TIDMRSG
RNS Number : 6683X
Resolute Mining Limited
27 April 2023
27 April 2023
Quarterly Activities Report
For the quarter ending 31 March 2023 ('March quarter' or 'the
Quarter')
Highlights
-- Total Recordable Injury Frequency Rate (TRIFR) increased to
0.85 from 0.41 in the preceding Quarter
-- Quarterly production (gold poured) of 92,259 ounces (oz), the
sixth consecutive quarter of increased production
-- All-In Sustaining Cost (AISC) of $1,453/oz for the Quarter, a
6% reduction from the December quarter benefiting from a build up
of stockpiles at both Syama and Mako
-- Quarterly gold sales of 88,151oz at an average realised gold
price in line with the average spot price of $1,890/oz compared to
93,326oz at an average realised gold price of $1,817/oz in the
previous quarter
-- Cash generation of $16.2 million excluding debt, interest
payments, working capital and other movements
-- $25 million was repaid on the Group's term loan facility, and
$5 million was repaid on the Revolving Credit Facility (RCF)
-- Net Debt of $19.9 million (down 37% from $31.6 million),
including Cash and Bullion of $75.8 million. Available liquidity
(Cash, Bullion and undrawn RCF) of $155.8 million
-- Ore Reserves and Mineral Resource Statement released on 8
March 2023 indicating a 15% (0.6Moz) increase in Ore Reserves to
4.6Moz and an 18% (1.7Moz) increase in Mineral Resource to 11.2Moz
of gold, both net of depletion
-- Syama North Mineral Resources increased to 3.2Moz, and Ore Reserves increased to 854koz
-- Syama North prefeasibility study (PFS) on track, with
expected outcomes to be available mid-2023
-- On track for full year guidance for 2023 of 350,000oz at an AISC of $1,480/oz
Note: Unless otherwise stated, all dollar figures are United
States dollars ($).
Resolute Mining Limited (Resolute, the Company or the Group)
(ASX/LSE: RSG) is pleased to present its Quarterly Activities
Report for the period ended 31 March 2023.
Terry Holohan, CEO and Managing Director, commented, "I am
pleased to report another solid quarter for Resolute, recording a
sixth consecutive increase in production with 92,259 oz of gold
poured, underpinned by improved productivity at all three mines
(Syama Sulphide, Syama Oxide and Mako). This is a significant
achievement especially given the pre-planned seven day downtime for
roaster maintenance at the Syama Sulphide operations, towards the
end of the Quarter. Costs for the Quarter improved 6% compared to
the December quarter, benefiting from stockpile build up, as the
Company mined more material than was processed across all
sites.
"The Company's focus for the remainder of 2023 at Mako is on the
planned pit extension, with mining for the remainder of the year
through a lower grade section. The Company expects the June and
September quarterly production levels to decrease marginally as the
operations move through this section of the pit. Once the extension
is complete, operations at Mako will return to the higher grade ore
and benefit from lower stripping ratios, thus enabling higher
production for the remainder of the mining life, out to 2025.
"At Syama, the emphasis remains on progressing the Syama North
PFS, with expected outcomes to be available mid-2023. The Scoping
study supports a low capital expansion costing between $40 - $50
million for items that will increase the sulphide processing
capacity by up to 60% from a nominal 2.4 million tonnes per annum
(Mtpa) capacity up to 4.0Mtpa with an expected lowering of unit
operating costs.
"The overall Company focus remains on reducing costs across both
operations, whilst maintaining the improved production particularly
at Syama, with a number of initiatives already underway across the
Group."
Operations Overview
The Company's performance compared to the previous quarter and
the prior comparable quarter, is set out below:
Mining
---------------------------------------------------------------------------
Ore Mined t 1,901,682 1,831,293 4% 1,649,964
------------------------ ------ ---------- ---------- ----- ----------
Mined Grade g/t 2.24 2.03 10% 1.88
------------------------ ------ ---------- ---------- ----- ----------
Processing
---------------------------------------------------------------------------
Ore Processed t 1,471,547 1,536,503 (4%) 1,275,252
------------------------ ------ ---------- ---------- ----- ----------
Processed Grade g/t 2.33 2.10 11% 2.01
------------------------ ------ ---------- ---------- ----- ----------
Recovery % 85.2 86.3 (1%) 87.7
------------------------ ------ ---------- ---------- ----- ----------
Gold Poured oz 92,259 91,777 1% 81,770
------------------------ ------ ---------- ---------- ----- ----------
Sales
---------------------------------------------------------------------------
Gold Sold oz 88,151 93,326 (6%) 88,773
------------------------ ------ ---------- ---------- ----- ----------
Average Realised Price $/oz 1,890 1,817 4% 1,846
------------------------ ------ ---------- ---------- ----- ----------
Costs
---------------------------------------------------------------------------
AISC $/oz 1,453 1,547 (6%) 1,383
------------------------ ------ ---------- ---------- ----- ----------
Table 1: Resolute Group Operational Performance Summary
Refer to the Appendix for Resolute's production and costs for
the March 2023 Quarter.
