Mast
Energy Developments PLC
(Incorporated in England and
Wales)
(Registration Number:
12886458)
LEI :213800HFVHGJ9YGO9F71
Share code on the LSE:
MAST
ISIN: GB00BMBSCV12
('MED' or 'the Company')
Dated: 13 June 2024
Mast Energy Developments PLC
('MED' or 'the Company')
Business
Update
Mast Energy Developments PLC,
the UK-based multi-asset owner, developer and operator in the
rapidly growing flexible power market, is pleased to announce an
update regarding business operational matters.
Pyebridge
Further to the Company's previous
announcement dated 21 May 2024, the 2nd Phase work
programme regarding the refurbishment of the first of the Pyebridge
site's 3x Jenbacher gensets is progressing well and according to
plan and expected timeline. The latest status is that the new
replacement genset long-block has been received from the supplier
in Austria, the existing genset has been disconnected and craned
out of the site and transported to Cooper Östlund's workshop.
Cooper Östlund has completed the full rebuild of the genset, which
involved the replacement of the genset long-block and the
replacement and or refurbishment of all the various major and
critical engine components onto the new engine block. Following the
completion of the rebuild, the refurbished genset was transported
back to the Pyebridge site, and successfully craned back into the
facility. The final remaining step in the process is the
recommissioning of the new genset, which is currently underway. It
is expected that the first genset's overhaul work will be fully
completed and the genset to start commercial operational running
and revenue generation around end of June 2024, in line with the
expected timeline.
To give more insight into the
work-stream involved in overhauling the genset, including photos of
key stages during the process, please visit the MED website,
"Pyebridge Overhaul Story" webpage at https://med.energy/?page_id=4466.
As this process was completed
seamlessly within the planned timeline and budget for the first
genset, we expect the overhaul of the site's other two gensets to
proceed similarly and thus meet our target to have all three
gensets overhauled and operating optimally in due course, as
previously announced.
In the meantime, the Pyebridge
site's other two gensets remain operational and will continue to
generate revenue via its PPA with Statkraft. Additionally,
Pyebridge will also keep receiving its current Capacity Market
contract's associated annual gross profit margin income of
c. £308,000 from the government, as previously
announced.
Additionally, as previously
announced the Pyebridge site has secured further Capacity Market
contracts to ensure minimum annual gross profit margin income as
follows:
·
T-1 2024/2025 CM contract -
c. £183,000 gross profit margin income;
·
T-4 2026/2027 CM contract -
c. £312,000 gross profit margin income; and
·
T-4 2027/2028 CM contract -
c. £322,000 gross profit margin income.
MED expects to bid for and secure an
additional T-1 Capacity Market contract for the 2025/2026 delivery
year in the next upcoming Capacity Market auction, thereby ensuring
uninterrupted minimum guaranteed income until 2028. The Site's
existing Capacity Market contracts are all fixed one-year
contracts. MED expects to apply for the maximum 15-year term and
capacity T-4 Capacity Market contract in due course.
The Pyebridge site's Capacity Market
contracts' gross profit margin income payments are in addition to
its electricity generation trading revenue generation via its PPA
with Statkraft. The plan and intention is to add a minimum
guaranteed gross profit margin income floor component to its PPA
with Statkraft (the "PPA Floor"). The PPA Floor value is currently
expected to be at least around £50/kW/annum, subject to
certain usual conditions such as assessment and agreement by
Statkraft, which would equate to a minimum annual gross profit
margin income of £405,000 in addition to the site's Capacity
Market contracts' income payments.
Both the above referred longer-term
Capacity Market contract and the PPA Floor are expected to be
implemented once the Pyebridge site's planned overhaul work
programme as referred to above has been completed, in order to
provide further enhanced and longer term minimum guaranteed gross
profit margin income to the site.
Pieter Krügel, MED CEO, commented: "We are pleased that
the overhaul of the first genset at Pyebridge is progressing
according to plan, timeline and budget, and near complete. We are
looking forward to completing the overhaul work within the expected
timeline, and once done, it will increase the Pyebridge site's
income generation substantially. The successful completion of the
overhaul of the first genset will also establish a proven blueprint
to move forward with the overhaul of the site's remaining two
gensets, as well as possible application on MED's other sites in
due course in order to reduce capex costs.
"We are looking forward to updating the market with further
progress across the board in due course."
ENDS
This announcement contains inside information for the purposes
of the UK version of the Market Abuse Regulation (EU No. 596/2014)
as it forms part of United Kingdom domestic law by virtue of the
European Union (Withdrawal) Act 2018 ('UK MAR'). Upon the
publication of this announcement, this inside information is now
considered to be in the public domain.
For further information please
visit www.med.energy or contact:
Pieter Krügel
|
info@med.energy
|
Mast Energy
Developments PLC
|
CEO
|
Jon Belliss
|
+44 (0)20 7399 9425
|
Novum Securities
|
Corporate Broker
|