Endeavour Silver Corp.
(“Endeavour” or the
“Company”) (NYSE: EXK; TSX: EDR) provides
a Q4 2023 construction progress update for its Terronera Project in
Jalisco state, Mexico. A photo gallery presentation accompanies
this news release and can be found
here or on the
Company website at
Terronera Project Progress
Photos. All dollar ($) references in this news release are
United States dollars.
The Terronera project has made significant
construction progress to date. Concrete work is well advanced, and
erection of structural steel for the grinding and flotation areas
has started. In early 2024, the Company provided an Updated Initial
Capital Cost (“2024 Updated Scenario”), which increased the project
budget by $41 million to $271 million. This increase was primarily
due to a stronger Mexican Peso, ongoing inflation and availability
of bulk materials such as steel, piping and electrical supplies
(see news release dated January 24, 2024). As of December 31, 2023,
approximately $1201 million had been invested in direct project
expenditures, with project commitments totaling $1711, 2 million or
63% of the updated budget. With an experienced and seasoned team
leading the project, the Company anticipates the schedule will
remain in line with previous guidance, with initial production
anticipated to start in the fourth quarter of 2024.
“Throughout 2023, we’ve achieved several major
milestones across multiple fronts,” commented Don Gray, Chief
Operating Officer. “We’ve concentrated our efforts on completing
key items including earthworks for our Upper Mill Platform,
procurement of equipment, and advances in plant concrete. Our
underground mine development continues to advance rapidly as we
look to start ore development sometime in Q2 2024. We’re extremely
satisfied with Terronera’s progress thus far and remain committed
to successfully completing and operating Endeavour’s next core
asset.
Q4 2023 Construction and Development
Highlights
As of December 31, 2023, site works and
activities included:
- Safety – Our strong onsite safety
focus continues: The Project finished 2023 with 172 days totaling
over 600,000 manhours with no lost-time accidents.
- Progress – Overall project progress
reached 43% completion including a 3% reduction due to the adjusted
weighting related to the 2024 Updated Scenario. The project remains
on track for commissioning in Q4 2024.
- Engineering – Detail engineering
for the mill and infrastructure began transitioning to construction
support towards the end of 2023. Excavation designs for the Lower
Platform and detail design for Tailing Storage Facility (“TSF”)
have been advanced using supplemental geotechnical investigation
results obtained in Q4 2023.
- Mine Development – Over 2,200
metres of underground development were completed in 2023. The
in-house mining team has been successfully transitioning from using
contracted to direct-hire labor with greater development
efficiencies. Development was focused on Portal 1, 2 and 4 declines
for accessing ore and setting up the main ventilation circuit and
haulage way; the Portal 4 incline broke through to surface and
preparations are underway to complete the portal structure in Q1
2024.
- Plant Site – Surface mill and
infrastructure construction is now almost 50% complete; concrete
works were well advanced to allow the start of vertical
construction in early Q1 2024. The electromechanical contract was
awarded and mobilization commenced.
- Primary Crusher – Concrete has been
completed for the jaw crusher foundation and the perimeter walls,
including backfill and compaction.
- Course Ore Stockpile and Reclaim
Tunnel – The Coarse Ore Stockpile support walls have been completed
along with the roof including the feeder chute imbeds. For the
reclaim tunnel, concrete has been completed for two major roof
sections with two sections remaining.
- Grinding – The concrete of the
grinding area is nearly complete and being prepared for release to
the general contractor to begin structural steel and mechanical
installations.
- Flotation – The concrete of the
flotation cell pedestals is nearly complete and being prepared for
release to the general contractor to begin structural steel and
mechanical installations.
- Thickener – The thickener tank
support pedestals were completed and was backfill initiated.
Concrete work has been started for the raw water, process water,
thickener surge, and concentrate storage tank pedestals and
foundations.
- Lower Facilities Platform and TSF –
Access road construction has commenced from the Lower Platform and
TSF area to the Upper Mill Platform.
- Procurement – Focused on procuring
bulk materials, including structural steel, piping, and electrical
cable following a comprehensive scheduling for delivery that tracks
construction requirements.
- Onsite Personnel – The workforce
had increased to 126 employees and 400 contractor workers.
- Community Relations – Supporting the local municipality has
continued to be a major focus with sponsoring cultural and
community activities in the area.
- Environmental – Environmental and social assessment initiatives
continue according to schedule as outlined under the Equator
Principal requirements for project loan financing.
2024 Outlook and Planning
Endeavour remains focused on advancing the
Terronera Project for initial production in Q4 2024, with a
comprehensive schedule and plan under the 2024 Updated
Scenario.
For Q1 2024, surface construction will focus on
completing concrete work to allow structural steel erection,
mechanical installations and initial electrical work for the
crushing, coarse-ore stockpile, grinding, flotation and tailing
thickener areas. Early in Q2, excavation is anticipated to be
complete for the Lower Platform, which includes facilities such as
the LNG and power generation areas and the concentrate and tailing
filtration areas. For Q2 and Q3, work is planned for all mill and
infrastructure areas with mechanical completion and commissioning
activities planned in Q4.
For the mine, development in Portal 1, 2 and 4
declines will continue with first ore development anticipated in
Q2. Initial long-hole mining is planned for Q3 and cut-and-fill
mining is planned with ore being stockpiled for mill ramp up.
