9 January 2025
Central Asia Metals
plc
(the 'Group', the
'Company' or 'CAML')
2024 Operations Update
Central Asia Metals plc (AIM: CAML) provides
its Q4 and full-year 2024 operations update for the Kounrad dump
leach, solvent extraction and electro-winning ('SX-EW') copper
recovery plant in Kazakhstan ('Kounrad') and the Sasa zinc-lead
mine in North Macedonia ('Sasa').
2024 operational summary
-
Zero lost time injuries ('LTIs') at Kounrad
-
Two LTIs at Sasa
-
Kounrad copper production firmly within the guidance
range:
o copper
production of 13,439 tonnes
-
Sasa zinc and lead production both fractionally below the
lower end of the guidance range:
o
zinc-in-concentrate production of 18,572 tonnes
o
lead-in-concentrate production of 26,617 tonnes
-
Sasa Capital Projects:
o transition to
paste-fill mining well under way
o Dry Stack
Tailings ('DST') Plant substantially complete
o Central Decline
completed
-
Aberdeen Minerals (CAML 28.4%) completed its 2024 exploration
drilling campaign
-
Cash balance at 31 December 2024 of $67.6 million
Outlook
-
Production guidance for FY2025:
o copper of
13,000 to 14,000 tonnes
o
zinc-in-concentrate of 19,000 to 21,000 tonnes
o
lead-in-concentrate of 27,000 to 29,000 tonnes
-
DST Plant at Sasa expected to be operational in Q1
2025
-
Assay results expected in Q1 2025 from Aberdeen Minerals 2024
drilling campaign
-
Building a project pipeline remains a key focus
CAML production summary
Metal
production (tonnes)
|
Q4
2024
|
Q4
2023
|
2024
|
2023
|
Copper
|
3,190
|
3,439
|
13,439
|
13,816
|
Zinc
|
4,790
|
5,446
|
18,572
|
20,338
|
Lead
|
6,881
|
7,022
|
26,617
|
27,794
|
Gavin Ferrar, Chief Executive
Officer, commented:
"Kounrad continued to perform well
in Q4 2024 and maintained its excellent safety record. Full-year
copper production for 2024 was firmly inside the guidance that CAML
set at the start of the year.
"Sasa also achieved solid production
in Q4 2024, despite the transition to paste-fill mining. The
effects of the transition, particularly in the first half of the
year, resulted in full-year production of zinc and lead coming in
around 2% below the guidance range, but I am confident that the
experience gained, along with the progress made in H2 2024, will
enable production to meet guidance in 2025.
"Meanwhile, the Capital Projects
programme at Sasa is essentially complete, with the DST Plant
expected to be operational in Q1 2025.
"As a Group, we look forward to 2025
for another year of safe, reliable production from our existing
operations, and to continuing the search for an acquisition to grow
the business.
"CAML's 2024 annual results are
scheduled to be released on 20 March 2025, at which date the final
dividend for 2024 will also be announced."
Health and Safety
Kounrad had no LTIs during Q4 2024,
and at 31 December 2024 had achieved 2,420 consecutive days LTI
free.
Sasa had one LTI during Q4 2024,
making a total of two LTIs for 2024.
Kounrad
Production
and sales update
Kounrad's Q4 2024 copper production of
3,190 tonnes brings output for 2024 to
13,439 tonnes. Copper sales during Q4 2024 were
3,375 tonnes, for a total of 13,521 tonnes in
2024.
By the end of Q4 2024, winter block
leaching was fully under way at both the Eastern and Western
Dumps.
Sasa
Production
and sales update
Sasa produces a zinc concentrate and a separate
lead concentrate, and typically receives from smelters
approximately 84% of the value of its zinc-in-concentrate and
around 95% of the value of its lead-in-concentrate. Accordingly, Q4
2024 payable production was 4,029
tonnes of zinc and 6,537 tonnes of lead,
bringing total payable production for 2024 to 15,614 tonnes of zinc and 25,286 tonnes of lead.
Payable base-metal-in-concentrate sales for Q4
2024 were 4,134 tonnes of zinc
and 6,389 tonnes of lead, essentially in line with production, and
the totals for the whole of 2024 were 15,839 tonnes and 25,560 tonnes
respectively.
During Q4 2024, Sasa sold 98,468 ounces of payable silver to Osisko Gold
Royalties, in accordance with its streaming agreement, bringing the
total for 2024 to 379,010
ounces.
|
Units
|
Q4
2024
|
Q4
2023
|
2024
|
2023
|
Ore
mined
|
t
|
201,144
|
210,301
|
762,456
|
805,621
|
Plant
feed
|
t
|
198,965
|
209,719
|
760,514
|
805,819
|
Zinc
grade
|
%
|
2.82
|
3.03
|
2.87
|
2.97
|
Zinc
recovery
|
%
|
85.5
|
85.6
|
85.2
|
85.0
|
Lead
grade
|
%
|
3.67
|
3.59
|
3.71
|
3.70
|
Lead
recovery
|
%
|
94.2
|
93.3
|
94.4
|
93.1
|
Zinc
concentrate
|
t (dry)
|
9,504
|
10,720
|
36,967
|
40,226
|
- Grade
|
%
|
50.4
|
50.8
|
50.2
|
50.6
|
- Contained
zinc
|
t
|
4,790
|
5,446
|
18,572
|
20,338
|
Lead
concentrate
|
t (dry)
|
9,762
|
9,915
|
37,596
|
39,136
|
- Grade
|
%
|
70.5
|
70.8
|
70.8
|
71.0
|
- Contained
lead
|
t
|
6,881
|
7,022
|
26,617
|
27,794
|
Capital
Projects - the transition to paste-fill mining and dry-stack
tailings
During Q4 2024 Sasa continued to
place paste-fill in the cut-and-fill production stopes on the
800-metre and 750-metre levels. Long-hole stoping using fill is
also well under way, with additional stopes to follow during 2025.
