TSX:
GMIN
OTCQX: GMINF
All amounts are in USD unless stated
otherwise
- First gold pour at Tocantinzinho achieved on time and budget,
only 22 months after the formal construction decision
- Commercial production and subsequent ramp-up to nameplate plant
capacity of 4.7 million tonnes per annum expected to be
achieved in H2-24
- Over 2.6 Mt of ore, containing over 78,000 gold ounces, mined
and stockpiled ahead of the processing plant ramp-up
BROSSARD, QC, July 9, 2024
/CNW/ - G Mining Ventures Corp. ("GMIN"
or the "Corporation") (TSX: GMIN) (OTCQX: GMINF) is pleased
to announce that it has completed its first gold pour at GMIN's
100%-owned Tocantinzinho Gold Project ("TZ" or the
"Project") in the State of Pará, Brazil. The first pour yielded
approximately 440 ounces of gold, and the Project remains on time
and budget for commercial production in the second half of
2024. Once in commercial production, TZ will become
Brazil's third-largest primary
gold mine.
Louis-Pierre Gignac, President
& Chief Executive Officer, commented: "I am delighted to
announce that TZ has achieved the significant milestone of the
first gold pour, less than two years after the formal construction
decision. The team successfully constructed TZ on time and in line
with the original budget while maintaining an outstanding safety
record. This milestone is a testament to the strength of our
self-perform approach and demonstrates our competitive advantage. I
sincerely thank our employees and contractors for their remarkable
efforts in achieving this milestone. I look forward to ramping up
the operation to commercial production in the second half of 2024.
We are excited about TZ's future and its significant role in
Brazil's gold mining
industry."
Construction of TZ was launched in September 2022, following the completion of a
Definitive Feasibility Study ("DFS") dated February 09, 2022 (filed under GMIN's profile on
Sedar, entitled "Feasibility Study – NI 43-101 Technical Report,
Tocantinzinho Gold Project."), which confirmed TZ's potential to be
a cornerstone asset for GMIN. The DFS contemplates a 10.5-year mine
life with an average annual gold production of 175,000 ounces with
an initial capital cost of $458
million. The DFS displayed robust economics at a
$2,000/oz gold price assumption,
including an after-tax NPV5% of $1.0
billion and an after-tax IRR of 34%.
Since the start of hot commissioning on June 11, 2024, approximately 77 thousand tonnes
of ore have been processed through the TZ process plant, with all
circuits operating as expected. At the end of June, approximately
2.6 million tonnes ("Mt") of ore have been stockpiled, with
2.1 Mt grading 0.80 g/t Au in the low-grade stockpile and 0.6 Mt
grading 1.31 g/t Au in the high-grade stockpile.
Project Development Timeline
The Project remains on track and budget for commercial
production in H2-2024.
Virtual Site Tour and Feasibility Study Presentation
Updated satellite imagery and 360 photography showing the site
progress is available through the corporate presentation at:
https://vrify.com/decks/14338. A 3D presentation of the
Project Feasibility Study is available at: Feasibility Study 3D
VRIFY Presentation. Both presentations can be accessed by
visiting GMIN's website at https://www.gminingventures.com.
Timetable and Next Steps
Upcoming key milestones include:
- July 9, 2024: GMIN's Annual
General and Special Shareholders Meeting for the approval of
transaction with Reunion Gold Corporation and annual corporate
matters
- July 15, 2024: Anticipated
closing of the transaction with Reunion Gold Corporation
- H2-24: Commercial production
Qualified Person
Louis-Pierre Gignac, President
& Chief Executive Officer of GMIN, a QP as defined in NI
43-101, has reviewed the press release on behalf of the Corporation
and has approved the technical disclosure contained in this press
release.
About G Mining Ventures Corp.
G Mining Ventures Corp. (TSX: GMIN) (OTCQX: GMINF) is a mining
company engaged in the acquisition, exploration and development of
precious metal projects to capitalize on the value uplift from
successful mine development. GMIN is well-positioned to grow into
the next mid-tier precious metals producer by leveraging strong
access to capital and proven development expertise. GMIN is
currently anchored by its flagship Tocantinzinho Gold Project in
mining friendly and prospective State of Pará, Brazil.
