1, 2022, the AMF
considers the transaction as currently structured to raise public
interest concerns.
The Special Committee is engaging with Rio Tinto in order to
address the differential treatment of minority shareholders
resulting from the Agreements. In the event that terms are reached
that satisfy the Special Committee’s concerns, the Company will
provide shareholders with supplemental disclosure regarding such
revised terms. In order to provide shareholders with sufficient
time to consider such supplemental disclosure, the Company
determined to adjourn the Special Meeting scheduled for November
15, 2022 to a date to be determined.
GOVERNMENT RELATIONS
Turquoise Hill’s ownership of the Oyu Tolgoi mine is held
through a 66% interest in OT LLC. The remaining 34% interest in OT
LLC is held by Erdenes. Turquoise Hill was obliged to fund Erdenes’
share of Oyu Tolgoi’s funding requirements until September 2016,
and Erdenes’ share of the capital costs and operating costs of the
underground mine until September 2021 under the ARSHA and the Oyu
Tolgoi Underground Mine Development and Financing Plan (UDP)
entered into on May 18, 2015 between, among others, the Company,
the Government of Mongolia, Erdenes and OT LLC.
Underground construction recommenced in May 2016 when OT LLC
received the final requirement for the restart of underground
development: formal notice to proceed approval by the Board, Rio
Tinto (as project manager) and OT LLC. Approval followed the
signing of the UDP in May 2015 and the signing of a $4.4 billion
project finance facility in December 2015. Development had been
suspended in August 2013 pending resolution of matters with the
Government of Mongolia.
Turquoise Hill’s investment in the Oyu Tolgoi mine is governed
by the 2009 Investment Agreement among Turquoise Hill, the
Government of Mongolia, OT LLC and an affiliate of Rio Tinto
(Investment Agreement or IA). The Investment Agreement framework
was authorised by the Mongolian Parliament and was concluded after
16 months of negotiations. It was reviewed by numerous
constituencies within the Government. Turquoise Hill has been
operating in good faith under the terms of the Investment Agreement
since 2009, and we believe not only that it is a valid and binding
agreement, but that it has proven to be beneficial for all
parties.
Adherence to the principles of the Investment Agreement, the
ARSHA and the UDP has allowed for the development of the Oyu Tolgoi
mine in a manner that has given rise to significant long-term
benefits to Mongolia. Benefits from the Oyu Tolgoi mine open-pit
operations and underground development include, but are not limited
to, employment, royalties and taxes, local procurement, economic
development and sustainability investments.
Renewed Partnership with Government of Mongolia
On January 24, 2022, the Company announced that it had
successfully reached a mutual understanding for a renewed
partnership with the Government of Mongolia and that the OT LLC
Board had unanimously approved the commencement of the undercut,
namely the commencement of blasting on January 25, 2022 that
started the Oyu Tolgoi underground mine production and the full
Definitive Estimate underground development budget.
The decision to approve the undercut represented a reset of the
relationship with the Government of Mongolia with a view to
delivering economic benefits to all stakeholders including the
people of Mongolia and followed resolution of many of the
conditions required in Resolution 103 including:
- Turquoise Hill agreeing to waive in full the $2.4 billion carry
account loan of Erdenes. See the section “Funding of OT LLC by
Turquoise Hill” of this press release;
- Improved cooperation with Erdenes in monitoring the Oyu Tolgoi
underground development and enhancing environment, social and
governance (ESG) matters;
- The approval of the Electricity Supply Agreement entered into
by OT LLC (the ESA); and
- The establishment of a funding structure at OT LLC that does
not incur additional loan financing prior to sustainable production
for Panel 0 (expected in the first half of 2023).
The Company continues to work with the Government of Mongolia
and Rio Tinto regarding measures set out in Resolution 103 and on
September 9, 2022, notices of termination of the UDP were sent by
Rio Tinto, OT LLC and the Company to Erdenes.
On October 3, 2022, the Company and Rio Tinto signed a waiver
deed poll whereby Rio Tinto agreed it will not charge management
services payments in respect of the capital costs relating to the
underground development incurred or to be incurred in excess of
$5.373 billion up to a maximum of $6.75 billion.
The Company continues to work with the Government of Mongolia
and Rio Tinto to finalise the remaining outstanding measures of
Resolution 103, including resolution of the outstanding OT LLC tax
arbitration.
Oyu Tolgoi Mine Power Supply
OT LLC currently sources power for the Oyu Tolgoi mine from
China’s Inner Mongolia Autonomous Region’s (IMAR) Western Grid, via
overhead power line, pursuant to back-to-back power purchase
arrangements with Mongolia’s National Power Transmission Grid
(NPTG), the relevant Mongolian power authority, and Inner Mongolia
Power International Cooperation Co., Ltd (IMPIC), the subsidiary of
Inner Mongolia’s power grid company expiring in July 2023.
OT LLC is obliged under the Investment Agreement to secure a
long-term domestic source of power for the Oyu Tolgoi mine. The
Power Source Framework Agreement (PSFA) entered into between OT LLC
and the Government of Mongolia in December 2018 (and as amended in
June 2020) provides a binding framework and pathway for long-term
power supply to the Oyu Tolgoi mine.
OT LLC entered into the Electricity Supply Agreement (ESA) on
January 26, 2022, with, amongst others, Southern Region Electricity
Distribution Network to provide OT LLC with power from the
Mongolian grid. Delivery of power under the ESA will commence once
certain conditions are satisfied, and the Mongolian grid becomes
capable of providing electricity to meet OT LLC’s total power
requirements on a long-term basis and imported power agreements are
terminated. The ESA has a term of 20 years and provides a pathway
to meeting OT LLC’s long-term power requirements from domestic
power sources.
While the Mongolian grid undergoes an upgrade to be in a
position to provide stable and reliable power to the Oyu Tolgoi
mine, OT LLC will continue to import its power from IMAR. On
September 30, 2022, a Memorandum of Understanding (MoU) was signed
between NPTG, OT LLC and IMPIC. The MoU is an important interim
step in securing Oyu Tolgoi’s long-term power supply, as it records
the agreement reached in principle to date with respect to
extension and amendment of the power import agreement, including
its extension to 2026 followed by two two-year automatic rolling
extensions up to July 2030 with termination rights by NPTG from
July 2028 by giving at least six months prior notice on or after
January 4, 2028. Pursuant to the MoU, NPTG, OT LLC and IMPIC will
endeavour to enter into a binding amendment agreement by no later
than December 31, 2022. However, on-going strict lockdowns due to
COVID-19 in China and IMAR and other factors could prevent the
negotiations to continue as planned, which may delay its
finalisation to Q1'23.
Oyu Tolgoi Tax Assessments
On January 16, 2018, Turquoise Hill announced that OT LLC had
received and was evaluating a tax assessment for approximately $155
million (which was converted from Mongolian Tugrik to U.S. dollars
at the exchange rate on that date) from the Mongolian Tax Authority
(MTA) relating to an audit on taxes imposed and paid by OT LLC
between 2013 and 2015 (the 2013 to 2015 Tax Assessment). In January
2018, OT LLC paid an amount of approximately $4.8 million to settle
unpaid taxes, fines and penalties for accepted items.