As in past periods, some previously mined voids were also filled
during Q4 2024. This void-filling provides the necessary ground
stability for current and future mining, as well as allowing a
significant proportion of Sasa's tailings to be stored underground.
Since the Paste Backfill Plant became operational in late 2023,
approximately 40% of the total tailings generated have been placed
as fill.
Construction of the DST Plant is
substantially complete. The plant is expected to be operational in
Q1 2025, following installation of the automation system, slightly
later than originally planned owing to equipment delivery delays
involving third-party suppliers. The first phase of the engineered
landform has been completed, including construction of the drainage
and dewatering channels, ready for the placing of geosynthetic
materials prior to the DST Plant becoming operational. Expansion of
the landform will continue in 2025.
The third element of Sasa's Capital
Projects, the Central Decline, was completed on schedule in
December 2024 with connection to the 750-metre level. The project
has involved total development of 3,735 metres.
Exploration activity
During Q4 2024 Aberdeen Minerals, in
which CAML holds a 28.4% shareholding with warrants to increase to
38.6%, completed the 2024 drilling campaign at its Arthrath
nickel-copper project in northeast Scotland. The drilling, which
totalled nearly 2,700 metres, recovered core including visible
massive sulphides. Assay results are expected in Q1
2025.
CAML Exploration ('CAML X'), an
80%-owned subsidiary of CAML, completed its first full field season
in Kazakhstan during 2024, with the focus on target generation and
licence applications.
2025 guidance
Kounrad is expected to produce
13,000 to 14,000 tonnes of copper in 2025, with guidance maintained
at the level of the preceding year.
Given that the challenges presented
by the mining transition in 2024 have been mostly overcome, Sasa
guidance is also maintained for 2025, at 790,000 to 810,000 tonnes
of ore mined and processed, and metal-in-concentrate production of
19,000 to 21,000 tonnes of zinc and 27,000 to 29,000 tonnes of
lead.
Another factor affecting Sasa during
2025 is the increase in concession fees applicable from 1 January
2025. The rate applicable to Sasa's products (zinc, lead and
silver) increases to 4% of revenue (based on the market value of
metal-in-concentrate produced) from 2% previously.
Total capital expenditure in 2025 is
expected to be in the range $18 million to $21 million, comprising
approximately $4 million to $5 million at Kounrad and $14 million
to $16 million at Sasa. The Kounrad total is higher than the
operation's typical annual sustaining capex, owing to the
allocation of approximately $2 million to move a minor portion of
Dump 15, owing to the proximity of an existing railway
line.
The Sasa total comprises sustaining
capex of $11 million to $12 million, plus capex of approximately $3
million to $4 million predominantly related to continued expansion
of the landform for future dry-tailings deposition.
In addition, exploration spending on
CAML X is expected to total $2 million to $3 million in
2025.
Group capex for 2024 is now expected
to be around the lower end of the guidance of $22 million to $25
million set at the start of last year.
Cash
At 31 December 2024, CAML held a
cash balance of $67.6 million and had no significant
debt.
For further
information contact:
Central Asia Metals
|
Tel: +44 (0) 20 7898 9001
|
Gavin Ferrar
|
|
CEO
|
|
Louise Wrathall
|
|
CFO
|
|
Richard Morgan
|
richard.morgan@centralasiametals.com
|
Investor
Relations Manager
|
|
|
|
Peel Hunt (Nominated Adviser and Joint
Broker)
|
Tel: +44 (0) 20 7418 8900
|
Ross Allister
|
|
David McKeown
Emily Bhasin
|
|
|
|
BMO
Capital Markets (Joint Broker)
|
Tel: +44 (0) 20 7236 1010
|
Thomas Rider
|
|
Pascal Lussier Duquette
|
|
|
|
BlytheRay (PR
Advisers)
|
Tel: +44 (0) 20 7138 3204
|
Tim Blythe
|
|
Megan Ray
|
|
|
|
Note to
editors:
Central Asia Metals, an AIM-quoted UK company
based in London, owns 100% of the Kounrad SX-EW copper project in
central Kazakhstan and 100% of the Sasa zinc-lead mine in North
Macedonia. The Company also owns an 80% interest in CAML
Exploration, a subsidiary formed to progress early-stage
exploration opportunities in Kazakhstan, and a 28.4% interest in
Aberdeen Minerals Ltd, a privately-owned UK company focused on the
exploration and development of base metals opportunities in
northeast Scotland.
For further information, please visit
www.centralasiametals.com and follow CAML on X at @CamlMetals and
on LinkedIn at Central Asia Metals Plc