Development activities at La Luz are expected to begin in Q3 with
portal construction and ramp advance to ore access anticipated in
Q4. The critical path remains the TSF construction and advancing
underground mine, where development efficiencies have been steadily
increasing.
The Company is well-positioned to satisfy the
Terronera project financing requirements and expects the first draw
under the $120 million project loan debt facility in Q1 2024.
Dedicated Project Website
The Company has launched a dedicated project
website, accessible at www.terronera.com, serving as a virtual hub
for the local community, key stakeholders, and other interested
parties to stay informed and engaged with the ongoing progress of
the Terronera Project. The Company invites all stakeholders to
explore the latest updates, learn about our commitment to
environmental stewardship and discover the positive impacts this
venture will bring to local communities.
About the Terronera Project
The Terronera project is a high-grade
silver-gold project being developed in the San Sebastian mining
district in Jalisco state, Mexico. It is located within the Sierra
Madre volcanic belt, which hosts most of Mexico’s gold and silver
deposits. It is a low-sulphidation epithermal vein system that will
be mined using a combination of long hole and cut and fill
techniques. The underground mine consists of two deposits,
Terronera and La Luz, which will feed a centralized 2,000 tonne per
day process plant. Based on the Feasibility Study, Terronera is
expected to produce 4 million ounces of silver and 38,000 ounces of
gold annually over its 10-year life.
For more information about the project and
details of the Feasibility Study, the technical report is entitled
“NI 43-101 Technical Report on the Feasibility Study of the
Terronera Project, Jalisco State, Mexico” dated October 21, 2021,
with an effective date of September 9, 2021, and it is available on
the company website or under the Company’s name on SEDAR at
www.sedar.com.
About Endeavour Silver –
Endeavour is a mid-tier precious metals mining company that
operates two high-grade underground silver-gold mines in Mexico.
Endeavour is advancing construction of the Terronera Project and
exploring its portfolio of exploration projects in Mexico, Chile
and the United States to facilitate its goal to become a premier
senior silver producer. Our philosophy of corporate social
integrity creates value for all stakeholders.
Contact InformationGalina Meleger, VP, Investor
RelationsEmail: gmeleger@edrsilver.comWebsite:
www.edrsilver.com
Follow Endeavour Silver on Facebook, X,
Instagram and LinkedIn.
Footnote:
- Financial
figures are based on a preliminary estimate. Final audited figures
will be released with the 2023 financial statements on March 11,
2024.
- Project
commitments are inclusive of total project expenditures.
Cautionary Note Regarding
Forward-Looking Statements
This news release contains “forward-looking
statements” within the meaning of the United States private
securities litigation reform act of 1995 and “forward-looking
information” within the meaning of applicable Canadian securities
legislation. Such forward-looking statements and information herein
include but are not limited to statements regarding the development
and financing of the Terronera Project including: capital cost
estimates, anticipated timing of the project construction;
anticipated timing of drawdown under the project loan debt
facility, Terronera’s forecasted operations, costs and
expenditures, and the timing and results of various related
activities. The Company does not intend to and does not assume any
obligation to update such forward-looking statements or
information, other than as required by applicable law.
Forward-looking statements or information
involve known and unknown risks, uncertainties and other factors
that may cause the actual results, level of activity, production
levels, performance or achievements of Endeavour and its operations
to be materially different from those expressed or implied by such
statements. Such factors include but are not limited changes in
production and costs guidance; the ongoing effects of inflation and
supply chain issues on mine economics; national and local
governments, legislation, taxation, controls, regulations and
political or economic developments in Canada, Chile, the U.S.A and
Mexico; financial risks due to precious metals prices; operating or
technical difficulties in mineral exploration, development and
mining activities; risks and hazards of mineral exploration,
development and mining; the speculative nature of mineral
exploration and development; risks in obtaining necessary licenses
and permits; satisfaction of conditions precedent to drawdown under
the project loan debt facility; the ongoing effects of inflation
and supply chain issues on the Terronera Project economics;
fluctuations in the prices of silver and gold, fluctuations in the
currency markets (particularly the Mexican peso, Chilean peso,
Canadian dollar and U.S. dollar); and challenges to the Company’s
title to properties; as well as those factors described in the
section “risk factors” contained in the Company’s most recent form
40F/Annual Information Form filed with the S.E.C. and Canadian
securities regulatory authorities.
Forward-looking statements are based on
assumptions management believes to be reasonable, including but not
limited to: the continued operation of the Company’s mining
operations, no material adverse change in the market price of
commodities, forecasted Terronera mine economics as of 2024, mining
operations will operate and the mining products will be completed
in accordance with management’s expectations and achieve their
stated production outcomes, and such other assumptions and factors
as set out herein. Although the Company has attempted to identify
important factors that could cause actual results to differ
materially from those contained in forward-looking statements or
information, there may be other factors that cause results to be
materially different from those anticipated, described, estimated,
assessed or intended. There can be no assurance that any
forward-looking statements or information will prove to be accurate
as actual results and future events could differ materially from
those anticipated in such statements or information. Accordingly,
readers should not place undue reliance on forward-looking
statements or information.
Endeavour Silver (NYSE:EXK)
Gráfica de Acción Histórica
De Oct 2024 a Nov 2024
Endeavour Silver (NYSE:EXK)
Gráfica de Acción Histórica
De Nov 2023 a Nov 2024