On February 20, 2020, the Company announced that OT LLC would be
proceeding with the initiation of a formal international
arbitration proceeding in accordance with dispute resolution
provisions within Chapter 14 of the Investment Agreement and
Chapter 8 of the UDP. The dispute resolution provisions call for
arbitration under the United Nations Commission on International
Trade Law (UNCITRAL) seated in London before a panel of three
arbitrators. By agreeing to resolve certain matters within the 2013
to 2015 Tax Assessment dispute under UNCITRAL Arbitration Rules,
both parties have agreed that the arbitral award shall be final and
binding on both parties and the parties shall carry out the award
without delay.
On December 23, 2020, Turquoise Hill announced that OT LLC had
received and was evaluating a tax assessment for approximately $228
million (which was converted from Mongolian Tugrik to U.S. dollars
at the exchange rate on that date) from the MTA relating to an
audit on taxes imposed and paid by OT LLC between 2016 and 2018
(the 2016 to 2018 Tax Assessment). Most of the matters raised in
respect of the 2016 to 2018 Tax Assessment are of a similar nature
to the matters that were raised in the 2013 to 2015 Tax Assessment.
The MTA also proposed a $1.4 billion adjustment to the balance of
OT LLC’s carried forward tax losses. The adjustments are to
disallow or defer certain tax deductions claimed in the 2016 to
2018 years.
On January 11, 2021, Turquoise Hill announced that OT LLC had
completed its evaluation of the 2016 to 2018 Tax Assessment claim
and confirmed that OT LLC had given notice of its intention to
apply to the UNCITRAL tribunal to amend its statement of claim to
include certain matters raised in the 2016 to 2018 Tax Assessment.
OT LLC’s application to include these matters in the pending
arbitration for the 2013 to 2015 Tax Assessment was accepted. In
addition to those matters included within the statement of claim,
there are certain limited tax matters included in the 2013 to 2015
and 2016 to 2018 Tax Assessments, which were addressed in local
Mongolian tax courts. As there was less certainty with respect to
the resolution of these matters, the Company accrued for certain
amounts and has also adjusted its loss carry forwards.
In February 2021, OT LLC received notices of payment totalling
approximately $228 million (which were converted from Mongolian
Tugrik to U.S. dollars at the exchange rate on those dates)
relating to amounts disputed under the 2016 to 2018 Tax Assessment,
and in March 2021, OT LLC received notices of payment totalling
$126 million (which were converted from Mongolian Tugrik to U.S.
dollars at the exchange rate on those dates) relating to amounts
disputed under the 2013 to 2015 Tax Assessment. Under the Mongolian
General Tax Law, the amounts were due and paid by OT LLC within 10
business days from the dates of the notices of payment. Under the
same legislation, OT LLC would be entitled to recover the amounts,
including via offset against future tax liabilities, in the event
of a favourable decision from the relevant dispute resolution
authorities.
On May 3, 2021, the Company announced that the Government of
Mongolia filed its statement of defence together with a
counterclaim (GoM Defence and Counterclaim) in relation to the tax
arbitration proceeding. Turquoise Hill was not a party to the
arbitration, but the GoM Defence and Counterclaim requested that
the arbitral tribunal add both the Company and a member of the Rio
Tinto Group as parties to the tax arbitration. The principal thrust
of the GoM Defence and Counterclaim is to seek the rejection of OT
LLC’s tax claims in their entirety. As part of the counterclaim,
the Government of Mongolia also makes assertions surrounding
previously reported allegations of historical improper payments
made to Government of Mongolia officials and seeks unquantified
damages. Also, in the event OT LLC’s tax claims are not dismissed
in their entirety, the Government of Mongolia is seeking in the
counterclaim an alternative declaration that the Investment
Agreement is void.
Turquoise Hill denied the allegations relating to the Company in
the GoM Defence and Counterclaim and filed submissions to the
arbitral tribunal to oppose the Government of Mongolia’s request
that it be added to the tax arbitration. As announced by the
Company on January 17, 2022, the arbitral tribunal issued a ruling
deciding that Turquoise Hill not be added as a party to the
arbitration. As described above, Resolution 103 authorised certain
measures to be completed by the Government of Mongolia in order for
Resolution 92 to be considered formally implemented.
On February 11, 2022, at the request of the parties to the tax
arbitration, the arbitral tribunal issued an order suspending the
tax arbitration for six months or until 21 days from when the
tribunal receives notice from OT LLC or the Government of Mongolia
to terminate the suspension. Initial discussions were held between
the parties but there were no material developments in relation to
the negotiations. On August 15, 2022, at the request of the parties
to the international tax arbitration, the arbitral tribunal issued
an order suspending the tax arbitration for a further twelve months
(until August 12, 2023) or until 21 days from when the tribunal
receives notice from OT LLC or the Government of Mongolia to
terminate the suspension.
The Company remains committed to continue to work with the
Government of Mongolia and Rio Tinto to finalise the outstanding
tax matters whether through arbitration or negotiation.
Anti-Corruption Authority Information requests
On March 1, 2022, OT LLC notified the Company that it received a
letter from the Mongolian Anti-Corruption Authority requesting
certain documents and information relating to an investigation
regarding the underground construction work. The Company has no
further details at this time and will update the market as
appropriate.
CLASS ACTION COMPLAINTS
US Class Action Dismissed
In October 2020, a class action complaint was filed in the U.S.
District Court, Southern District of New York against the Company,
certain of its current and former officers as well as Rio Tinto and
certain of its current and former officers. The complaint alleges
that the defendants made material misstatements and material
omissions with respect to, among other things, the schedule, cost
and progress to completion of the development of Oyu Tolgoi in
violation of Section 10(b) of the U.S. Securities Exchange Act of
1934, as amended (the Exchange Act) and Rule 10b-5 thereunder.
Under the schedule established by the court, a first amended
complaint was filed on March 16, 2021, and a second amended
complaint was filed on September 16, 2021. The defendants moved to
dismiss the operative amended complaint on October 19, 2021, under
Rule 12(b)(6) of the Federal Rules of Civil Procedure and the
Private Securities Litigation Reform Act of 1995, for failure to
state a claim. As of December 17, 2021, the motion was fully
briefed and oral argument was held on August 25, 2022. On September
2, 2022, the court granted the Company’s and its defendant
officers’ motion to dismiss in its entirety.
Quebec Class Action Update
In January 2021, a proposed class action was initiated in the
Superior Court in the District of Montreal against the Company and
certain of its current and former officers. An amended complaint
was filed on July 27, 2021 which did not substantially alter the
claim. The claim alleges that the Company and its current and
former officers named therein as defendants made material
misstatements and material omissions with respect to, among other
things, the schedule, cost and progress to completion of Oyu
Tolgoi, in violation of, among other things, sections 225.8, 225.9
and 225.11 of the Securities Act (Quebec). On January 7, 2022 the
plaintiff re-amended its claim to include allegations relating to
developments arising since the previous amended complaint was
filed.
The Company and its defendant officers filed evidence to defend
the claim in June 2022 and the class plaintiff subsequently
announced their intention to add additional parties as defendants
to the action, which led to an effective suspension of the
proceedings. It is unknown at this time if or when additional
defendants might be named in the proceedings, but the case remains
in abeyance for the time being. No hearing has been scheduled yet.