Environmental Social Governance
Resolute's TRIFR at 31 March 2023 was 0.85, an increase compared
to the previous quarter, due to a rise in first aid and medical
treatment injuries, especially at Syama. Corporate and Site
management teams are monitoring the incidents and working on
strategies to raise awareness on behavioural-based safety, which
has been the root cause of the majority of those incidents.
Following the award of the International Organization for
Standardisation (ISO) certification for ISO:45001:2018
(Occupational Health & Safety) and ISO:14001:2015
(Environmental Management Systems), the Company is focusing its
efforts on closing out follow-up actions, in preparation for Year 1
surveillance audits, which are scheduled for later in the year.
Syama, Mali
The Syama sulphide operation produced 41,142oz, a decrease of 5%
from the prior quarter. AISC remained in line with the prior
quarter at $1,389/oz. The oxide operations had another steady
quarter with production of 17,513oz at an AISC of $1,659/oz.
Further details of these two operations are set out below.
Syama sulphide
Ore Grade Ore Grade Recovery Gold Poured AISC
(t) (g/t) (t) (g/t) (%) (oz) ($/oz)
--------------- -------- ------- -------- ------- --------- ------------ --------
December 2022 665,297 2.74 561,475 2.83 79.1 43,508 1,400
--------------- -------- ------- -------- ------- --------- ------------ --------
March 2023 630,445 2.86 549,072 2.99 79.1 41,142 1,389
--------------- -------- ------- -------- ------- --------- ------------ --------
Table 2: Sulphide Production and Cost Summary
The underground mined grade increased to 2.86g/t from 2.74g/t in
the prior quarter, this was as per schedule with the current mine
sequence and areas mined. Ore volumes mined remained high for the
Quarter to allow a build-up of stockpiles to provide a strong
position leading into the middle of the year and the coming wet
season.
Ore processed was comparable with the previous quarter with the
processing grade increasing to 2.99g/t with preferential ore
blending delivered from the underground. Gold poured reduced 5% to
41,142oz impacted by a planned seven-day roaster shutdown towards
the end of the Quarter to complete minor maintenance work on the
fluoseal return leg to the roaster.
AISC of $1,389/oz reduced from the December quarter, with cash
costs remaining in line with December and a reduction in gold drawn
from the circuit.
Syama oxide
Ore Grade Ore Grade Recovery Gold Poured AISC
(t) (g/t) (t) (g/t) (%) (oz) ($/oz)
--------------- -------- ------- -------- ------- --------- ------------ --------
December 2022 384,996 1.55 430,882 1.41 88.0 17,834 1,693
--------------- -------- ------- -------- ------- --------- ------------ --------
March 2023 495,293 1.83 421,203 1.56 84.9 17,513 1,659
--------------- -------- ------- -------- ------- --------- ------------ --------
Table 3: Oxide Production and Cost Summary
The majority of the ore mined of 495,293t was sourced from the
Tabakoroni pits. Additionally, mining commenced at the Folona pit
during the Quarter.
The increased mined grade provided an 11% increase to the
processed grade, partially offset by a lower recovery rate due to
high organic carbon in the mill feed resulting in gold poured of
17,513oz in line with the December quarter.
Oxide AISC/oz reduced by 3% from the December quarter to
$1,659/oz with operational costs increasing due to the increase in
volume mined during the Quarter, offset by build-up of ore
stockpiles and gold in circuit.
Mako, Senegal
Mako gold production for the Quarter was 33,604oz at an AISC of
$1,307/oz. The operational performance for Mako is set out in the
table below.
