MONTREAL, July 15, 2021 /PRNewswire/ - Turquoise Hill
Resources Ltd. ("Turquoise Hill" or the "Company") today announced
second quarter 2021 production for Oyu Tolgoi LLC ("Oyu Tolgoi")
and provided an update on the Oyu Tolgoi mine.
Q2 2021 highlights
- In Q2 2021, open pit mining activities were impacted by
personnel shortages due to COVID-19 restrictions. This resulted in
an increase of lower-grade stockpile material being processed
during the quarter.
-
- Copper production of 36,735 tonnes, in-line with Q2 2020 and a
decrease of 19% vs Q1 2021; and
- Gold production of 113,054 ounces, an increase of 263% vs Q2
2020 and a decrease of 22% vs Q1 2021
- Q2 2021 mill throughput was impacted by reduced personnel
numbers due to COVID-19 in addition to planned maintenance
activities. Consequently, Q2 2021 mill throughput of 9.4 million
tonnes was 2% lower than Q2 2020 and 4% lower than Q1 2021.
- Access to higher copper and gold grades from Phase 4B is expected to continue through the remainder
of the year.
COVID-19 Update
COVID-19 cases increased significantly in Mongolia during Q2 2021, causing a series of
lockdowns in the country and South Gobi region which limited the
ability of Oyu Tolgoi to maintain normal roster changes for its
workers. This resulted in personnel numbers below 25% of planned
requirements at certain points during the quarter. COVID-19
restrictions adversely impacted both open pit operations and
underground development progress. The additional 2021 development
cost impact of the known COVID-19 delays up to June 30, 2021 is estimated to be approximately
$100 million. The Company will
continue to monitor the costs associated with COVID-19 delays and
update the market as appropriate.
As at July 9, 2021, the Oyu Tolgoi
workforce is 93% fully vaccinated and appropriate controls continue
to be followed at site. Oyu Tolgoi continues to cooperate with the
Mongolian authorities to implement and maintain control measures to
protect the health and well-being of its workers as well as the
local community.
Underground Development
During Q2 2021, underground development progress was
significantly impacted by the COVID-19 constraints on site and in
Mongolia, including restrictions
on movement of international expertise. Despite these constraints,
Material Handling System 1 is greater than 90% complete and all
development and technical readiness activities pertaining to the
initiation of the undercut have been met or are on track to being
met, to achieve sustainable production in October 2022. Further, recent easing of
quarantine constraints and increasing workforce vaccination rates
have supported gradual improvements in site personnel levels.
Shafts 3 and 4 were also impacted by COVID-19 related quarantine
requirements and travel restrictions with no significant
development progress during the quarter. The impact of further
delays to Shaft 3 and 4 and other activities is currently under
assessment, and could impact production ramp-up post Panel 0.
Turquoise Hill and Rio Tinto continue to engage with various
Mongolian governmental bodies with a view to resolving
outstanding non-technical undercut issues. All parties remain
committed to moving the project forward and ensuring long-term and
mutually beneficial solutions to the issues under discussion.
Delayed resolution of these issues and the slowing of discussions
as a result of the COVID-19 situation in Mongolia, will delay the Company's expected
timing for the initiation of the undercut. Some contractual
commitments for future works such as on Material Handling System 2
and the concentrator upgrade, have experienced delays as entering
into these commitments is currently pending approval of the
Definitive Estimate and required budget uplift by the Oyu Tolgoi
Board. Any significant delay to the initiation of the undercut
would have a material impact on project schedule, including the
timing of sustainable production for Panel 0, as well as the timing
and quantum of underground capital expenditure, which would
materially adversely impact the timing of expected cash flows from
the Oyu Tolgoi underground project thereby increasing the amount of
Turquoise Hill's incremental funding requirement. The Company will
continue to monitor the situation and assess any impact of a delay
to the undercut initiation, and update the market as
appropriate.
Force Majeure
Q2 2021 concentrate shipments to customers were impacted by
COVID-19 related Mongolia /
Chinese border restrictions which resulted in force majeure being
declared from 30 March 2021.
Shipments to Chinese customers recommenced on April 15, 2021 and Oyu Tolgoi continues to work
closely with Mongolian and Chinese authorities to manage the supply
chain disruptions. The force majeure will remain in place until
there are sufficiently sustained volumes of convoys crossing the
border to ensure Oyu Tolgoi's ability to meet its on-going
commitments to customers and to return on-site concentrate
inventory to target levels.
