Cadence Minerals
Plc
("Cadence Minerals",
"Cadence", or "the Company")
Optimisation Study Delivers
Material Capital Savings at the Amapá Iron Ore
Project
Cadence Minerals (AIM/NEX: KDNC;
OTC: KDNCY) is pleased to report the successful completion of its
capital expenditure optimisation program at the Amapá Iron Ore
Project (the "Project", "Amapa" or "Amapá Project"). The program
has identified significant savings in processing plant
recommissioning and increased production. The optimisation study
was conducted at a pre-feasibility level and marks an important
milestone in the company's progress towards achieving
cost-efficient and sustainable operations.
Highlights:
· PFS-level optimisation studies (the "Study") have identified
33% (US$63.2 million) of capital savings associated with the
beneficiation plant at the Amapá Project.
· The
Study has resulted in a forecast increase in production of
approximately 4.8% to 5.5 Mtpa of iron ore concentrate, of which
4.51 will be a 65% product and 0.99 Mtpa a 62% product.
· Alongside our joint venture partners, we plan to redesign the
mine plan to reduce mining costs.
· The
revised capex and mine plan will form the basis of an amended
economic assessment at a PFS level.
· Fully
committed to advancing the development of a 67% "Green Iron" Fe
product flow sheet at a production rate of 5.5 Mtpa.
· The
capital requirement for the entire Project is now in the bottom
quartile of comparables at US$58 per million tonnes of annual
capacity.
· The
Study was completed ahead of schedule, so we do not anticipate any
delays to the timeline already announced.
Cadence CEO Kiran Morzaria
commented: "We're
thrilled to announce the successful completion of our capital
expenditure optimisation program at the Amapá Iron Ore Project.
This effort has delivered a substantial 33% reduction in capital
costs, saving $63.2 million and forecasted a 4.8% to 5.5 Mtpa
increase in iron ore concentrate
production.
Moreover, given the Study was completed ahead of schedule, we
do not anticipate any delays to the timeline already announced,
even with the additional work associated with optimising the mine
plan to accommodate the increased production.
We
remain fully committed to advancing the development of the 67% Fe
product flow sheet, aligning with our vision for sustainable growth
and value maximisation."
Background to Optimisations Studies
As per the announcement made on 7
March 2024, our joint venture company Pedra and Branca Alliance
("PBA"), which owns 100% of the Amapá Iron Ore project, engaged an
engineering firm in 2023 to carry out an in-depth review of the
processing plant flowsheet to significantly reduce capital and
operating expenditures and, possibly, improving the iron ore
concentrate quality.
We are pleased to report that the
review of capital and operating expenditures is complete, and the
67% flow sheet development continues.
Results from Amapá Project Optimisation
Studies
This part of the optimisation study
focused on the iron ore beneficiation plant at the Amapá Project.
It aimed to reduce the capital and operational expenditure while
producing a product mix of 65% Blast Furnace Pellet Feed ("BFPF")
and 58% spiral concentrate.
An independent Chinese consulting
engineering company carried out this work and identified several
material capital savings, particularly in the equipment and
materials suppliers. As a result of their work, the direct and
indirect capital associated with the beneficiation plant has been
reduced by US$63.2 million (approximately 33%) from US$191.7
million to US$128.5 million. Utilising the comparables within the
PFS report published in 2023, the entire capital required for the
Amapá Project is in the bottom quartile of capital intensity at
US$58 per million tonnes of capacity; the median of the comparable
projects is US$142 per million tonnes of capacity.
In addition, the utilisation and
availability rates of the beneficiation plant were increased,
resulting in an increase in plant throughput and production from
5.28 million tonnes per annum ("Mtpa") to 5.5 Mtpa, both on a dry
basis. This also led to a marginal reduction in operating costs.
Out of the 5.5 Mtpa, approximately 4.51 Mtpa will be 65% BFPF, and
0.99 Mtpa will be a 58% spiral concentrate.
Next Steps
Based on the positive results
derived from the optimisation study, which included an increase in
throughput, we have decided, in conjunction with our joint venture
partners, to redesign the mine plan to reduce mining costs. As
already highlighted, the Study was completed ahead of schedule.