Ore Grade Ore Grade Recovery Gold Poured AISC
(t) (g/t) (t) (g/t) (%) (oz) ($/oz)
--------------- -------- ------- -------- ------- --------- ------------ --------
December 2022 781,000 1.68 544,146 1.91 92.3 30,435 1,520
--------------- -------- ------- -------- ------- --------- ------------ --------
March 2023 775,944 1.99 501,272 2.26 92.3 33,604 1,307
--------------- -------- ------- -------- ------- --------- ------------ --------
Table 4: Mako Production and Cost Summary
Ore mined at Mako remained in line with the December quarter.
Throughput decreased 8%, due to a mill reline during the Quarter.
The mill feed grade increased by 18%, reflecting a higher mine
grade, resulting in a 10% increase in gold poured of 33,604oz from
the prior quarter.
AISC decreased 14% to $1,307/oz, with increased gold poured and
reduced sustaining capital spend. Total operational costs remained
in line with the prior quarter, with a build-up in stockpiles.
The Company completed the acquisition of the Mako power plant
during the Quarter. This purchase will reduce the ongoing
operational overheads for power generation at the mine site.
Gold poured at Mako will decrease over the remainder of the year
as the focus moves to the Stage 6 pit extension. During this
period, the Company will be mining through a lower grade section in
the Mako pit.
Exploration
Total exploration spend for the March quarter was $5.2 million,
primarily on Syama North.
An updated Mineral Resource estimate for Syama North was
announced on 19 January with an increase to 34 million tonnes at
2.9g/t Au for 3.18 million ounces.
The drilling program at Syama North is ongoing and will be
extended throughout 2023 with the expectation of increasing the
Mineral Resources. The sulphide mineralisation remains open at
depth and appears to be contiguous along the entire 6km strike
length of the Alpha to A21 deposits.
Infill drilling will continue similarly to the previous period
to convert more of the 1.3 million ounces of Inferred resources to
indicated in the updated Resource Model.
To date exploration drilling has been restricted to zones within
150m of the surface to concentrate on identifying open pit
extractable Mineral Resources. This was increased to 200m below
surface at the centre of A21 where the mineralisation widens
sufficiently to enable recovery by open pit mining.
It is expected Resolute will be able to provide a further
updated Mineral Resource model for Syama North during Q3 2023.
During the Quarter, the Company released its 31 December 2022
Ore Reserves and Mineral Resource Statement. Refer to ASX
announcement entitled "Ore Reserves and Mineral Resource Statement"
dated 8 March 2023. The Global Mineral Resources increased by
1.7Moz to 11.2Moz (net of depletion), with the Mineral Resource at
Syama North increasing to 3.2Moz. Ore Reserves increased to 4.6Moz
(net of depletion), with Ore Reserves at Syama North increasing to
854koz, with 10% (85koz) being oxide material.
Syama North prefeasibility study
The Syama North PFS is progressing and is forecast to be
completed and presented to the Company board for project stage gate
approval in the third quarter of 2023. The maiden reserves for the
Syama North Sulphide deposits were published early this year and
form the basis for the expanded Sulphide processing capacity.
A Scoping study was completed in the first quarter of 2023, in
which lead engineering consultancies investigated several low
capital options with various processing capacity rates, along with
the corresponding mine schedules. Initial mine schedules confirm
that Syama North can deliver the required ore to the modified
process plants over the eight years of the project life.
The Scoping study confirmed the robustness and viability of the
project, and the most feasible option was selected to progress the
PFS, which would see the overall Sulphide processing capacity
increase by more than 60% from a nominal 2.4Mtpa to a nominal
4.0Mtpa.
This increase in capacity will be achieved by making
modifications to the existing Oxide comminution circuit to enable
it to process Sulphide ore and includes modifications to the
roasting circuit and Calcine carbon-in-leach circuit to handle the
increased throughput as well as expansions to non-process
infrastructure. A key design feature of the modified comminution
circuit is it will be able to be switched to treat either Oxide
ore, or Sulphide ore, both at a throughput rate of 1.6Mtpa. The
circuit will be able to switch ore types within one shift. A new
flotation circuit will be added downstream from the modified
comminution circuit to produce concentrate when the circuit treats
Sulphide ore. The concentrate from this modified comminution
circuit and the concentrate from the existing Sulphide flotation
circuit will be blended and treated in the roasting circuit to
produce calcine, which will be leached in the existing calcine
carbon-in-leach circuit.