Oyu Tolgoi
Production Data
|
All data
represents full production and sales on a 100% basis
|
|
|
|
|
|
|
|
|
|
|
2Q
|
3Q
|
4Q
|
1Q
|
2Q
|
1H
|
1H
|
Full Year
|
|
2020
|
2020
|
2020
|
2021
|
2021
|
2021
|
2020
|
2020
|
|
|
|
|
|
|
|
|
|
Open pit material
mined ('000 tonnes)
|
23,218
|
23,979
|
23,663
|
22,588
|
15,829
|
38,417
|
50,052
|
97,694
|
Ore treated ('000
tonnes)
|
9,645
|
10,072
|
9,594
|
9,813
|
9,401
|
19,214
|
20,534
|
40,200
|
Average mill head
grades:
|
|
|
|
|
|
|
|
|
Copper (%)
|
0.47
|
0.45
|
0.50
|
0.56
|
0.47
|
0.51
|
0.45
|
0.46
|
Gold (g/t)
|
0.19
|
0.21
|
0.41
|
0.68
|
0.50
|
0.59
|
0.17
|
0.24
|
Silver
(g/t)
|
1.22
|
1.22
|
1.16
|
1.29
|
1.19
|
1.24
|
1.18
|
1.18
|
Concentrates produced
('000 tonnes)
|
169.9
|
168.5
|
190.2
|
201.9
|
173.2
|
375.1
|
334.4
|
693.1
|
Average concentrate
grade (% Cu)
|
21.5
|
21.5
|
21.9
|
22.5
|
21.2
|
21.9
|
21.4
|
21.6
|
Production of metals
in concentrates:
|
|
|
|
|
|
|
|
|
Copper ('000
tonnes)
|
36.5
|
36.3
|
41.6
|
45.4
|
36.7
|
82.2
|
71.7
|
149.6
|
Gold ('000
ounces)
|
31
|
37
|
88
|
146
|
113
|
259
|
57
|
182
|
Silver ('000
ounces)
|
212
|
219
|
231
|
255
|
235
|
490
|
426
|
876
|
Concentrate sold
('000 tonnes)
|
194.3
|
167.9
|
181.5
|
186.3
|
92.6
|
278.9
|
320.2
|
669.6
|
Sales of metals in
concentrates:
|
|
|
|
|
|
|
|
|
Copper ('000
tonnes)
|
39.7
|
34.4
|
37.9
|
39.0
|
19.6
|
58.6
|
65.5
|
137.8
|
Gold ('000
ounces)
|
31
|
34
|
66
|
111
|
73
|
183
|
51
|
150
|
Silver ('000
ounces)
|
220
|
201
|
194
|
207
|
106
|
313
|
366
|
760
|
Metal recovery
(%)
|
|
|
|
|
|
|
|
|
Copper
|
79.1
|
78.9
|
85.9
|
86.3
|
79.7
|
83.4
|
76.7
|
79.6
|
Gold
|
52.0
|
53.7
|
68.8
|
72.2
|
69.3
|
71.0
|
49.3
|
58.6
|
Silver
|
55.8
|
54.6
|
64.3
|
65.3
|
62.5
|
64.0
|
53.6
|
56.4
|
Forward-looking statements and forward-looking
information
Certain statements made herein, including statements relating to
matters that are not historical facts and statements of the
Company's beliefs, intentions and expectations about developments,
results and events which will or may occur in the future,
constitute "forward-looking information" within the meaning of
applicable Canadian securities legislation and "forward-looking
statements" within the meaning of the "safe harbor" provisions of
the United States Private Securities Litigation Reform Act of 1995.