The Company believes that the complaint against it is without merit
and will defend the application for leave and certification of the
proceeding.
See the risk factor titled “The Company may be subject to public
allegations, regulatory investigations or litigation that could
materially and adversely affect the Company’s business” in the
“RISKS AND UNCERTAINTIES” section of the Company’s MD&A for the
year ended December 31, 2021.
NOTICE OF ARBITRATION
In May 2022, the Company received a notice of arbitration from
Entrée Resources Ltd. in connection with the earn-in-agreement with
Entrée.
The Company disputes the characterisations made by Entrée in its
news release dated May 26, 2022 announcing the initiation of
arbitration proceedings. Turquoise Hill has been in discussions
with Entrée in order to resolve certain commercial disagreements in
connection with the Earn-in Agreement. The Company reserves all of
its rights and will vigorously defend itself.
See the risk factor titled “The Company may be subject to public
allegations, regulatory investigations or litigation that could
materially and adversely affect the Company’s business” in the
“RISKS AND UNCERTAINTIES” section of the Company’s MD&A for the
year ended December 31, 2021.
CORPORATE ACTIVITIES
Exploration
Turquoise Hill, through its wholly owned subsidiaries, Asia Gold
Mongolia LLC, Heruga Exploration LLC and SGLS LLC, operates an
exploration programme in Mongolia on licences that are not part of
Oyu Tolgoi. Turquoise Hill owns three exploration licences: Bag and
Od-2 in the Umnugobi province and Khatavch in the Dornogovi
province.
During Q3’22, Turquoise Hill
drilled two diamond drill holes designed to test Induced
Polarisation (IP) chargeability anomalies that were defined from
the 2020 geophysical surveys. Both holes reached their target
depths and intersected volcanic rocks including tuffaceous volcanic
sandstone / siltstone (lithic and lapilli tuff), massive andesitic
tuff, aphyric basaltic andesite tuff and rhyodacite tuff along with
lesser coal seams and carbonaceous siltstone. Samples every 20
metres were submitted for assay (49 elements ICM40B and Au, Pd and
Pt fire Assay FAI313) and no anomalous results were received. The
results from this programme suggest that the source of the IP
chargeability anomaly is likely to be related to intersections of
coal seam, carbonaceous black shale chlorite-clay (phengite)
alteration and/or pyritisation.
The Turquoise Hill exploration team continues to monitor any
opportunities to grow their portfolio through acquiring new land.
The next land release by the Mineral Resources and Petroleum
Authority of Mongolia is still expected in Q1’23.
NON-GAAP AND OTHER FINANCIAL MEASURES
The Company presents and refers to the following non-GAAP
financial measures, non-GAAP ratios and supplementary financial
measures, which are not defined in IFRS. A description and, when
required, a calculation of each measure is given below. Such
measures may differ from similarly named measures provided by other
issuers. These measures are presented in order to provide investors
and other stakeholders with additional understanding of performance
and operations at the Oyu Tolgoi mine and are not intended to be
used in isolation from, or as a replacement for, measures prepared
in accordance with IFRS.
Non-GAAP financial measures
Non-GAAP financial measure is defined in National Instrument
52-112 – Non-GAAP and Other Financial Measures Disclosure (NI
52-112) as a financial measure disclosed that (a) depicts the
historical or expected future financial performance, financial
position or cash flow of an entity, (b) with respect to its
composition, excludes an amount that is included in, or includes an
amount that is excluded from, the composition of the most directly
comparable financial measure disclosed in the primary financial
statements of the entity, (c) is not disclosed in the financial
statements of the entity, and (d) is not a ratio, fraction,
percentage or similar representation.
Total operating cash costs
The measure of total operating cash costs excludes: depreciation
and depletion; exploration and evaluation; charges for asset
write-down (including write-down of materials and supplies
inventory) and includes management services payments to Rio Tinto
and management services payments to Turquoise Hill, which are
eliminated in the consolidated financial statements of the Company.
Total operating cash costs is used internally by management to
assess the performance of the business in effectively allocating
and managing costs and is provided in order to provide investors
and other stakeholders with additional information about the
underlying cash costs of OT LLC. Total operating cash costs are
relevant to the understanding of the Company’s operating
profitability and ability to generate cash flows. The most
comparable financial measure that is disclosed in the primary
financial statements for total operating costs is “Cost of sales”.
A reconciliation of total operating cash costs for its current and
comparative period is presented under “Non-GAAP Ratios” herein
below.
Consolidated working capital
Consolidated working capital comprises those components of
current assets and liabilities which support and result from the
Company’s ongoing running of its current operations. It is provided
in order to give a quantifiable indication of the Company’s
short-term cash generation ability and business efficiency. As a
measure linked to current operations and the sustainability of the
business, the Company’s definition of consolidated working capital
excludes: non-trade receivables and payables; financing items; cash
and cash equivalents; deferred revenue and non-current inventory.
Management and investors consider movements in consolidated working
capital to understand the Company’s cash flow generated from
operating activities before interest and tax.
A reconciliation of consolidated working capital to the
financial statements and notes is provided below.
Consolidated working capital
September 30,
December 31,
(Stated in $000's of dollars)
2022
2021
Inventories (current)
239,019
290,017
Trade and other receivables
13,643
16,119
Trade and other payables: - trade payables and accrued liabilities
(342,643)
(320,791)
- payable to related parties
(89,593)
(54,153)
(179,574)
(68,808)
Contractual obligations
The following section of this press release discloses
contractual obligations in relation to the Company’s project
finance, lease, purchase, power and asset retirement obligations.
Amounts relating to these obligations are calculated on the
assumptions of the Company carrying out its future business
activities and operations as planned at the period end. As such,
contractual obligations presented in this press release and in the
Company’s Q3 2022 MD&A will differ from amounts presented in
the financial statements, which are prepared on the basis of
minimum uncancellable commitments to pay in the event of contract
termination. The presentation of contractual obligations here and
the Company’s Q3 2022 MD&A is provided in order to give an
indication of future expenditure, for the disclosed categories,
arising from the Company’s continuing operations and development
projects.
A reconciliation of contractual obligations as at September 30,
2022 to the relevant line items from among the current assets and
liabilities in the consolidated financial statements and notes is
provided below.
(Stated in $000's of dollars)
Project FinanceFacility
Purchaseobligations OtherObligations
Powercommitments Leaseliabilities
Decommissioningobligations Commitments
(MD&A)
4,240,316
476,634
462,107
98,521
21,844
409,028
Cancellable obligations (net of exit costs)
-
(403,501)
-
(32,984)
-
-
Accrued capital expenditure
-
(42,353)
42,353
-
-
-
Discounting and other adjustments
(112,887)
-
-
-
(5,167)
(228,187)
Financial statement amount
4,127,429
30,780
504,460
65,537
16,677
180,841
Contractual obligations is used to present contractual and other
obligations that are both cancellable or non-cancellable.