The new comminution and flotation circuits will enable overall
concentrate production to be higher than the roasting circuit can
process. Excess concentrate will be stored in ponds to be reclaimed
and treated while the comminution circuit is treating oxide ores.
This flexibility is a key focus of the project, which will allow
calcine production at full roaster throughput capacity, taking full
advantage of the enhancements made to the roaster in the 2021
shutdown, when the modified comminution circuit is switched to
treat Oxide ore, but also provides concentrate inventory to
continue calcine production if one of the flotation circuits were
not available.
When the modified comminution circuit is switched to treat Oxide
ore from Syama North or from future discoveries, the resulting
Oxide slurry will be leached in the existing Oxide carbon-in-leach
circuit.
Assessments have also been carried out to further increase the
roasting circuit throughput with lower capital options than those
initially anticipated. The addition of oxygen to manage the next
phase of expanded throughput capacity remains an option for the
roasting circuit.
The PFS is expected to build on the results from the Scoping
study to confirm a robust and executable project, with key
activities during the second quarter of 2023 including the
following:
-- geotechnical drilling within the open pit designs
-- advancing regulatory approvals
-- infill drilling to increase the Ore Reserves
-- further metallurgical test work and PFS-level engineering
-- investigation of opportunities to optimise capital and
maximise cash flow, preparation of operational and capital cost
estimates
-- engagement with the Local community to increase their understanding of the project
The delivery of the project is expected to be during the first
half of 2025, assuming the results of the PFS support the initial
Scoping outcomes.
Corporate
Quarterly Cash and Bullion Movements
(*Included in Operating Cash flows are $5.1 million of
royalties, $13.0 million of VAT and taxes, and movements in
Bullion.)
Chart 1: Quarterly Cash and Bullion Movements
The average realised gold price achieved for the Quarter was
$1,890/oz in line with the average spot price of $1,890/oz. Debt
repayments consisted of $25.0 million on the Term Loan Facility and
$5.0 million on the RCF (now fully undrawn). Working capital and
other comprises of an inflow of $2.4 million for creditors and
consumables movements offset by overdraft movements, government
dividends and other taxes for a net outflow of $0.9 million.
Balance sheet
Net debt decreased by $11.7 million to $19.9 million at 31 March
2023. Available liquidity of $155.8 million including cash of $54.0
million, bullion of $21.8 million, and undrawn RCF of $80.0
million. Total borrowings at 31 March 2023 were $95.7 million,
comprising $50.0 million on the Term Loan Facility and $35.6
million and $10.1 million on the overdraft facilities in Mali and
Senegal, respectively.
Hedging
At 31 March 2023, Resolute's forward sales commitments were:
June 2023 $1,900 55,000
---------------- ------- --------
September 2023 $1,919 60,000
---------------- ------- --------
December 2023 $1,926 59,000
---------------- ------- --------
March 2024 $1,940 42,500
---------------- ------- --------
Total $1,920 216,500
---------------- ------- --------
Table 5: Committed Hedging Forward Sales in US dollars
As well as the above, the Company has in place 12,000oz of zero
cost collars maturing in the March 2024 quarter. These comprise of
put options at an average strike price of $1,600/oz and call
options with an average strike price of $1,873/oz.
Resolute maintains a policy of discretionary hedging in
compliance with its funding obligations, requiring a minimum of 30%
of the next 12 months of forecast production to be hedged.
Reporting Calendar
25 May 2023 - Annual General Meeting
27 July 2023 - June Quarterly Activities Report
Investor and analyst conference call
Resolute will host a conference call for investors, analysts,
and media on Thursday, 27 April 2023, to discuss the Company's
Quarterly Activities Report for the period ending 31 March 2023.
This call will conclude with a question-and-answer session.
Conference Call (pre-registration required)
Conference Call: 4:30pm (AEST, Sydney) / 7:30am (BST,
London)
Pre-Registration Link:
https://s1.c-conf.com/diamondpass/10030292-hd94u6.html
Participants will receive a calendar invite with dial-in details
once the pre-registration process is complete.