Forward-looking statements and information relate to future events
or future performance, reflect current expectations or beliefs
regarding future events and are typically identified by words such
as "anticipate", "could", "should", "expect", "seek", "may",
"intend", "likely", "plan", "estimate", "will", "believe" and
similar expressions suggesting future outcomes or statements
regarding an outlook. These include, but are not limited to,
statements and information regarding: discussions with, and the
nature of the Company's relationship and interaction with, the
Government of Mongolia on the
continued operation and development of Oyu Tolgoi, including with
respect to the definitive estimate and the potential termination,
amendment or replacement of the Investment Agreement ("IA") or the
Oyu Tolgoi Mine Development and Financing Plan ("UDP"); the
willingness and ability of the parties to the IA or the UDP to
amend or replace the UDP; the implementation and successful
execution of the funding plan that is the subject of the Heads of
Agreement ("HoA") and the amount of any additional future funding
gap to complete the Oyu Tolgoi project as well as the amount and
potential sources of additional funding required therefor, all as
contemplated by the HoA; the expectations set out in the 2020 Oyu
Tolgoi Technical Report ("OTTR20"); the timing and amount of future
production and potential production delays; statements in respect
of the impacts of any delays on achieving first commercial
production the Company's cash flows; expected copper and gold
grades; the merits of the class action complaints filed against the
Company in October 2020 and
January 2021, respectively; the
likelihood that the Company will be added as a party to the
international tax arbitration brought by Oyu Tolgoi against the
Government of Mongolia and the
merits of its defence and counterclaim; liquidity, funding sources
and funding requirements; the amount of any funding gap to complete
the Oyu Tolgoi project; the amount and potential sources of
additional funding; the Company's ability to re-profile its
existing project debt in line with current cash flow projections;
the amount by which a successful re-profiling of the Company's
existing debt would reduce the Company's currently projected
funding requirements; the Company's ability to raise supplemental
senior debt; the timing of studies, announcements and analyses;
status of underground development; the mine design for Panel 0 of
Hugo North Lift 1 and the related cost and production schedule
implications; the re-design studies for Panels 1 and 2 of Hugo
North Lift 1 and the possible outcomes, content and timing thereof;
expectations regarding the possible recovery of ore in the two
structural pillars, to the north and south of Panel 0; the possible
progression of a state-owned power plant ("SOPP") and related
amendments to the Power Source Framework Agreement ("PSFA") as well
as power purchase agreements and extensions to; the timing of
construction and commissioning of the potential SOPP; sources of
interim power; the continuing impact of COVID-19, including any
restrictions imposed by health or governmental authorities relating
thereto on the Company's business, operations and financial
condition, as well as delays and the development cost impacts of
delays caused by the COVID-19 pandemic; capital and operating cost
estimates; mill and concentrator throughput; the outcome of formal
international arbitration proceedings; anticipated business
activities, planned expenditures, corporate strategies, and other
statements that are not historical facts.
Forward-looking statements and information are made based upon
certain assumptions and other important factors that, if untrue,
could cause the actual results, performance or achievements of the
Company to be materially different from future results, performance
or achievements expressed or implied by such statements or
information. There can be no assurance that such statements or
information will prove to be accurate. Such statements and
information are based on numerous assumptions regarding present and
future business strategies, local and global economic conditions,
and the environment in which the Company will operate in the
future, including the price of copper, gold and silver; projected
gold, copper and silver grades; anticipated capital and operating
costs; anticipated future production and cash flows; the
anticipated location of certain infrastructure in Hugo North Lift 1
and sequence of mining within and across panel boundaries; the
availability and timing of required governmental and other
approvals for the construction of the SOPP; the ability of the
Government of Mongolia to finance
and procure the SOPP within the timeframes anticipated in the PSFA,
as amended, subject to ongoing discussions relating to a standstill
period; the willingness of third parties to extend existing power
arrangements; the status and nature of the Company's relationship
and interactions and discussions with the Government of
Mongolia on the continued
operation and development of Oyu Tolgoi and Oyu Tolgoi LLC internal
governance (including the outcome of any such interactions or
discussions); the willingness and ability of the parties to the IA
or the UDP to amend or replace either such agreement; the nature
and quantum of the current and projected economic benefits to
Mongolia resulting from the
continued operation of Oyu Tolgoi; the implementation and
successful execution of the funding plan that is the subject of the
HoA and the amount of any additional future funding gap to complete
the Oyu Tolgoi project as well as the amount and potential sources
of additional funding required therefor, all as contemplated by the
HoA.
Certain important factors that could cause actual results,
performance or achievements to differ materially from those in the
forward-looking statements and information include, among others:
copper, gold and silver price volatility; discrepancies between
actual and estimated production; mineral reserves and resources and
metallurgical recoveries; development plans for processing
resources; public health crises such as COVID-19; matters
relating to proposed exploration or expansion; mining operational
and development risks, including geotechnical risks and ground
conditions; litigation risks, including the outcome of the class
action complaints filed against the Company; the outcome of the
international arbitration proceedings; regulatory restrictions
(including environmental regulatory restrictions and liability);
Oyu Tolgoi LLC or the Government of Mongolia's ability to deliver a domestic power
source for the Oyu Tolgoi project within the required contractual
time frame; communications with local stakeholders and community
relations; activities, actions or assessments, including tax
assessments, by governmental authorities; events or circumstances
(including public health crises strikes, blockades or similar
events outside of the Company's control) that may affect the
Company's ability to deliver its products in a timely manner;
currency fluctuations; the speculative nature of mineral
exploration; the global economic climate; global climate change;
dilution; share price volatility; competition; loss of key
employees; cyber security incidents; additional funding
requirements, including in respect of the development or
construction of a long-term domestic power supply for the Oyu
Tolgoi project; capital and operating costs, including with respect
to the development of additional deposits and processing
facilities; defective title to mineral claims or property; and
human rights requirements. Although the Company has attempted to
identify important factors that could cause actual actions, events
or results to differ materially from those described in
forward-looking statements and information, there may be other
factors that cause actions, events or results not to be as
anticipated, estimated or intended. All such forward-looking
statements and information are based on certain assumptions and
analyses made by the Company's management in light of their
experience and perception of historical trends, current conditions
and expected future developments, as well as other factors
management believes are reasonable and appropriate in the
circumstances. These statements, however, are subject to a variety
of risks and uncertainties and other factors that could cause
actual events or results to differ materially from those projected
in the forward-looking statements or information.