Non-GAAP ratios
A non-GAAP ratio is defined by NI 52-112 as a financial measure
disclosed that (a) is in the form of a ratio, fraction, percentage
or similar representation, (b) has a non-GAAP financial measure as
one or more of its components, and (c) is not disclosed in the
financial statements. The non-GAAP financial measures used to
calculate the non-GAAP ratios below are C1 cash costs, all-in
sustaining costs, mining costs and milling costs.
C1 cash costs per pound of copper
produced
C1 cash costs is a metric representing the cash cost per unit of
extracting and processing the Company’s principal metal product,
copper, to a condition in which it may be delivered to customers
net of gold and silver credits from concentrates sold. This metric
is provided in order to support peer group comparability and to
provide investors and other stakeholders with additional
information about the underlying cash costs of OT LLC and the
impact of gold and silver credits on the operations’ cost
structure. C1 cash costs are relevant to understanding the
Company’s operating profitability and ability to generate cash
flow. When calculating costs associated with producing a pound of
copper, the Company deducts gold and silver revenue credits as the
production cost is reduced by selling these products. The most
comparable financial measure that is disclosed in the primary
financial statements for total operating costs is “Cost of
sales”.
All-in sustaining costs per pound of
copper produced
All-in sustaining costs (AISC) is an extended cash-based cost
metric providing further information on the aggregate cash, capital
and overhead outlay per unit and is intended to reflect the costs
of producing the Company’s principal metal product, copper, in both
the short term and over the life-cycle of its operations. As a
result, sustaining capital expenditures on a cash basis is included
rather than depreciation. As the measure seeks to present a full
cost of copper production associated with sustaining current
operations, development project capital is not included. AISC
allows Turquoise Hill to assess the ability of OT LLC to support
sustaining capital expenditures for future production from the
generation of operating cash flows.
A reconciliation of total operating cash costs, C1 cash costs
and AISC is provided below.
(Three Months Ended) (Nine Months Ended)
C1 costs (Stated in $000's of
dollars)
September 30, 2022
September 30, 2021
September 30, 2022
September 30, 2021
(Restated)(1)
(Restated)(1)
Cost of sales
254,626
210,608
649,052
451,763
Cost of sales: $/lb of copper sold
2.76
2.06
2.75
1.95
Depreciation and depletion
(49,064)
(50,131)
(133,131)
(123,548)
Change in inventory
(42,357)
(22,066)
(30,809)
80,807
Other operating expenses
56,360
77,542
179,773
207,306
Less:
- Inventory (write-down) reversal
(271)
(6)
(460)
3,598
- Depreciation
(570)
(580)
(1,612)
(1,775)
Management services payment to Turquoise Hill
9,265
8,703
23,677
20,581
Total operating cash costs
227,989
224,093
686,490
638,717
Total operating cash costs: $/lb of copper produced
2.85
2.43
3.20
2.33
Adjustments to total operating cash costs(2)
11,760
(13,132)
581
(24,642)
Less: Gold and silver revenues
(102,216)
(266,362)
(350,050)
(592,030)
C1 costs ($'000)
137,533
(55,401)
337,021
22,045
C1 costs: $/lb of copper produced
1.72
(0.60)
1.57
0.08
All-in sustaining costs (Stated in $000's
of dollars)
Corporate administration
16,971
5,255
45,967
26,823
Asset retirement expense
3,053
2,457
8,908
5,440
Royalty expenses
16,849
37,592
70,201
82,794
Ore stockpile and stores write-down (reversal)
271
6
460
(3,598)
Other expenses
1,709
908
3,908
1,714
Sustaining cash capital including deferred stripping
31,618
16,300
100,451
43,385
All-in sustaining costs ($'000)
208,004
7,117
566,916
178,603
All-in sustaining costs: $/lb of copper produced
2.60
0.08
2.65
0.65
(1)
Prior year comparatives have been restated
for adoption of the IAS16 amendment to Property, Plant and
Equipment: Proceeds before intended Use. Please refer to the
Section titled “Recent Accounting Pronouncements” on page 25 of the
Company’s Q3 2022 MD&A for further information.
(2)
Adjustments to total operating cash costs
include: treatment, refining and freight differential charges less
the 5% Government of Mongolia royalty and other expenses not
applicable to the definition of C1 cash cost.
Cost of sales is the most comparable measure for mining and
milling costs. Mining and milling costs represent total operating
cash costs of Oyu Tolgoi’s open-pit mining and concentrator
operations.
Mining, milling and G&A costs per tonne ratios are used
internally by management and investors to assess the performance of
the business by providing information on cost efficiency across the
important components of Oyu Tolgoi’s operations - its open-pit
mine, concentrator and support functions.
Mining costs per tonne of material
mined
Mining costs per tonne of material mined for the three and nine
months ended September 30, 2022 are calculated by reference to
total mining costs, respectively, of $66.0 million and $182.8
million (Q3’21: $46.9 million and $134.2 million) and total
material mined of 26.1 million and 76.0 million tonnes (Q3’21: 22.6
million and 61.0 million tonnes).
Milling costs per tonne of ore
treated
Milling costs per tonne of ore treated for the three and nine
months ended September 30, 2022 are calculated by reference to
total milling costs, respectively, of $73.8 million and $205.5
million (Q3’21: $74.8 million and $202.8 million) and total ore
treated of 10.7 million and 30.0 million tonnes (Q3’21: 9.3 million
and 28.6 million tonnes).
Supplementary financial measures
Supplementary financial measures are defined under NI 52-112 as
financial measures (a) which are neither non-GAAP financial
measures nor non-GAAP ratios, (b) that are not presented in the
financial statements and (c) that are, or are intended to be,
disclosed periodically to depict the historical or expected future
financial performance, financial position or cash flow. The below
are supplementary financial measures that the Company uses to
depict its financial performance, financial position or cash
flows.
Cost of sales per pound of copper
sold
Cost of sales is reported in the consolidated income statement.
Cost of sales per pound of copper sold supports management’s
objective of efficient cost allocation and is used by management
and investors to understand operating profitability.
Capital expenditures
These measures are derived from and comprise sustaining and
development expenditures on property, plant and equipment in the
cash flow statement.
i. Capital expenditures
on surface operations
Capital expenditures on surface operations comprise investment
in the above ground assets and infrastructure that now support both
operation of the open pit and processing of underground material.
This includes the expenditures related to the open pit, including
deferred stripping, the concentrator and tailings storage.
ii. Capital
expenditures on the underground project
Capital expenditures on the underground project comprise
underground sustaining capital expenditures and underground
development capital expenditures.
a. Underground
sustaining capital expenditures
Underground sustaining capital expenditures represent cash spent
on assets lasting for more than one year that support lateral
development of the underground system, including drawpoint
construction. This measure is used to support management's
objective of effective and efficient capital allocation as the
Company needs to invest in sustaining capital assets in order to
optimise productive capacity, including during the period from
undercut commencement in January 2022 through to sustainable
production, currently anticipated in H1’2023, and into the
future.
b. Underground
development capital expenditures
Underground development capital expenditures reflect spending
required to complete the underground project, including on the
underground materials handling and ventilation infrastructure. It
includes construction of the shafts, primary crushers, material
handling systems and the surface to conveyor system. This measure
is used to support management's objective of delivering growth
through completion of development on the underground project.
iii. Underground
development capital incurred
Underground development capital incurred reflects the value of
work completed, usually equal to amounts invoiced or accrued, where
goods or services have been delivered but the invoice has not been
received or processed. Amounts incurred, on being invoiced and paid
will become underground development capital expenditures.
iv. Underground
development capital committed
Underground development capital committed reflects the value of
the work awarded to a vendor or contractor, including the work of
the owners teams required to support awarded contracts. Amounts
committed, once the scope of the contract packages have been
delivered will become underground development capital incurred.