The Conference Call will also be streamed live online at:
https://webcast.openbriefing.com/rsg-qtr-2023/
About Resolute
Resolute Mining (ASX/LSE: RSG) is an African gold miner,
developer, and explorer with more than 30 years of experience
across Australia and Africa. To date the Company has produced over
nine million ounces of gold. It currently operates the Syama Gold
Mine in Mali and the Mako Gold Mine in Senegal. Resolute's gold
production and cost guidance for 2023 is 350,000oz at an AISC of
$1,480/oz.
Through all its activities, sustainability is the core value at
Resolute. This means that protecting the environment, providing a
safe and productive working environment for employees, uplifting
host communities, and practicing good corporate governance are
non-negotiable priorities. Resolute's commitment to sustainability
and good corporate citizenship has been cemented through its
adoption of and adherence to the Responsible Gold Mining Principles
(RGMPs). This framework, which sets out clear expectations for
consumers, investors, and the gold supply chain as to what
constitutes responsible gold mining, is an initiative of the World
Gold Council of which Resolute has been a full member since 2017.
The Company is on track to reach full compliance with these RGMPs
in 2023.
Appendix
March 2023 Quarter Production and Costs (unaudited)
UG Lateral Development m 1,136 - 1,136 - 1,136
------ --------- ----------- ----------- ----------- -----------
UG Vertical Development m - - - - -
------ --------- ----------- ----------- ----------- -----------
Total UG Development m 1,136 - 1,136 - 1,136
------ --------- ----------- ----------- ----------- -----------
UG Ore Mined t 630,445 - 630,445 - 630,445
------ --------- ----------- ----------- ----------- -----------
UG Grade Mined g/t 2.86 - 2.86 - 2.86
------ --------- ----------- ----------- ----------- -----------
OP Operating Waste BCM - 1,943,569 1,943,569 1,830,086 3,773,655
------ --------- ----------- ----------- ----------- -----------
OP Ore Mined BCM - 233,629 233,629 275,502 509,131
------ --------- ----------- ----------- ----------- -----------
OP Grade Mined g/t - 1.83 1.83 1.99 1.91
------ --------- ----------- ----------- ----------- -----------
Total Ore Mined t 630,445 495,293 1,125,738 775,944 1,901,682
------ --------- ----------- ----------- ----------- -----------
Total Tonnes Processed t 549,072 421,203 970,275 501,272 1,471,547
------ --------- ----------- ----------- ----------- -----------
Grade Processed g/t 2.99 1.56 2.36 2.26 2.33
------ --------- ----------- ----------- ----------- -----------
Recovery % 79.1 84.9 81.6 92.3 85.2
------ --------- ----------- ----------- ----------- -----------
Gold Recovered oz 41,575 17,954 59,529 33,682 93,211
------ --------- ----------- ----------- ----------- -----------
Gold in Circuit Drawdown/(Addition) oz (433) (441) (874) (78) (952)
------ --------- ----------- ----------- ----------- -----------
Gold Poured oz 41,142 17,513 58,655 33,604 92,259
------ --------- ----------- ----------- ----------- -----------
Gold Bullion in Metal
Account Movement (Increase)/Decrease oz (916) (59) (975) (3,133) (4,108)
------ --------- ----------- ----------- ----------- -----------
Gold Sold oz 40,226 17,454 57,680 30,471 88,151
------ --------- ----------- ----------- ----------- -----------
Achieved Gold Price $/oz 1,890
------ --------- ----------- ----------- ----------- -----------
Mining $/oz 507 543 518 729 595
------ --------- ----------- ----------- ----------- -----------
Processing $/oz 511 587 534 396 484
------ --------- ----------- ----------- ----------- -----------
Site Administration $/oz 151 301 196 116 167
------ --------- ----------- ----------- ----------- -----------
Site Operating Costs $/oz 1,169 1,431 1,248 1,241 1,246
------ --------- ----------- ----------- ----------- -----------
Royalties $/oz 113 108 111 85 104
------ --------- ----------- ----------- ----------- -----------
By-Product Credits
+ Corp Admin $/oz (2) (2) (2) - 38
------ --------- ----------- ----------- ----------- -----------
Total Cash Operating
Costs $/oz 1,280 1,537 1,357 1,326 1,388
------ --------- ----------- ----------- ----------- -----------
Sustaining Capital
+ Others $/oz 94 207 127 5 83
------ --------- ----------- ----------- ----------- -----------
Total Cash Expenditure $/oz 1,374 1,744 1,484 1,331 1,471
------ --------- ----------- ----------- ----------- -----------
Inventory Adjustments $/oz (11) (111) (41) (56) (46)
------ --------- ----------- ----------- ----------- -----------
Asset Reclamation &
Remediation $/oz 26 26 26 32 28
------ --------- ----------- ----------- ----------- -----------
