Mast
Energy Developments PLC
(Incorporated in England and
Wales)
(Registration Number:
12886458)
LEI :213800HFVHGJ9YGO9F71
Share code on the LSE:
MAST
ISIN: GB00BMBSCV12
('MED' or 'the Company')
Dated: 20 August 2024
Mast Energy Developments PLC
('MED' or 'the Company')
Pyebridge 2nd
Genset Overhaul Commences and Application for Increased CM
Contract
Mast Energy Developments PLC is
pleased to announce the official commencement of the 2nd
genset overhaul, and application for an increased Capacity Market
contract at its Pyebridge flexible power generation asset
("Pyebridge"). The details of the foregoing are set out
below.
Pyebridge Key Highlights
·
First refurbished genset achieving
c. £57k revenue in its first month of operation paved the
way for 2nd genset overhaul;
·
Pyebridge signed Engineering Works contract for
2nd genset's overhaul; and
·
2nd genset overhaul enables Pyebridge
to apply for enhanced capacity CM contract.
Further to the Company's previous
announcement dated 7 August 2024, following the successful
completion of the refurbishment of the first of the Pyebridge
site's 3x 2.7MW Jenbacher gensets (thus 8.1MW generation
capacity in total), and the resulting first refurbished genset
achieving c. £57k revenue (or c. £21k per MW month) in
its first month of operation (inclusive of initial ramp-up period),
Pyebridge has signed an Engineering Works contract with the
Pyebridge site's O&M contractor, Cooper Östlund regarding the
full long-block overhaul of the 2nd genset, and certain
further essential improvements to the site.
In addition to the expected enhanced
revenue generation via Pyebridge's PPA with Statkraft, the overhaul
of the 2nd genset enables, and it is expected that
Pyebridge will apply for its next T-1 CM contract in the upcoming
CM pre-qualification assessment window and subsequent bid auction
for the 2025/2026 delivery year, at an enhanced generation
capacity, which will result in increased contractual gross profit
margin income received from that contract.
Once the work on the 2nd
genset has been completed, Pyebridge will have 2x 2.7MW completely
refurbished gensets operating and generating at optimum capacity
and performance, which should have a direct positive impact
regarding the site's PPA revenue generation accordingly. The plan
remains to overhaul the then remaining 3rd genset in due
course, in order to maximise full reliability, efficiency and
revenue generating ability of the Pyebridge site in the most
cost-efficient manner.
During the time that the work on the
2nd genset will be performed, it is expected that the
site's first refurbished genset will remain operational and will
largely continue to generate revenue via its PPA with Statkraft.
Pyebridge will also keep receiving its current Capacity Market
contract income from the government as previously
announced.
The total costs for the above
referred works on the 2nd genset's overhaul will be
funded under the Project Finance agreement with RiverFort (please
refer to previous announcement dated 28 February 2024 for further
details of the Project Finance), with Pyebridge as the borrower. As
such, the board of MED has agreed with RiverFort a 3rd
Advance against the Project Finance agreement amounting to a gross
total of £1,137,190. The gross draw includes a VAT funding element,
and once the associated VAT has been reclaimed, and an expected
refund for the genset's replaced long-block been received, it will
be paid back to RiverFort (anticipated to be in September),
resulting in a net 3rd Advance of c. £839,658. The
proceeds from the 3rd Advance will solely be used for
the above-mentioned works at Pyebridge on the 2nd
genset's overhaul. The 3rd Advance accelerates the
overhaul of the 2nd genset, and once the work is
completed will result in additional revenue being
generated.
The Project Finance with RiverFort,
has enabled the successful completion of the first genset's
overhaul, as well the commencement of the 2nd genset's
overhaul, and MED is appreciative of RiverFort's ongoing support as
its asset-level strategic funding partner, in order to grow the
business.
Pieter Krügel, MED CEO, commented: "We are pleased to
have officially initiated the 2nd genset's overhaul,
following the successful completion of the 1st genset's
overhaul and its positive maiden performance results. It is
expected that the completion of the 2nd genset's
overhaul will not only see additional enhanced revenue generation
via the Pyebridge site's PPA with Statkraft, but also enable the
application for an enhanced CM contract which will further boost
income.
"MED's funding partnership with RiverFort has been
instrumental in enabling and fast-tracking the work programme at
Pyebridge, which has already resulted in increased revenue
generation sooner than expected. RiverFort's ongoing support to MED
is invaluable and much appreciated.
"We are looking forward to updating the market with further
progress across the board in due course."
ENDS
This announcement contains inside information for the purposes
of the UK version of the Market Abuse Regulation (EU No. 596/2014)
as it forms part of United Kingdom domestic law by virtue of the
European Union (Withdrawal) Act 2018 ('UK MAR'). Upon the
publication of this announcement, this inside information is now
considered to be in the public domain.
For further information please
visit www.med.energy or contact:
Pieter Krügel
|
Info@med.energy
|
Mast Energy
Developments PLC
|
CEO
|
Jon Belliss
|
+44 (0)20 7399 9425
|
Novum Securities
|
Corporate Broker
|