Underground development capital incurred and underground
development capital committed provide information on the delivery
of the project to date both in terms of commitments made with
vendors and scope delivered. These measures are useful since they
illustrate how much of the project remains to be delivered, which
is increasingly important to management as we approach completion
of the project.
These measures are used to support management's objective of
effective and efficient capital allocation as the Company needs to
invest in sustaining existing assets across our operations in order
to maintain and improve productive capacity, and to deliver growth
through completion of development on the underground project.
G&A costs per tonne of ore
treated
G&A costs per tonne of ore treated for the three and nine
months ended September 30, 2022 are calculated by reference to
total general & administrative costs. General &
administrative costs are equivalent to Oyu Tolgoi administrative
expenses and totalled, respectively, $35.0 million and $97.2
million (Q3’21: $33.9 million and $114.8 million). Total ore
treated for those periods were 10.7 million and 30.0 million tonnes
(Q3’21: 9.3 million and 28.6 million tonnes). G&A is used to
promote cost effectiveness through measurement of the overhead
required to support the business.
INTERNAL CONTROL OVER FINANCIAL REPORTING AND DISCLOSURE
CONTROLS AND PROCEDURES
There were no changes in the Company’s internal control over
financial reporting (as such term is defined in Rule 13a-15(f) and
15d-15(f) under the Exchange Act) that occurred during the three
months ended September 30, 2022 that have materially affected, or
are reasonably likely to materially affect, the Company’s internal
control over financial reporting.
Disclosure controls and procedures are designed to provide
reasonable assurance that information required to be disclosed by
the Company under applicable securities legislation is gathered and
reported to senior management, including the Company’s CEO and CFO,
on a timely basis so that appropriate decisions can be made
regarding public disclosures. There were no changes in the
Company’s disclosure controls and procedures during the three
months ended September 30, 2022.
QUALIFIED PERSON
Disclosure of information of a scientific or technical nature in
the Company’s Q3 2022 MD&A in respect of the Oyu Tolgoi mine
was approved by Jo-Anne Dudley (FAusIMM(CP)), Chief Operating
Officer of the Company. Jo-Anne Dudley is a “qualified person”
within the meaning of National Instrument 43-101 – Standards of
Disclosure for Mineral Projects (NI 43-101).
SELECTED QUARTERLY DATA
The Company’s interim financial statements are reported under
IFRS applicable to interim financial statements, including IAS 34
Interim Financial Reporting.
($ in millions, except per share information) Quarter Ended
Sep-30
Jun-30
Mar-31
Dec-31
2022
2022
2022
2021
Restated (b)
Revenue
391.1
402.0
402.7
522.3
Income for the period
40.0
93.3
394.3
221.6
Income attributable to owners of Turquoise Hill Resources
Ltd
46.6
82.6
275.2
165.8
Basic and diluted earnings per share attributable to owners
of Turquoise Hill Resources Ltd (a)
0.23
0.41
1.37
0.82
Quarter Ended
Sep-30
Jun-30
Mar-31
Dec-31
2021
2021
2021
2020
Restated (b)
Restated (b)
Revenue
662.1
329.8
526.5
405.1
Income for the period
54.4
127.8
332.1
241.6
Income attributable to owners of Turquoise Hill Resources
Ltd
55.7
102.9
236.7
159.9
Basic and diluted earnings per share attributable to owners
of Turquoise Hill Resources Ltd (a)
0.28
0.51
1.18
0.79
(a)
Basic and diluted earnings per share has
been recalculated pursuant to the share consolidation completed on
October 23, 2020 for all periods presented.
(b)
Comparatives have been restated for
adoption of the IAS16 amendment to Property, Plant and Equipment:
Proceeds before intended Use. Please refer to the Section titled
“Recent Accounting Pronouncements” on page 25 of the Company’s Q3
2022 MD&A for further information.
Consolidated Statements of Income (Stated in thousands of
U.S. dollars, except share and per share amounts)
(Unaudited) Three Months Ended Nine Months Ended September
30, September 30, Note
2022
2021
2022
2021
Restated -Note 2 (c)(i) Restated -Note 2 (c)(i) Revenue
4
$
391,080
$
662,131
$
1,195,768
$
1,518,477
Cost of sales
5
(254,625
)
(210,608
)
(649,052
)
(451,763
)
Gross margin
136,455
451,523
546,716
1,066,714
Operating expenses
6
(56,360
)
(77,542
)
(179,773
)
(207,306
)
Corporate administration expenses
(16,971
)
(5,255
)
(45,967
)
(26,823
)
Other expenses
19
(13,644
)
(3,676
)
(36,413
)
(31,463
)
Income before finance items and taxes
49,480
365,050
284,563
801,122
Finance items
Finance income
7
1,804
446
3,691
2,343
Finance costs
7
(4,588
)
(2,590
)
(11,336
)
(5,821
)
(2,784
)
(2,144
)
(7,645
)
(3,478
)
Income from operations before taxes
46,696
362,906
276,918
797,644
Income and other taxes
13
(6,662
)
(308,541
)
250,758
(283,288
)
Income for the period
$
40,034
$
54,365
$
527,676
$
514,356
Attributable to owners of Turquoise Hill Resources Ltd.
$
46,558
$
55,685
$
404,422
$
395,259
Attributable to owner of non-controlling interest
(6,524
)
(1,320
)
123,254
119,097
Income for the period
$
40,034
$
54,365
$
527,676
$
514,356
Basic and diluted earnings per share
attributable to owners of Turquoise Hill Resources Ltd.
$
0.23
$
0.28
$
2.01
$
1.96
Basic weighted average number of shares outstanding (000's)
201,231
201,231
201,231
201,231
The notes to the Company’s financial statements, which are
available on the Company’s website, are part of its consolidated
financial statements.
Consolidated Statements of Comprehensive Income (Stated
in thousands of U.S. dollars) (Unaudited) Three Months
Ended Nine Months Ended September 30, September 30,
2022
2021
2022
2021
Restated -Note 2 (c)(i) Restated -Note 2 (c)(i)
Income
for the period
$
40,034
$
54,365
$
527,676
$
514,356
Other comprehensive income: Items that will not be
reclassified to income: Changes in the fair value of marketable
securities at FVOCI
56
141
218
5,028
Other comprehensive income for the period (a)
$
56
$
141
$
218
$
5,028
Total comprehensive income for the period
$
40,090
$
54,506
$
527,894
$
519,384
Attributable to owners of Turquoise Hill
46,614
55,826
404,640
400,287
Attributable to owner of non-controlling interest
(6,524
)
(1,320
)
123,254
119,097
Total comprehensive income for the period
$
40,090
$
54,506
$
527,894
$
519,384
(a) No tax charges and no credits arose on items recognized
as other comprehensive income or loss in 2022 (2021: nil).