Therefore, we do not anticipate any delays in the already announced
timeline.
This revision and the revised capex
will form the basis of an amended economic assessment of the
Project at a PFS level. Additionally, we are fully committed to
advancing the development of the 67% Fe product flow sheet, as
previously outlined in the announcement on 7 March 2024. We also
anticipate it being at a production rate of 5.5 Mtpa.
About the Amapá Project and Cadence's
Ownership
The Amapá Project is a brownfield
integrated iron ore project in the Amapá State of Brazil. It has
Mineral Resources of 276 million tonnes (Mt) at 38.33% Iron (Fe)
and Ore Reserves of 196 Mt at 39.34%. The Project consists of the
mine, processing plant, wholly owned port and a 194km railway, all
operated by PBA. A PFS was published in January 2023. The PFS
delivered a post-tax net present value of US$949 million at a
discount rate of 10% and a post-tax internal rate of return of 34%,
with an average annual life of mine EBITDA of US$235 million
annually. In the PFS, after ramp-up, the planned yearly average
production was forecast to be 5.3 Mtpa of Fe concentrate,
consisting of 4.4 Mtpa at 65.4% Fe and 0.9 Mtpa at 62% Fe
concentrate. Over the life of the mine, The Project is forecast to
deliver free on-board C1 Cash Costs of US$35.53 / dry metric
tonne.
At the end of September 2023,
Cadence's total investment in the Amapá Project stood at
approximately US$12.1 million, with the equity stake in the Project
standing at 32.6%. Since then, Cadence has continued to invest in
the Amapá Project, and a further updated equity position will be
provided at the end of March 2024.
For further information
contact:
|
|
Cadence Minerals plc
|
+44
(0) 20 3582 6636
|
Andrew Suckling
|
|
Kiran Morzaria
|
|
|
|
WH
Ireland Limited (NOMAD & Broker)
|
+44
(0) 20 7220 1666
|
James Joyce
|
|
Darshan Patel
|
|
|
|
Fortified Securities - Joint Broker
|
+44
(0) 20 3411 7773
|
Guy Wheatley
|
|
|
|
Brand Communications
|
+44
(0) 7976 431608
|
Public & Investor
Relations
|
|
Alan Green
|
|
Qualified Person
Kiran Morzaria B.Eng. (ACSM), MBA,
has reviewed and approved the information contained in this
announcement. Kiran holds a Bachelor of Engineering (Industrial
Geology) from the Camborne School of Mines and an MBA (Finance)
from CASS Business School.
Cautionary and
Forward-Looking Statements
Certain statements in this
announcement are or may be considered forward-looking.
Forward-looking statements are identified by their use of terms and
phrases such as "believe", "could", "should", "envisage",
"estimate", "intend", "may", "plan", "will", or the negative of
those variations or comparable expressions
including references to assumptions. These forward-looking
statements are not based on historical facts but rather on the
Directors' current expectations and assumptions regarding the
company's future growth results of operations
performance, future
capital, and other expenditures (including the
amount, nature, and sources of funding thereof) competitive
advantages business prospects and opportunities. Such
forward-looking statements reflect the Directors' current beliefs
and assumptions and are based on information currently available to
the Directors. Many factors could cause actual results to
differ materially from the results discussed in the forward-looking
statements, including risks associated with vulnerability to
general economic and business conditions, competition,
environmental and other regulatory changes actions by governmental
authorities, the availability of capital markets reliance on key
personnel uninsured and underinsured losses and other factors many
of which are beyond the control of the company. Although any
forward-looking statements contained in this announcement are based
upon what the Directors believe to be reasonable assumptions. The
company cannot assure investors that results will be consistent
with such forward-looking statements.
The information contained within this announcement is deemed
by the company to constitute Inside Information as stipulated under
the Market Abuse Regulation (E.U.) No. 596/2014, as it forms part
of U.K. domestic law under the European Union (Withdrawal) Act
2018, as amended. Upon the publication of this announcement via a
regulatory information service, this information is considered to
be in the public domain.