North River Resources Plc Financing Proposal and -4-
11 Agosto 2015 - 1:01AM
UK Regulatory
The Company has been successful in the past in raising small
tranches of equity funding of around US$1.0 million from equity
investors. However, the Independent Directors believe that the
Company's near term funding requirements are such that a larger
raise is necessary to allow management to commit to reaching a
construction decision. The Greenstone Placing:
-- secures US$1.2 million in the relative short term, subject to
Shareholder approval and satisfaction or waiver of the Conditions,
which will allow management to progress project development whilst
the Placing and Open Offer is prepared and launched;
-- provides certainty as to the proceeds of the Placing and Open Offer; and
-- demonstrates the confidence that the Independent Directors
and Greenstone have in the Namib Project, which the Independent
Directors hope will encourage other investors to take up the US$2.8
million to be offered in the Placing and Open Offer.
Accordingly, the Independent Directors consider, having
consulted with Strand Hanson, that the terms of the Greenstone
Placing are fair and reasonable insofar as Shareholders are
concerned.
6. Consequences of failure to approve the Resolution
If the Resolution is not approved and/or the Conditions are not
satisfied or waived, the Greenstone Placing will not proceed.
Without access to the funds from the Greenstone Placing, the
Company would immediately need to seek to secure alternative
sources of funds to enable it to fund its corporate activities in
the period immediately following the General Meeting. The
Independent Directors are unable to provide any assurance that any
alternative financing could immediately be secured or, that if it
were secured, it would be on terms as favourable to the Company or
would not result in a substantial dilution of Shareholders'
interests. If no funds were immediately available, it is highly
likely that the Company would cease to be able to trade, in which
circumstances it is unlikely that there would be any value
attributable to Shareholders. The Independent Directors have,
before entering negotiations with Greenstone, considered
alternative sources of financing (including both debt and equity
funding) and believe it is highly unlikely that the Company could
secure funding on as favourable terms on a timely basis in such
circumstances particularly given the recent downturn in commodity
prices. Even if financing were immediately available and the
Company were able to continue trading, the Independent Directors
believe that the circumstances of such financing could result in a
material adverse effect on the share price of the Company.
7. Update on the Company
As set out in the announcement made by the Company on 22 July
2015, the Company submitted its application for a Mining Licence in
April 2014 while working through the final phase of the DFS, which
was announced in November 2014. The results of the DFS, in
combination with a detailed Board-level review, identified key
additional studies on the mine development plan and mining process
flow sheet that would be required ahead of the Company being in a
position to take an investment decision on the Namib Project.
The Company advanced these studies during the first half of
2015, announcing the results of the metallurgical test work
programme on 22 July 2015. This positions the Company to commence
FEED on an optimised processing plant as well as providing the
catalyst to progress early mine development work. Subject to
receipt of up to US$4.0 million of funding, the Company expects to
be in a position to complete these phases of work during the fourth
quarter of 2015, which will be sufficient to support an investment
decision on the Namib Project.
The Company is cognisant that the above constitutes a revised
timeline to project development of the Namib Project. The
requirement to complete these additional studies, alongside
discussions with the Ministry of Mines and Energy in Namibia (the
"Ministry") on the award of the Mining Licence, have delayed the
originally scheduled commencement of construction of the Namib
Project. As regards the Mining Licence, the Company is pleased to
have hosted the newly appointed Minister of Mines and Energy, the
Honourable Obeth Kandjoze, as well as a ministerial delegation on a
recent site visit at the Namib Project. The Company looks forward
to continuing to work with the Ministry on the Mining Licence
application and remains confident that the Mining Licence will be
granted in due course, but this cannot be guaranteed.
In light of the above, the Company has devised a revised funding
strategy for the Namib Project. Subject to timing of commencing
construction and the definitive capital requirement estimate post
completion of early engineering and design, the Company estimates a
total funding requirement of between US$25 million and US$30
million through to expected project commissioning of the Namib
Project. It is the Company's intention that this financing will be
structured in two phases:
(a) an initial equity fundraising of US$4.0 million to cover the
short term working capital required for initial FEED, early
development of the Namib Project's North decline, sourcing of plant
and equipment, and the ongoing underground development programme
required to establish access for the next phase of resource
expansion drilling (being the Phase One Fundraising). This is
intended to finance the Company to take the Namib Project through
to the end of 2015 and a construction decision, assuming that the
Mining Licence is issued and Phase Two Fundraising is achieved
without undue delay (it being noted that the current Work Programme
nominally assumes that the Mining Licence will be issued on or
before 31 October 2015); and
(b) a second fundraising, subject to the formal grant and issue
of the Mining Licence by the Namibian authorities, which will
comprise both debt and equity, and which will cover the cost of
construction and an ongoing resource expansion drilling programme
("Phase Two Fundraising").
Should the Resolution be approved by Shareholders and the
Conditions be satisfied or waived, the Greenstone Placing and the
Open Offer and Placing will together comprise the Phase One
Fundraising.
As noted above, the Company has an immediate funding requirement
which it aims to address through the issue of the Tranche One Notes
pursuant to the Greenstone Placing (conditional on Shareholders
approving the Resolution and the Conditions being satisfied or
waived).
Subject to Shareholders approving the Resolution, the balance of
the funds required under the Phase One Fundraising will be raised
pursuant to the Open Offer and Placing, which itself is being
conditionally fully underwritten by the Underwriting Facility
pursuant to the Greenstone Placing. It is the Company's intention
that the Open Offer and Placing will be launched during September
2015. The Company looks forward to updating Shareholders in due
course as to the terms of, and definitive timetable for, the Open
Offer and Placing.
Assuming the Open Offer and the Placing proceed to raise US$2.8
million, the Tranche One Notes will be converted either fully or in
part (depending on the Issue Price and the FT Exchange Rate) such
that Greenstone will hold no more than 29.99 per cent. of the
Issued Share Capital following the Open Offer and the Placing and
such conversion, and no further Convertible Loan Notes will be
issued.
While the Company believes that the total amount of US$4.0
million proposed to be raised pursuant to the Open Offer and the
Placing, including the Greenstone Placing, should be sufficient for
the Phase One Fundraising provided that the Mining Licence is
issued and Phase Two Fundraising is achieved without undue delay,
it is possible that additional working capital may be required if
there are delays or unexpected costs and/or if the Company is not
permitted to disburse funds raised pursuant to the Greenstone
Placing (which are limited to purposes stated in the Work
Programme) in respect of any of its costs. It is noted that the
Company has been engaging with multiple parties in order to prepare
for the inclusion of a debt package into the Namib Project's Phase
Two Fundraising package at the point of a construction decision.
While conversations with debt providers continue to progress, it is
clear that the availability of debt for the sector is becoming
tougher to obtain due to weak commodity prices, even for
commodities with positive fundamentals such as zinc and lead. The
Company is conscious that there is no guarantee that debt finance
will be available at the relevant time and as such is aware of the
need to make the necessary provisions for this in its financing
strategy. On completion of the FEED phase the Company intends to
progress debt discussions as a priority and will update its
Shareholders on the outcomes of this process, as well as the other
financing instruments that are being considered. The Company is
therefore proposing to obtain additional authority pursuant to the
Resolution to raise further equity of up to a further US$2.0
million for working capital purposes free from statutory
pre-emption rights.
8. Information regarding Greenstone
North River (LSE:NRRP)
Gráfica de Acción Histórica
De Dic 2024 a Ene 2025
North River (LSE:NRRP)
Gráfica de Acción Histórica
De Ene 2024 a Ene 2025