The notes to the Company’s financial statements, which are
available on the Company’s website, are part of its consolidated
financial statements.
Consolidated Statements of Cash Flows (Stated in
thousands of U.S. dollars) (Unaudited) Three Months
Ended Nine Months Ended September 30, September 30, Note
2022
2021
2022
2021
Restated -Note 2 (c)(i) Restated -Note 2 (c)(i)
Cash generated
from / (used in) operating activities before interest and
tax
16
$
(8,359
)
$
382,491
$
429,651
$
935,494
Interest received
1,838
466
3,307
2,319
Interest paid
(27,020
)
(903
)
(112,600
)
(111,925
)
Income and other taxes paid
18
(57
)
(38
)
(2,534
)
(358,686
)
Net cash generated / (used in) from operating activities
$
(33,598
)
$
382,016
$
317,824
$
467,202
Cash flows from investing activities Expenditures on
property, plant and equipment
$
(267,606
)
$
(208,955
)
$
(758,413
)
$
(686,598
)
Purchase of commodity put options
-
-
-
(29,907
)
Other investing cash flows
-
(131
)
(1
)
(69
)
Cash used in investing activities
$
(267,606
)
$
(209,086
)
$
(758,414
)
$
(716,574
)
Cash flows from financing activities Proceeds from
bank overdraft facility
$
5,000
$
-
$
5,000
$
-
Payment of lease liability
(2,443
)
(1,848
)
(7,595
)
(2,143
)
Repayment of project finance facility
-
-
(41,826
)
(21,744
)
Cash generated / (used in) financing activities
$
2,557
$
(1,848
)
$
(44,421
)
$
(23,887
)
Effects of exchange rates on cash and cash equivalents
(502
)
(283
)
(32
)
(490
)
Net increase / (decrease) in cash and cash equivalents
$
(299,149
)
$
170,799
$
(485,043
)
$
(273,749
)
Cash and cash equivalents - beginning of period
$
508,402
$
679,073
$
694,296
$
1,123,621
Cash and cash equivalents - end of period
$
209,253
$
849,872
$
209,253
$
849,872
The notes to the Company’s financial statements, which are
available on the Company’s website, are part of its consolidated
financial statements.
Consolidated Balance Sheets (Stated in thousands of U.S.
dollars) (Unaudited)
September 30,
December 31,
Note
2022
2021
Restated -Note 2 (c)(i)
Current assets Cash and cash
equivalents
8
$
209,253
$
694,296
Inventories
9
239,019
290,017
Trade and other receivables
13,643
16,119
Prepaid expenses and other assets
76,316
120,715
538,231
1,121,147
Non-current assets
Property, plant and equipment
10
12,991,708
12,049,958
Inventories
9
43,724
60,711
Prepaid expenses and other assets
18
296,427
348,671
Deferred income tax assets
13
885,284
602,862
Other financial assets
17,520
16,818
14,234,663
13,079,020
Total assets
$
14,772,894
$
14,200,167
Current liabilities
Borrowings and other financial liabilities
11
$
716,001
$
397,421
Trade and other payables
12
504,460
384,488
Deferred revenue
49,263
149,368
1,269,724
931,277
Non-current liabilities
Borrowings and other financial liabilities
11
3,433,105
3,785,358
Deferred income tax liabilities
13
176,894
145,434
Decommissioning obligations
14
180,841
153,662
3,790,840
4,084,454
Total liabilities
$
5,060,564
$
5,015,731
Equity
Share capital
$
11,432,122
$
11,432,122
Contributed surplus
1,555,774
1,555,774
Accumulated other comprehensive income
4,581
4,363
Deficit
(3,835,235
)
(2,840,896
)
Equity attributable to owners of Turquoise Hill
9,157,242
10,151,363
Attributable to non-controlling interest
15
555,088
(966,927
)
Total equity
$
9,712,330
$
9,184,436
Total liabilities and equity
$
14,772,894
$
14,200,167
The notes to the Company’s financial statements, which are
available on the Company’s website, are part of its consolidated
financial statements.
Consolidated Statements of Equity (Stated in thousands of
U.S. dollars) (Unaudited) Nine Months Ended
September 30, 2022 Attributable to owners of Turquoise
Hill
Accumulated
other
Non-controlling
Contributed
comprehensive
Interest
Share capital
surplus
income
Deficit
Total
(Note 15)
Total equity
Opening balance
$
11,432,122
$
1,555,774
$
4,363
$
(2,840,896
)
$
10,151,363
$
(966,927
)
$
9,184,436
Income for the period
-
-
-
404,422
404,422
123,254
527,676
Other comprehensive income for the period
-
-
218
-
218
-
218
Waiver of non-recourse loans (Note 15)
-
-
-
(1,398,761
)
(1,398,761
)
1,398,761
-
Closing balance
$
11,432,122
$
1,555,774
$
4,581
$
(3,835,235
)
$
9,157,242
$
555,088
$
9,712,330
Nine Months Ended September 30, 2021 Attributable
to owners of Turquoise Hill
Accumulated
other
Non-controlling
Contributed
comprehensive
Interest
Share capital
surplus
income
Deficit
Total
(Note 15)
Total equity
Opening balance
$
11,432,122
$
1,558,834
$
1,418
$
(3,415,601
)
$
9,576,773
$
(1,148,820
)
$
8,427,953
Impacts of change in accounting policy Note 2(c)(i)
-
-
-
13,630
13,630
7,022
20,652
Opening balance (Restated)
$
11,432,122
$
1,558,834
$
1,418
$
(3,401,971
)
$
9,590,403
$
(1,141,798
)
$
8,448,605
Income for the period (Restated Note 2(c)(i))
-
-
-
395,259
395,259
119,097
514,356
Other comprehensive income for the period
-
-
5,028
-
5,028
-
5,028
Employee share plans
-
(3,060
)
-
-
(3,060
)
-
(3,060
)
Closing balance (Restated)
$
11,432,122
$
1,555,774
$
6,446
$
(3,006,712
)
$
9,987,630
$
(1,022,701
)
$
8,964,929
The notes to the Company’s financial statements, which are
available on the Company’s website, are part of its consolidated
financial statements.
About Turquoise Hill Resources
Turquoise Hill is an international mining company focused on the
operation and continued development of the Oyu Tolgoi copper-gold
mine in Mongolia, which is the Company’s principal and only
material mineral resource property. Turquoise Hill’s ownership of
the Oyu Tolgoi mine is held through a 66% interest in Oyu Tolgoi
LLC (Oyu Tolgoi); Erdenes Oyu Tolgoi LLC (Erdenes), a Mongolian
state-owned entity, holds the remaining 34% interest.
Forward-looking statements and forward-looking
information
Certain statements made herein, including statements relating to
matters that are not historical facts and statements of the
Company’s beliefs, intentions and expectations about developments,
results and events which will or may occur in the future,
constitute “forward-looking information” within the meaning of
applicable Canadian securities legislation and “forward-looking
statements” within the meaning of the “safe harbour” provisions of
the United States Private Securities Litigation Reform Act of 1995.
