Mast
Energy Developments PLC
(Incorporated in England and
Wales)
(Registration Number:
12886458)
LEI :213800HFVHGJ9YGO9F71
Share code on the LSE:
MAST
ISIN: GB00BMBSCV12
('MED' or 'the Company')
Dated: 11 April 2024
Mast Energy Developments PLC
('MED' or 'the Company')
Business
Update
Mast Energy Developments PLC,
the UK-based multi-asset owner, developer and operator in the
rapidly growing flexible power market, is pleased to announce an
update regarding business operational matters.
HIGHLIGHTS
·
The initial first phase work programme at MED's
Pyebridge 9MW flexible power generation asset ("Pyebridge")
successfully completed ahead of schedule, with the site now
officially back into operation.
·
Initial pre-construction work completed at MED's
7.5MW Hindlip Lane flexible power generation project ("Hindlip"),
and Certificate of Lawful Commencement granted.
FURTHER INFORMATION
Pyebridge
Further to the Company's previous
announcement dated 28 February 2024, the MED management team
successfully completed the initial work programme ahead of schedule
at its Pyebridge 9MW flexible power generation asset ("Pyebridge"),
with the site now officially back into operation.
Resultingly, MED was able to
schedule and perform the minimum 3x separate generation runs ahead
of schedule to meet its Satisfactory Performance Days ("SPD")
requirements that are due by the end of April 2024 under its
existing T-1 Capacity Market contract (the "CM Contract"). It is
expected that Pyebridge will pass its next SPD test, and retain the
CM Contract's associated annual gross profit margin income of c.
£308,000 which is paid and received monthly in arrears.
Additionally, as previously
announced the Pyebridge site has secured further Capacity Market
contracts to ensure minimum annual gross profit margin income as
follows:
·
T-1 2024/2025 CM contract - c. £183,000 gross
profit margin income;
·
T-4 2026/2027 CM contract - c. £312,000 gross
profit margin income; and
·
T-4 2027/2028 CM contract - c. £322,000 gross
profit margin income.
MED expects to bid for and secure an
additional T-1 Capacity Market contract for the 2025/2026 delivery
year in the next upcoming Capacity Market auction, thereby ensuring
uninterrupted guaranteed income until 2028. The Site's existing
Capacity Market contracts are all fixed one-year contracts. MED
expects to apply for the maximum 15-year term and capacity T-4
Capacity Market contract in due course.
The Pyebridge site's Capacity Market
contracts' gross profit margin income payments are in addition to
its electricity generation trading revenue generation via its PPA
with Statkraft. The plan and intention is to add a minimum
guaranteed gross profit margin income floor component to its PPA
with Statkraft (the "PPA Floor"). The PPA Floor value is currently
expected to be at around £50/kW/annum, subject to certain usual
conditions such as assessment and agreement by Statkraft, which
would equate to an additional minimum annual gross profit margin
income of £405,000.
Both the above referred longer-term
Capacity Market contract and the PPA Floor are expected to be
implemented once the Pyebridge site's planned overhaul work
programme as referred to below has been completed, in order to
provide further enhanced and longer term minimum guaranteed gross
profit margin income to the site.
Further, following the successful
completion of the first phase of the work programme, the plan and
intention is that the next larger second phase work programme (the
"2nd Phase") will be initiated shortly. The
2nd Phase will be performed in separate consecutive
tranches on each of the Pyebridge site's 3x gensets, and is
expected to take around 6 to 8 weeks per genset.
The cost of the 2nd Phase
will be funded under the new funding agreement as recently
announced. The 2nd Phase will involve the
following main improvements to the site and gensets, in order to
get the site up to its full efficiency, revenue generation and
profitability potential:
·
Complete long-block and major parts replacements
and full overhauls for each of the existing 3 x Jenbacher J620
engines.
·
Replacement engine long-blocks will feature
upgraded internal deflagration protection technology, which will
significantly reduce the risk of potential damage due to engine
backfires.
·
The overhauls will ensure optimal overall
generation efficiency, reduced operations- and maintenance costs
and downtime, and optimal overall availability.
Hindlip and MED's other existing sites
Initial pre-construction work at
Hindlip was successfully completed to satisfy planning consent
requirements. As a result, the site's Certificate of Lawful
Commencement has been granted.
The following MED sites, Hindlip
(7.5MW), Bordesley (4.5MW) and Rochdale (4.5MW) are each
construction-ready, with all required key cornerstones of a
flexible generation site in place and in good standing, most
notably fully specified EPC and O&M offers, planning consent,
gas connection offer, grid connection offer and construction
management plan. Subject to capex funding, these sites will
immediately continue with the construction phase with an expected
timeline to commercial operations date of around 12 months from
receipt of funding, to go into production and revenue
generation.
Project Capex Funding
As stated above, most of MED's sites
under development are either ready for construction, or in
early-stage construction, subject to securing project capex
funding. In order to address this key next step in these projects'
development lifecycle to get each project into production as
quickly as possible, MED is currently in discussions with various
potential debt and equity funders, including banking institutions
that are interested to provide the necessary capex
funding.
Pieter Krügel, MED CEO, commented: "We are pleased to
have successfully completed the first phase work programme at
Pyebridge, and that the site is now back into operation. We are
looking forward to initiating the next 2nd Phase work
programme shortly, which when successfully completed will see the
site operating and generating income at its full expected
efficiency, availability and profitability potential. We will
update the market with progress in due course."
ENDS
This announcement contains inside information for the purposes
of the UK version of the Market Abuse Regulation (EU No. 596/2014)
as it forms part of United Kingdom domestic law by virtue of the
European Union (Withdrawal) Act 2018 ('UK MAR'). Upon the
publication of this announcement, this inside information is now
considered to be in the public domain.
For further information please
visit www.med.energy or contact:
Pieter Krügel
|
info@med.energy
|
Mast Energy
Developments PLC
|
CEO
|
Jon Belliss
|
+44 (0)20 7399 9425
|
Novum Securities
|
Corporate Broker
|