Highbank Resources Ltd. (the "Company") (TSX VENTURE:HBK)(FRANKFURT:V7O) has
contracted Megatech Engineering Ltd. of Surrey, B.C. to supply the Company with
Conceptual Engineering Drawings for our Swamp Point Barge Load-out structure.
The drawings will form a part of the overall site plan and supplement the mine
plan information to include the shore abutment for the marine works to the
discharge into the barge loading area, including the required mooring structures
and barge winch articulation. Micon International Limited is reviewing and
compiling all the data and will be preparing the revised Notice of Work ("NoW")
application for submission shortly and should be able to finalize the submission
upon receipt of the Megatech documentation.


Warrant Extensions and Amendments 

The Company is announcing that the TSX Venture Exchange has agreed to extend the
terms of the following warrants:


Original Expiry - November 3, 2013 and November 29, 2013. These warrants were
originally issued on November 3, 2011 and November 29, 2011 and had an expiry of
two years. The Company has obtained regulatory approval to extend the expiry for
an additional one year along with amending the exercise price from $0.20 to
$0.15. 


Original Expiry - February 7, 2015, February 27, 2015 and April 25, 2015 - These
warrants were originally issued on February 7, 2013, February 27, 2013 and April
25, 2013 and had an expiry date of two years. The Company has obtained
regulatory approval to amend the exercise price as to $0.12. All other terms
remain the same. 


The Company will not be issuing new warrants unless a written request is
provided by the warrant holder to the Company. Warrant holders requiring the
issuance of a new warrant should do so in writing to the Company at Suite 600,
625 Howe Street, Vancouver, B.C. V6C 2T6. New warrants will only be issued upon
the warrant holder surrendering their original warrant.


If you have any questions, please feel free to contact the Company at (604)
683-6648.


On behalf of the Board of Directors of 

HIGHBANK RESOURCES LTD.

Gary Musil, CFO and Director 

Website re-launched:  

The company has now re-launched its Corporate website www.highbankresources.com
and www.highbankres.com. Aside from an updated user friendly presentation the
site now acts as a "Virtual Investor Centre" for a broad range of social media
platforms. Shareholders, potential investors, brokers, associated organizations
and interested parties now may 'follow" us on:


Facebook: https://www.facebook.com/HighbankResourcesLtd?ref=hl  

Twitter: https://twitter.com/HighbankHBK  

GooglePlus:
https://plus.google.com/b/115999208073439737262/115999208073439737262/posts 


YouTube: http://www.youtube.com/watch?v=iF-4vHNRRLw  

LinkedIn: http://www.linkedin.com/company/highbank-resources-ltd-?trk=top_nav_home 

Slideshare: http://www.slideshare.net/stockshaman/highbank-res

Please feel free to "Share", "Like", or "Follow" these Highbank Resources Ltd.
social media platforms within their respective mediums. 


Neither TSX Venture Exchange nor its Regulation Services Provider (as that term
is defined in the policies of the TSX Venture Exchange) accepts responsibility
for the adequacy or accuracy of this release. 


FOR FURTHER INFORMATION PLEASE CONTACT: 
Highbank Resources Ltd.
(604) 683-6648
(604) 683-1350 (FAX)
www.highbankresources.com

Highbank Resources (TSXV:HBK)
Gráfica de Acción Histórica
De Abr 2024 a May 2024 Haga Click aquí para más Gráficas Highbank Resources.
Highbank Resources (TSXV:HBK)
Gráfica de Acción Histórica
De May 2023 a May 2024 Haga Click aquí para más Gráficas Highbank Resources.