Forward-looking statements and information relate to future events
or future performance, reflect current expectations or beliefs
regarding future events and are typically identified by words such
as “anticipate”, “believe”, “could”, “estimate”, “expect”,
“intend”, “likely”, “may”, “plan”, “seek”, “should”, “will” and
similar expressions suggesting future outcomes or statements
regarding an outlook. These include, but are not limited to,
statements and information regarding: the Arrangement, including
the provision of supplemental disclosure to shareholders and the
adjournment of the Special Meeting; the nature of the Company’s
ongoing relationship and interaction with the Government of
Mongolia with respect to the continued operation and development of
Oyu Tolgoi as and when the key agreements entered into with the
Government of Mongolia announced on January 24, 2022 (the GoM
Agreements) are implemented along with the implementation of
Resolution 103, the resolution passed by the Parliament of Mongolia
in December 2021 to resolve the outstanding issues among the
Company, Rio Tinto and the Government of Mongolia in relation to
the implementation of Resolution 92, the resolution passed by the
Parliament of Mongolia in November 2019 mandating the Government of
Mongolia to take necessary measures to ensure the benefits to
Mongolia of Oyu Tolgoi; the continuation of undercutting in
accordance with the mine plan and design; the actual timing of
first sustainable production as well as the lifting of restrictions
by the Government of Mongolia on the ability of OT LLC to incur any
additional indebtedness; the implementation and successful
execution of the updated funding plan that is the subject of the
Amended HoA, as such agreement may be further amended or restated,
and the amount of any additional future funding gap to complete the
Oyu Tolgoi project and the availability and amount of potential
sources of additional funding required therefor, all as
contemplated by the Amended HoA, as well as potential delays
in the ability of the Company and OT LLC to proceed with the
funding elements contemplated by the Amended HoA; liquidity,
funding sources and funding requirements in general, in particular
until sustainable first production is achieved, including the
Company’s ability to reach agreement with project finance lenders
on the re-profiling of existing debt payments in line with current
cash flow projections, as well as the Company (or a wholly-owned
subsidiary) and OT LLC entering into a pre-paid copper concentrate
sale arrangement; the availability and amount of potential sources
of additional funding, including the short-term secured advance to
be provided by Rio Tinto to the Company under the Amended HoA; the
amount by which a successful re-profiling of the Company’s existing
debt would reduce the Company’s currently projected funding
requirements; the Company’s ability to conduct one or more equity
offerings as contemplated by the Amended HoA in light of future and
then prevailing market conditions; the expectations set out in the
2020 Oyu Tolgoi Technical Report (2020 OTTR); the timing and amount
of future production and potential production delays; statements in
respect of the impacts of any delays on achieving first sustainable
production and on the Company’s cash flows; expected copper and
gold grades; the merits of the class action complaint filed against
the Company in January 2021; the international tax
arbitration brought by OT LLC and the likelihood of the parties
being able to amicably resolve the ongoing tax issues; the timing
of studies, announcements and analyses; the status of underground
development, including any slowdown of work; the causes of the
increase in costs and schedule extension of the underground
development; the mine design for Panel 0 of Hugo North Lift 1 and
the related cost and production schedule implications; the
re-design studies for Panels 1 and 2 of Hugo North Lift 1 and the
possible outcomes, content and timing thereof; the timing and
progress of the sinking of Shafts 3 and 4 and any delays in that
regard in addition to previously announced delays; expectations
regarding the possible recovery of ore in the two structural
pillars, to the north and south of Panel 0; the possible
progression of a state-owned power plant (SOPP) and related
amendments to the PSFA, as amended, as well as power purchase
agreements and extensions thereto; the finalisation of an agreement
with IMPIC on extension of the current power import arrangements;
the timing of construction and commissioning of the potential SOPP;
sources of interim power; the continuing impact of COVID-19,
including any restrictions imposed by health or governmental
authorities relating thereto on the Company’s business, operations
and financial condition, as well as delays and the development cost
impacts of delays caused by the COVID-19 pandemic; the Company’s
ability to operate sustainably, its community relations and its
social licence to operate in Mongolia; capital and operating cost
estimates, including inflationary pressures thereon resulting in
cost escalation; the content of the Definitive Estimate; mill and
concentrator throughput; anticipated business activities, planned
expenditures, corporate strategies; supply disruptions of oil and
gas to the Oyu Tolgoi project caused by the ongoing Russia-Ukraine
conflict; and other statements that are not historical facts.
Forward-looking statements and information are made based upon
certain assumptions and other important factors that, if untrue,
could cause the actual results, performance or achievements of the
Company to be materially different from future results, performance
or achievements expressed or implied by such statements or
information. There can be no assurance that such statements or
information will prove to be accurate. Such statements and
information are based on numerous assumptions regarding present and
future business strategies, local and global economic conditions,
and the environment in which the Company will operate in the
future, including: the ability of the Company and Rio Tinto to
agree to satisfactory terms to address the differential treatment
of minority shareholders resulting from the Agreements and to
satisfy any concerns of the AMF or any other regulators; the
ability of the Company and Rio Tinto to satisfy, in a timely
manner, the other conditions to the completion of the Arrangement;
the price of copper, gold and silver; projected gold, copper and
silver grades; anticipated capital and operating costs; anticipated
future production and cash flows; the anticipated location of
certain infrastructure in Hugo North Lift 1 and sequence of mining
within and across panel boundaries; the nature of the Company’s
ongoing relationship and interaction with the Government of
Mongolia with respect to the continued operation and development of
Oyu Tolgoi as and when the GoM Agreements are implemented along
with the implementation of Resolution 103; the continuation of
undercutting in accordance with the mine plan and design; the
actual timing of first sustainable production as well as the
lifting of restrictions by the Government of Mongolia on the
ability of OT LLC to incur any additional indebtedness; the ability
of the Company and Rio Tinto to receive in a timely manner and on
satisfactory terms the necessary shareholder approvals (including
the minority approval) and Court approval; the availability and
timing of required governmental and other approvals for the
construction of the SOPP; the ability of the Government of Mongolia
to finance and procure the SOPP within the timeframes anticipated
in the PSFA, as amended, subject to ongoing discussions relating to
a standstill period; finalisation of an agreement with IMPIC on an
extension of the current power import arrangements; the eventual
pre-payment arrangement between the Company (or a wholly-owned
subsidiary) and OT LLC; the implementation and successful execution
of the updated funding plan that is the subject of the Amended HoA,
as such agreement may be further amended and restated; the
Company’s ability to operate sustainably, its community relations
and its social licence to operate in Mongolia; and the amount of
any additional future funding gap to complete the Oyu Tolgoi
project and the availability and amount of potential sources of
additional funding required therefor.