Additional Information
For further information on GMIN, please visit the website at
www.gmin.gold.
Cautionary Statement on Forward-Looking Information
All statements, other than statements of historical fact,
contained in this press release constitute "forward-looking
information" and "forward-looking statements" within the meaning of
certain securities laws and are based on expectations and
projections as of the date of this press release. Forward-looking
statements contained in this press release include, without
limitation, those related to (i) the Project remaining on schedule
and on budget for commercial production in H2-2024 (with subsequent
ramp-up to nameplate plant capacity also to be achieved in
H2-2024); (ii) the Project's expected economics as set out in the
DFS; (iii) the anticipated annual production of 175,000 ounces of
gold over a 10.5-year mine of life; (iv) the Project becoming
Brazil's third-largest primary
gold mine; (v) the anticipated closing of the transaction with
Reunion Gold on July 15, 2024; (vi)
the quoted expectations of GMIN's President & Chief Executive
Officer; and (vii) more generally, the horizontal bar
chart entitled "Project Development Timeline" as well as the
sections entitled "Timetable and Next Steps" and "About G Mining
Ventures Corp.".
Forward-looking statements are based on expectations,
estimates and projections as of the time of this press release.
Forward-looking statements are necessarily based upon a number of
estimates and assumptions that, while considered reasonable by the
Corporation as of the time of such statements, are inherently
subject to significant business, economic and competitive
uncertainties and contingencies. These estimates and assumptions
may prove to be incorrect. Such assumptions include,
without limitation, those relating to the price of gold and
currency exchange rates, those outlined in the DFS and those
underlying the items listed on the above sections entitled
"Timetable and Next Steps" and "About G Mining Ventures
Corp.".
Many of these uncertainties and contingencies can directly or
indirectly affect, and could cause, actual results to differ
materially from those expressed or implied in any forward-looking
statements. There can be no assurance that, notably but without
limitation, the Corporation will (i) continue to progress on all
fronts at TZ, (ii) keep its expenditures and schedule in line with
the DFS, (iii) carry its next steps as per the above timetable and
effect the transition to production as contemplated, to bring the
Project into commercial production in H2-2024, or at all, (iv) grow
TZ into Brazil's third-largest
primary gold mine, (v) use TZ to grow GMIN into the next
intermediate producer, or (vi) complete its transaction with
Reunion Gold Corporation, as currently contemplated or at all, as
future events could differ materially from what is currently
anticipated by the Corporation. In addition, there can be no
assurance that the State of Pará, in Brazil, will remain a mining friendly and
prospective jurisdiction.
By their very nature, forward-looking statements involve
inherent risks and uncertainties, both general and specific, and
risks exist that estimates, forecasts, projections and other
forward-looking statements will not be achieved or that assumptions
do not reflect future experience. Forward-looking statements are
provided for the purpose of providing information about
management's expectations and plans relating to the future. Readers
are cautioned not to place undue reliance on these forward-looking
statements as a number of important risk factors and future events
could cause the actual outcomes to differ materially from the
beliefs, plans, objectives, expectations, anticipations, estimates,
assumptions and intentions expressed in such forward-looking
statements. All of the forward-looking statements made in this
press release are qualified by these cautionary statements and
those made in the Corporation's other filings with the securities
regulators of Canada including,
but not limited to, the cautionary statements made in the relevant
sections of the Corporation's (i) Annual Information Form dated
March 27, 2024, for the financial
year ended December 31, 2023, and
(ii) Management Discussion & Analysis. The Corporation cautions
that the foregoing list of factors that may affect future results
is not exhaustive, and new, unforeseeable risks may arise from time
to time. The Corporation disclaims any intention or obligation to
update or revise any forward-looking statements or to explain any
material difference between subsequent actual events and such
forward-looking statements, except to the extent required by
applicable law.
View original content to download
multimedia:https://www.prnewswire.com/news-releases/g-mining-ventures-announces-first-gold-pour-at-tocantinzinho-project-302192092.html
SOURCE G Mining Ventures Corp