Project remains fully funded, on schedule,
approximately 73% complete, within guidance for initial capital
expenditure, and is advancing operational readiness
TSXV: ARTG
VANCOUVER, BC, April 24,
2024 /CNW/ - Artemis Gold Inc. (TSXV: ARTG) ("Artemis
Gold" or the "Company") provides an update on Q1 construction
progress at the Blackwater Mine in central British Columbia. The project remains fully
funded, within the guidance for initial capital expenditure, and on
schedule for first gold pour in H2 2024.
At March 31, 2024 overall
construction was approximately 73% complete, and approximately
C$523 million of the guided initial
capital expenditure of C$730 to
C$750 million had been spent. By the
end of Q1 2024, the Company had entered into contractual
commitments for C$682 million (or 93%
of the lower end of the guided initial capital expenditure). The
majority of uncommitted expenditures relate to owners' cost and
earthworks associated with mining pre-strip and construction of the
tailings storage facility and other civil structures.
Steven Dean, Chairman and CEO of
Artemis Gold, stated: "We have an exceptional team managing the
development of the Blackwater Mine. Execution is critical in all
projects, and managing the day-to-day challenges that arise in
building a mine of this scale and complexity is key to being
successful. We have an experienced group of people who are first
class problem solvers, ensuring we advance toward operational
readiness and remain on track for first gold pour in H2 2024.
"The remainder of 2024 will be transformational for Artemis Gold
as we progress the Blackwater Mine, a tier one asset in a tier one
jurisdiction, into production."
Construction Update
Mild weather conditions in Q1 2024 provided good, early access
to infrastructure areas at the Blackwater Mine. Construction of
major site water management facilities, including the water
management pond, the central diversion system and the Davidson
Creek diversion, have been completed. Work on the tailings storage
facility dam is progressing well. Initial material placement has
been successfully achieved, including tying into the surrounding
topography, providing for optimal productivity moving into
summer.
Total major works hours worked up to March 31, 2024 surpassed 1.7 million hours with a
zero LTIFR1 and an AIFR2 of 87.68.
Process Plant
At the end of March 2024, the
Sedgman EPC contract work on the processing plant was approximately
84% complete overall, with engineering, design and procurement
essentially complete.
Process plant construction continues to progress well,
particularly within steel erection and conveyor installation.
Installation of mechanical equipment within the secondary and
tertiary crushing circuits, as well as the screening station, was
completed during the quarter. Notable achievements throughout the
period included the installation of the ball mill, intensive leach
reactor and the regeneration kiln, while installation of the
gravity concentrator has commenced. All major tanks have been
completed, including pre-leach, carbon-in-leach, and elution, and
hydrotesting is underway.
Concrete work is nearing completion with most of the major pours
now completed including the primary crusher run-of-mine slab,
crusher vault and ore stockpile reclaim tunnel. Erection of the
reagents and mill buildings are in progress with cladding works
planned to commence in April.
Electrical and instrumentation activities are scaling up, with
the installation of the main electrical room in the crushing
circuit area now complete.
Transmission Line
During Q1 2024 the transmission line right-of-way clearing
was completed. Construction contracts were awarded, and contractors
mobilized to the region. Laydown areas and camp facilities have
been established and civil foundation work and structure erection
commenced. All electrical conductors have been delivered to site.
Poles and hardware deliveries are in progress and sequenced to
support the construction schedule.
The line is being built in two parts, north and south of the
Nechako River. The length of the northern section is approximately
50km and the southern section approximately 80km.
Upgrades to the BC Hydro Glenannan substation are progressing to
plan. Commissioning planning with BC Hydro is advancing as
planned.
Work associated with Blackwater's 25kV power distribution
network has progressed according to plan with engineering at an
issued-for-construction (IFC) level, procurement complete, and
most materials on site. Pole foundations are 65% completed and pole
erection has commenced.
Heavy Equipment
Assembly and commissioning of the owner's mining fleet continues
to advance. Two 400-tonne hydraulic backhoe excavators, six
240-tonne rigid frame haul trucks and two large mining front-end
loaders are fully assembled. The remainder of the fleet to support
initial operations is on site and nearing completion. Additional
units will be added to the fleet as operations ramp up.
Personnel
The Company maintained its workforce of 320 employees in Q1 2024
and the ratios of the workforce have remained consistent,
approximately:
- 20% of the team are women
- 30% identify as Indigenous
- 50% are from the local region, and;
- 80% are B.C. residents.
The total Blackwater Mine workforce, including staff and
contractors, surpassed 600 at the end of March.
Operational Readiness
Recruitment for the Blackwater Mine operations team commenced
this quarter with the first hires starting in early Q2 2024.
A laboratory contract has been signed and all mill reagents have
been tendered, with plans to finalize the contracts in Q2 2024.
Procurement for commissioning, operations and critical spares
was completed, and the operational readiness planning commenced
during the quarter.
Funding
During Q1 2024, the Company completed an additional draw of
$130 million under the project loan
facility, bringing the total drawn to $280
million, along with approximately C$5
million in cumulative capitalized interest at March 31, 2024.
At March 31, 2024, Artemis Gold
had estimated remaining Phase 1 capital expenditures of
C$207 to C$227
million. At the same date, the committed sources of funding
totalled C$295 million,
comprising:
- cash and cash equivalents of C$155
million;
- remaining drawdowns from the project loan facility of
C$100 million (including
approximately C$20 million of
capitalized interest remaining available), and
- a cost overrun facility of C$40
million.
In addition, the Company had 23.2 million warrants outstanding
which are exercisable at C$1.08 per
warrant before August 27, 2024, for
anticipated proceeds of C$25
million.
