The Secretariat of Environment and Sustainability in the
Brazilian state of Pará (SEMAS) issued a statement late on Monday
stating it will order Norwegian aluminium company Norsk Hydro ASA's
alumina refinery Alunorte to cut production by 50 percent due to
non-compliance with a resolution to achieve a freeboard of 1 meter
in the bauxite residue deposit DRS1. In addition, SEMAS said it
would order the Paragominas bauxite mine to suspend operations at
one of two tailing dams at the plant.
SEMAS said it would formally notify the company on Tuesday, 27
February.
In the original resolution from Friday, 23 February, SEMAS
ordered Alunorte to reduce the water level in the DRS1 deposit
following extreme rainfall on 16-17 February that led to regional
flooding.
"We have taken considerable measures to meet the deadline at
Alunorte, and we will continue with full force to make sure that we
comply with expectations and requirements," says Hydro CEO Svein
Richard Brandtzæg. "We will continue our dialog with local
authorities to ensure that we take all necessary steps to ensure
safe and sound operations - with respect for people, the
environment and for the local communities that we are a part of,"
Brandtzæg says.
While it is too early to determine the size and impact of the
resolution, it could potentially have significant operational and
financial consequences.
Measures implemented at Alunorte to comply with SEMAS'
resolution have led to continuous improvement in the average DRS1
freeboard - the distance between the top of the tailing dam and the
water level.
The resolution by SEMAS came after Brazilian environment
minister José Sarney Filho expressed similar concerns during a
press conference on Monday evening local Brazilian time, calling on
the Brazilian Institute of the Environment and Natural Resources
(IBAMA) to implement any necessary mitigating actions to remedy the
worries about a possible water contamination in the local area,
including fines or a possible suspension of activities at
Alunorte.
SEMAS also said it would introduce daily fines of around BRL 1
million until Alunorte reached a freeboard of at least 1 meter at
DRS1.
Hydro owns 92.1 percent of the Alunorte alumina refinery and 100
percent in the Paragominas bauxite mine.
Investor contactsStian Hasle+47
97736022Stian.Hasle@hydro.com
Even Simonsen +47 97953364Even.Simonsen@hydro.com
Press contactHalvor Molland+47
92979797Halvor.Molland@hydro.com
Cautionary note Certain statements included in this announcement
contain forward-looking information, including, without limitation,
information relating to (a) forecasts, projections and estimates,
(b) statements of Hydro management concerning plans, objectives and
strategies, such as planned expansions, investments, divestments,
curtailments or other projects, (c) targeted production volumes and
costs, capacities or rates, start-up costs, cost reductions and
profit objectives, (d) various expectations about future
developments in Hydro's markets, particularly prices, supply and
demand and competition, (e) results of operations, (f) margins, (g)
growth rates, (h) risk management, and (i) qualified statements
such as "expected", "scheduled", "targeted", "planned", "proposed",
"intended" or similar.
Although we believe that the expectations reflected in such
forward-looking statements are reasonable, these forward-looking
statements are based on a number of assumptions and forecasts that,
by their nature, involve risk and uncertainty. Various factors
could cause our actual results to differ materially from those
projected in a forward-looking statement or affect the extent to
which a particular projection is realized. Factors that could cause
these differences include, but are not limited to: our continued
ability to reposition and restructure our upstream and downstream
businesses; changes in availability and cost of energy and raw
materials; global supply and demand for aluminium and aluminium
products; world economic growth, including rates of inflation and
industrial production; changes in the relative value of currencies
and the value of commodity contracts; trends in Hydro's key markets
and competition; and legislative, regulatory and political
factors.
No assurance can be given that such expectations will prove to
have been correct. Hydro disclaims any obligation to update
or revise any forward-looking statements, whether as a result of
new information, future events or otherwise.
This information is subject of the disclosure requirements
pursuant to section 5-12 of the Norwegian Securities Trading
Act.
Norsk Hydro (LSE:NHY)
Gráfica de Acción Histórica
De Nov 2024 a Dic 2024
Norsk Hydro (LSE:NHY)
Gráfica de Acción Histórica
De Dic 2023 a Dic 2024