With respect to specific forward-looking information concerning
the continued operation and development of Oyu Tolgoi, the Company
has based its assumptions and analyses on certain factors which are
inherently uncertain. Uncertainties and assumptions include, among
others: the timing and cost of the construction and expansion of
mining and processing facilities; the timing and availability of a
long-term domestic power source (or the availability of financing
for the Company or the Government of Mongolia to construct such a source) for Oyu
Tolgoi; the implementation and successful execution of the funding
plan that is the subject of the HoA and the amount of any
additional future funding gap to complete the Oyu Tolgoi project as
well as the amount and potential sources of additional funding
required therefor, all as contemplated by the HoA; the status and
nature of the Company's relationship, interactions and discussions
with the Government of Mongolia on
the continued operation and development of Oyu Tolgoi and Oyu
Tolgoi LLC internal governance (including the outcome of any such
interactions or discussions); the willingness and ability of the
parties to the IA and the UDP to amend or replace either such
agreement; the nature and quantum of the current and projected
economic benefits to Mongolia
resulting from the continued operation of Oyu Tolgoi; the potential
impact of COVID-19, including any restrictions imposed by health
and governmental authorities relating thereto, as well as the
development cost impacts of delays caused by the COVID-19 pandemic;
the impact of changes in, changes in interpretation to or changes
in enforcement of, laws, regulations and government practices in
Mongolia; the availability and
cost of skilled labour and transportation; the obtaining of (and
the terms and timing of obtaining) necessary environmental and
other government approvals, consents and permits; delays and the
costs which would result from delays, including delays caused by
COVID-19 restrictions and impacts and related factors, in the
development of the underground mine (which could significantly
exceed the costs projected in OTTR20); projected copper, gold and
silver prices and their market demand; and production estimates and
the anticipated yearly production of copper, gold and silver at Oyu
Tolgoi.
The cost, timing and complexities of mine construction and
development are increased by the remote location of a property such
as Oyu Tolgoi. It is common in mining operations and in the
development or expansion of existing facilities to experience
unexpected problems and delays during development, construction and
mine start-up. Additionally, although Oyu Tolgoi has achieved
commercial production, there is no assurance that future
development activities will result in profitable mining
operations.
Readers are cautioned not to place undue reliance on
forward-looking information or statements. By their nature,
forward-looking statements involve numerous assumptions, inherent
risks and uncertainties, both general and specific, which
contribute to the possibility that the predicted outcomes will not
occur. Events or circumstances could cause the Company's actual
results to differ materially from those estimated or projected and
expressed in, or implied by, these forward-looking statements.
Important factors that could cause actual results to differ from
these forward-looking statements are included in the "Risk Factors"
section in the Company's annual information form for the year ended
December 31, 2020 ("AIF"), as
supplemented by the "Risks and Uncertainties" section of the
Company's management's discussion and analysis for the first
quarter ended March 31, 2021
("MD&A").
Readers are further cautioned that the list of factors
enumerated in the "Risk Factors" section of the AIF and in the
"Risks and Uncertainties" section of the MD&A that may affect
future results is not exhaustive. When relying on the Company's
forward-looking statements and information to make decisions with
respect to the Company, investors and others should carefully
consider the foregoing factors and other uncertainties and
potential events. Furthermore, the forward-looking statements and
information contained herein are made as of the date of this
document and the Company does not undertake any obligation to
update or to revise any of the included forward-looking statements
or information, whether as a result of new information, future
events or otherwise, except as required by applicable law. The
forward-looking statements and information contained herein are
expressly qualified by this cautionary statement.
View original content to download
multimedia:https://www.prnewswire.com/news-releases/turquoise-hill-announces-second-quarter-2021-production-and-provides-oyu-tolgoi-mine-update-301335099.html
SOURCE TURQUOISE HILL RESOURCES LTD