Artemis Gold President and COO Jeremy
Langford commented: "Looking ahead to Q2 2024, we expect to
complete the construction and commissioning of the initial phase of
the mining fleet, advance the tailings storage facility main dam
wall, and move to the completion of the construction activity in
the processing facility. At the end of Q1 2024, we remain on track
for first gold pour in H2 2024."
Video
Watch here for a Q1 project update video:
https://youtu.be/JFwpIC9fFZo
Photos- April 2024
About Artemis Gold
Artemis Gold is a well-financed, growth-oriented gold
development company with a strong financial capacity aimed at
creating shareholder value through the identification, acquisition,
and development of gold properties in mining-friendly
jurisdictions. The Company's current focus is the construction of
the Blackwater Mine in central British
Columbia approximately 160km southwest of Prince George and 450km northeast of
Vancouver. The project is one of
the largest capital investments in central British Columbia in over a decade. The first
pour of gold and silver at Blackwater is expected in H2 2024.
Artemis Gold trades on the TSX-V under the symbol ARTG. For more
information visit www.artemisgoldinc.com.
Qualified Person
Jeremy Langford, FAUSIMM, a
Qualified Person as defined by National Instrument 43-101, has
reviewed and approved the scientific and technical information in
this press release.
On behalf of the Board of
Directors
Steven Dean
Chairman and Chief Executive Officer
+1 604 558 1107
Neither the TSX Venture Exchange nor its Regulation Services
Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or
accuracy of this news release.
Cautionary Note Regarding
Forward-looking Information
This press release contains certain forward-looking
statements and forward-looking information as defined under
applicable Canadian and U.S. securities laws. Statements contained
in this press release that are not historical facts are
forward-looking statements that involve known and unknown risks and
uncertainties. Any statements that refer to expectations,
projections or other characterizations of future events or
circumstances contain forward-looking statements. In certain cases,
forward-looking statements and information can be identified using
forward-looking terminology such as "may", "will", "expect",
"intend", "estimate", "anticipate", "believe", "continue", "plans",
"potential" or similar terminology. Forward-looking statements and
information are made as of the date of this press release, and
include, but are not limited to, statements regarding the potential
of the Blackwater mine project; the jobs to be created in
connection with the project; the contribution of the project to the
economy; opinions of the Province of British Columbia regarding the project and the
region; agreements and relationships with Indigenous partners; the
future of mining in British
Columbia; the plans of the Company with respect to the
project, including construction, site preparation, clearing,
consultation with indigenous groups, and other plans and
expectations of the Company with respect to the project.
These forward-looking statements represent management's
current beliefs, expectations, estimates and projections regarding
future events and operating performance, which are based on
information currently available to management, management's
historical experience, perception of trends and current business
conditions, expected future developments and other factors which
management considers appropriate. Such forward-looking statements
involve numerous risks and uncertainties, and actual results may
vary. Important risks and other factors that may cause actual
results to vary include, without limitation: risks related to the
ability of the Company to accomplish its plans and objectives with
respect to the development of the project within the expected
timing or at all, the timing and receipt of certain required
approvals, changes in commodity prices, changes in interest and
currency exchange rates, risks inherent in exploration estimates
and results, risks inherent in exploration and development
activities, changes in development or mining plans due to changes
in logistical, technical or other factors, unanticipated
operational difficulties (including failure of plant, equipment or
processes to operate in accordance with specifications, cost
escalation, unavailability of materials, equipment or third party
contractors, delays in the receipt of government approvals,
industrial disturbances, job action, and unanticipated events
related to heath, safety and environmental matters), changes in
governmental regulation of mining operations, political risk,
social unrest, changes in general economic conditions or conditions
in the financial markets, and other risks related to the ability of
the Company to proceed with its plans for the project and other
risks set out in the Company's most recent MD&A, which is
available on the Company's website at
www.artemisgoldinc.com and on SEDAR+ at
www.sedarplus.ca
In making the forward-looking statements in this press
release, the Company has applied several material assumptions,
including without limitation, the assumptions that: (1) market
fundamentals will result in sustained mineral demand and prices;
(2) any necessary approvals and consents in connection with the
development of the project will be obtained; (3) financing for the
development, construction and continued operation of the project
will continue to be available on terms suitable to the Company; (4)
sustained commodity prices will continue to make the project
economically viable; and (5) there will not be any unfavourable
changes to the economic, political, permitting and legal climate in
which the Company operates. Although the Company has attempted to
identify important factors that could affect the Company and may
cause actual actions, events, or results to differ materially from
those described in forward-looking statements, there may be other
factors that cause the actual results or performance by the Company
to differ materially from those expressed in or implied by any
forward-looking statements. Accordingly, no assurances can be given
that any of the events anticipated by the forward-looking
statements will transpire or occur, or if any of them do so, what
impact they will have on the results of operations or the financial
condition of the Company. Investors should therefore not place
undue reliance on forward-looking statements. The Company is under
no obligation and expressly disclaims any obligation, to update,
alter or otherwise revise any forward-looking statement, whether
written or oral, that may be made from time to time, whether
because of new information, future events or otherwise, except as
may be required under applicable securities laws.
__________________________
1
LTIFR or Lost Time Injury Frequency Rate refers to the number of
lost time injuries occurring per million man-hours worked, divided
by total man-hours worked.
|
2
AIFR or All Injury Frequency Rate refers to the total number of
recordable incidents occurring per million man-hours worked,
divided by total man-hours worked.
|
SOURCE Artemis Gold Inc.