Total Non-Cash Adjustments $/oz 15 (85) (15) (24) (18)
------ --------- ----------- ----------- ----------- -----------
All-In Sustaining Cost
(AISC)
AISC is calculated
on gold poured $/oz 1,389 1,659 1,469 1,307 1,453
------ --------- ----------- ----------- ----------- -----------
Cautionary Statement about Forward-Looking Statements
This announcement contains certain "forward-looking statements"
including statements regarding our intent, belief, or current
expectations with respect to Resolute's business and operations,
market conditions, results of operations and financial condition,
and risk management practices. The words "likely", "expect", "aim",
"should", "could", "may", "anticipate", "predict", "believe",
"plan", "forecast" and other similar expressions are intended to
identify forward-looking statements. Indications of, and guidance
on, future earnings, anticipated production, life of mine and
financial position and performance are also forward-looking
statements. These forward-looking statements involve known and
unknown risks, uncertainties and other factors that may cause
Resolute's actual results, performance and achievements or industry
results to differ materially from any future results, performance
or achievements, or industry results, expressed or implied by these
forward-looking statements. Relevant factors may include (but are
not limited to) changes in commodity prices, foreign exchange
fluctuations and general economic conditions, increased costs and
demand for production inputs, the speculative nature of exploration
and project development, including the risks of obtaining necessary
licences and permits and diminishing quantities or grades of
reserves, political and social risks, changes to the regulatory
framework within which Resolute operates or may in the future
operate, environmental conditions including extreme weather
conditions, recruitment and retention of personnel, industrial
relations issues and litigation.
Forward-looking statements are based on Resolute's good faith
assumptions as to the financial, market, regulatory and other
relevant environments that will exist and affect Resolute's
business and operations in the future. Resolute does not give any
assurance that the assumptions will prove to be correct. There may
be other factors that could cause actual results or events not to
be as anticipated, and many events are beyond the reasonable
control of Resolute. Readers are cautioned not to place undue
reliance on forward-looking statements, particularly in the
significantly volatile and uncertain current economic climate.
Forward-looking statements in this document speak only at the date
of issue. Except as required by applicable laws or regulations,
Resolute does not undertake any obligation to publicly update or
revise any of the forward-looking statements or to advise of any
change in assumptions on which any such statement is based. Except
for statutory liability which cannot be excluded, each of Resolute,
its officers, employees and advisors expressly disclaim any
responsibility for the accuracy or completeness of the material
contained in these forward-looking statements and excludes all
liability whatsoever (including in negligence) for any loss or
damage which may be suffered by any person as a consequence of any
information in forward-looking statements or any error or
omission.
Authorised by Mr Terry Holohan, Managing Director and Chief
Executive Officer
Contact
Resolute Public Relations
James Virgo, GM Finance, and Jos Simson / Emily Moss, Tavistock
Investor Relations resolute@tavistock.co.uk
contact@rml.com.au +44 207 920 3150 / +44 7788
+61 8 9261 6100 554 035
Corporate Broker
Jennifer Lee, Berenberg
+44 20 3753 3040
This information is provided by RNS, the news service of the
London Stock Exchange. RNS is approved by the Financial Conduct
Authority to act as a Primary Information Provider in the United
Kingdom. Terms and conditions relating to the use and distribution
of this information may apply. For further information, please
contact rns@lseg.com or visit www.rns.com.
RNS may use your IP address to confirm compliance with the terms
and conditions, to analyse how you engage with the information
contained in this communication, and to share such analysis on an
anonymised basis with others as part of our commercial services.
For further information about how RNS and the London Stock Exchange
use the personal data you provide us, please see our Privacy
Policy.
END
MSCZZGZDFNFGFZG
(END) Dow Jones Newswires
April 27, 2023 02:00 ET (06:00 GMT)
Resolute Mining (LSE:RSG)
Gráfica de Acción Histórica
De Abr 2024 a May 2024
Resolute Mining (LSE:RSG)
Gráfica de Acción Histórica
De May 2023 a May 2024