Certain important factors that could cause actual results,
performance or achievements to differ materially from those in the
forward-looking statements and information include, among others:
the possibility that the Arrangement will not be completed on the
terms and conditions currently contemplated or at all due to
failure to obtain or satisfy, in a timely manner or otherwise,
required shareholder and court approvals and other conditions of
closing or for other reasons; the possibility of adverse reactions
or changes in business relationships resulting from the pendency or
completion of the Arrangement; risks relating to the retention of
key personnel while the Arrangement is pending; the possibility of
litigation relating to the Arrangement; risks related to the
diversion of management’s attention from the Company’s ongoing
business operations while the Arrangement is pending; and other
risks inherent in the Company’s business and/or other factors
beyond its control which could have a material adverse effect on
the Company or the ability to consummate the Arrangement; copper,
gold and silver price volatility; discrepancies between actual and
estimated production; mineral reserves and resources and
metallurgical recoveries; development plans for processing
resources; the accuracy of the Definitive Estimate; public health
crises such as COVID-19; matters relating to proposed exploration
or expansion; mining operational and development risks, including
geotechnical risks and ground conditions; litigation risks,
including the outcome of the class action complaint filed against
the Company; the outcome of the international arbitration
proceedings, including the likelihood of the parties being able to
amicably resolve the ongoing tax issues; regulatory restrictions
(including environmental regulatory restrictions and liability); OT
LLC or the Government of Mongolia’s ability to deliver a domestic
power source for the Oyu Tolgoi project within the required
contractual time frame; the Company’s ability to operate
sustainably, its community relations, and its social licence to
operate in Mongolia; activities, actions or assessments, including
tax assessments, by governmental authorities; events or
circumstances (including public health crises, strikes, blockades
or similar events outside of the Company’s control) that may affect
the Company’s ability to deliver its products in a timely manner;
currency fluctuations; the speculative nature of mineral
exploration; the global economic climate; global climate change;
dilution; share price volatility; competition; loss of key
employees; cyber security incidents; additional funding
requirements, including in respect of the development or
construction of a long-term domestic power supply for the Oyu
Tolgoi project; capital and operating costs, including with respect
to the development of additional deposits and processing
facilities; inflationary pressures on prices for critical supplies
for Oyu Tolgoi including fuel, power, explosives and grinding media
resulting in cost escalation; defective title to mineral claims or
property; human rights requirements; international conflicts such
as the ongoing Russia-Ukraine conflict; and new tax measures, such
as a minimum corporate tax rate, that might be implemented as a
result of evolving global initiatives. Although the Company has
attempted to identify important factors that could cause actual
actions, events or results to differ materially from those
described in forward-looking statements and information, there may
be other factors that cause actions, events or results not to be as
anticipated, estimated or intended. All such forward-looking
statements and information are based on certain assumptions and
analyses made by the Company’s management in light of their
experience and perception of historical trends, current conditions
and expected future developments, as well as other factors
management believes are reasonable and appropriate in the
circumstances. These statements, however, are subject to a variety
of risks and uncertainties and other factors that could cause
actual events or results to differ materially from those projected
in the forward-looking statements or information.
With respect to specific forward-looking information concerning
the continued operation and development of the Oyu Tolgoi project,
the Company has based its assumptions and analyses on certain
factors which are inherently uncertain. Uncertainties and
assumptions include, among others: the nature of the Company’s
ongoing relationship and interaction with the Government of
Mongolia with respect to the continued operation and development of
Oyu Tolgoi as and when the GoM Agreements are implemented along
with the implementation of Resolution 103; the continuation of
undercutting in accordance with the mine plan and design; the
approval or non-approval by the OT LLC Board of any future
necessary additional investment, and the likely consequences on the
timing and overall economic value of the Oyu Tolgoi project,
including slowdown on the underground development and significant
delays to first sustainable production; the timing and cost of the
construction and expansion of mining and processing facilities; the
timing and availability of a long-term domestic power source (or
the availability of financing for the Company or the Government of
Mongolia to construct such a source) for Oyu Tolgoi; the
implementation and successful execution of the updated funding plan
that is the subject of the Amended HoA, as such agreement may be
further amended or restated, and the amount of any additional
future funding gap to complete the Oyu Tolgoi project and the
availability and amount of potential sources of additional funding
required therefor the eventual pre-payment arrangement between the
Company (or a wholly-owned subsidiary) and OT LLC; the potential
impact of COVID-19, including any restrictions imposed by health
and governmental authorities relating thereto, as well as the
development cost impacts of delays caused by the COVID-19 pandemic;
the Company’s ability to operate sustainably, its community
relations and its social licence to operate in Mongolia; the impact
of changes in, changes in interpretation to or changes in
enforcement of, laws, regulations and government practices in
Mongolia; the availability and cost of skilled labour and
transportation; the obtaining of (and the terms and timing of
obtaining) necessary environmental and other government approvals,
consents and permits; delays and the costs which would result from
delays, including delays caused by COVID-19 restrictions and
impacts and related factors, in the development of the underground
mine (which could significantly exceed the costs projected in the
2020 OTTR); projected copper, gold and silver prices and their
market demand; production estimates and the anticipated yearly
production of copper, gold and silver at Oyu Tolgoi; inflationary
pressures on prices for critical supplies for Oyu Tolgoi, including
fuel, power, explosives and grinding media resulting in cost
escalation; and the potential impact of the ongoing Russia-Ukraine
conflict, including supply disruptions of oil and gas to the Oyu
Tolgoi project caused thereby.
The cost, timing and complexities of mine construction and
development are increased by the remote location of a property such
as Oyu Tolgoi. It is common in mining operations and in the
development or expansion of existing facilities to experience
unexpected problems and delays during development, construction and
mine start-up. Additionally, although Oyu Tolgoi has achieved
commercial production, there is no assurance that future
development activities will result in profitable mining
operations.
Readers are cautioned not to place undue reliance on
forward-looking information or statements. By their nature,
forward-looking statements involve numerous assumptions, inherent
risks and uncertainties, both general and specific, which
contribute to the possibility that the predicted outcomes will not
occur. Events or circumstances could cause the Company’s actual
results to differ materially from those estimated or projected and
expressed in, or implied by, these forward-looking statements.
Important factors that could cause actual results to differ from
these forward-looking statements are included in the “Risk Factors”
section in the AIF, as supplemented by the “Risks and
Uncertainties” section in the Company’s Q3 2022 MD&A.
Readers are further cautioned that the list of factors
enumerated in the “Risk Factors” section in the AIF and the “Risks
and Uncertainties” section of in the Company’s Q3 2022 MD&A
that may affect future results is not exhaustive. When relying on
the Company’s forward-looking statements and information to make
decisions with respect to the Company, investors and others should
carefully consider the foregoing factors and other uncertainties
and potential events. Furthermore, the forward-looking statements
and information contained herein are made as of the date of this
document and the Company does not undertake any obligation to
update or to revise any of the included forward-looking statements
or information, whether as a result of new information, future
events or otherwise, except as required by applicable law. The
forward-looking statements and information contained herein are
expressly qualified by this cautionary statement.
View source
version on businesswire.com: https://www.businesswire.com/news/home/20221114005098/en/
Vice President Investors Relations and Communications Roy
McDowall roy.mcdowall@turquoisehill.com Follow us on Twitter
@TurquoiseHillRe
Turquoise Hill Resources (NYSE:TRQ)
Gráfica de Acción Histórica
De Nov 2024 a Dic 2024
Turquoise Hill Resources (NYSE:TRQ)
Gráfica de Acción Histórica
De Dic 2023 a Dic 2024