MONTREAL, Oct. 14, 2021 /PRNewswire/ - Turquoise Hill
Resources Ltd. ("Turquoise Hill" or the "Company") today announced
third quarter 2021 production for Oyu Tolgoi LLC ("Oyu Tolgoi" or
"OT") and provided an update on the Oyu Tolgoi mine.
Q3 2021 production highlights
In Q3 2021, both copper and gold production from the open pit
were higher vs Q3 2020 due to higher copper and gold head grade ore
from Phase 4B:
- Copper production of 41,935 tonnes, an increase of 16% vs Q3
2020 and an increase of 14% vs Q2 2021
- Gold production of 130,799 ounces, an increase of 256% vs Q3
2020 and an increase of 16% vs Q2 2021
- Copper and gold production guidance for 2021 remains within the
ranges of 150,000 to 180,000 tonnes and 400,000 to 480,000 ounces
respectively
Mill throughput of 9.34 million tonnes in Q3 2021 was in line
with Q2 2021 and 7% lower than Q3 2020. Processing of harder ore as
well as lower SAG mill availability, due to maintenance, impacted
Q3 2021 mill throughput.
Oyu Tolgoi has advised that the full impacts of the previously
disclosed open-pit geotechnical events as well as the on-going
impacts of on-site COVID-19 restrictions have resulted in delayed
waste movement, which is currently forecast to result in deferral
of some open-pit metal to beyond 2024. While opportunities to
reduce the impact of this forecast metal deferral are under
consideration, related work is not expected to be completed until
Q1 2022.
Underground Development
All technical undercut readiness activities have been completed
or are on-track for completion, and Oyu Tolgoi has been ready from
a technical perspective to commence the undercut since July 2021. However, undercut commencement remains
delayed and is pending resolution of certain non-technical undercut
criteria, including the support of all OT Board directors to
increase the underground development capital and to commence
discussions with the project finance lenders, obtaining
outstanding, required regulatory approvals and to agree on a
pathway to meet OT's long-term power requirements.
During Q3 2021, underground development progress continued to be
significantly impacted by the COVID-19 constraints on-site and in
Mongolia, including restrictions
on movement of both domestic and international expertise. Despite
these on-going constraints, breakthrough of the conveyor decline
was achieved in August 2021, and
breakthrough of the service decline is forecast by the end of
October 2021. Material Handling
System 1 ("MHS1") is almost complete; its construction is currently
scheduled for completion by the end of October 2021, and its commissioning is scheduled
for completion by the end of January
2022. Construction of the first on-footprint truck chute is
well advanced and currently forecast to be completed by February
2022. Completion of both MHS1 and the first on-footprint
truck chute is broadly in-line with the Definitive Estimate, which
is an excellent result given the challenging circumstances.
Nevertheless, given the cumulative and on-going impacts of
COVID-19, continued delayed commitments resulting from the
Definitive Estimate not yet having received the support of all
directors of the Oyu Tolgoi Board, as well as the outstanding
unresolved non-technical undercut issues, the Company now expects
sustainable production for Panel 0 to be delayed until at least
January 2023.
Progress on Shafts 3 and 4 has been impacted by quarantine
requirements and international travel restrictions related to
COVID-19, and no significant development progress on these shafts
was made during Q3 2021. Consequently, Oyu Tolgoi has advised that
a 9-month delay on Shafts 3 and 4 is currently forecast which, in
combination with the reduced underground development progress, will
result in delays to the start of Panel 2. Sinking of Shaft 4
recommenced in mid-October, and preparatory work for Shaft 3
sinking is continuing.
Study work continues on Panels 1 and 2 with future mine design
refinements expected to reflect the learnings from Panel 0.
COVID-19
Mongolia continued to
experience a significant number of cases of COVID-19 during Q3
2021, which continued to limit the ability of Oyu Tolgoi to
maintain normal roster changes for its workers. While Oyu Tolgoi
did experience an improvement to on-site personnel numbers vs Q2
2021, average workforce numbers remained below 50% of planned
requirements during Q3 2021.
COVID-19 restrictions have adversely impacted both open pit
operations and underground development, which, through the end of
Q3 2021, have resulted in a cumulative increase of US$140 million to the estimate of underground
development capital included in the Definitive Estimate. This
increase includes the currently known, incremental, time-related
costs of COVID-19 restrictions; however, it does not include any
impacts arising from associated schedule delays or delayed
commitments caused by the Definitive Estimate not yet having
received the support of all the directors of the OT Board, as these
are still under assessment. The Company will continue to monitor
these costs and will update the market as appropriate.
All workers at Oyu Tolgoi site have had two doses of vaccine,
and a third dose program is well advanced. Improvements in
quarantine protocols both on-site and off-site have resulted in
improvements in restrictions, which resulted in higher workforce
numbers in September 2021 while still
minimising the spread of COVID-19. A return to normal workforce
levels is expected by the end of 2021, and Oyu Tolgoi will continue
to cooperate with the Mongolian authorities to implement and
maintain control measures to protect the health and well-being of
its workers as well as the local community.
Funding
Oyu Tolgoi has provided the Company with preliminary information
that the underground delays and open-pit metal deferrals discussed
above have caused an increase in the Company's base case estimated
incremental funding requirement to US$3.6
billion. The Company continues to review this preliminary
information received from Oyu Tolgoi. While OT has indicated
further open-pit mine plan optimization opportunities are under
consideration, which could have a favourable impact on the
Company's estimated incremental funding requirement, related work
is not expected to be completed until Q1 2022.
Negotiations with Government of Mongolia
In September 2021, the updated
Resources and Reserves (RR19) was approved by the Minerals Council
of Mongolia, and the updated
Feasibility Study (OTFS20) will be able to be submitted for
assessment once the RR19 registration process progresses
further.
Turquoise Hill continues to engage Rio Tinto and various
Mongolian governmental bodies to resolve the remaining outstanding
non-technical undercut criteria, and the Company remains committed
to moving the project forward and ensuring long-term and mutually
beneficial solutions to the issues under discussion. Nevertheless,
delayed resolution of outstanding issues, as well as the slowing of
discussions as a result of the COVID-19 situation in Mongolia, will delay the Company's expected
timing for initiation of the undercut. Some contractual commitments
for future works on items such as Material Handling System 2 and
the Concentrator upgrade have experienced delays, as entering into
these commitments is currently pending approval of the Definitive
Estimate and related budget uplift by the Oyu Tolgoi Board. Any
significant further delay to the initiation of the undercut would
result in further, unfavorable impacts to the underground project
schedule, including the timing of sustainable production for Panel
0, the timing to commence Panel 2 and the timing and quantum of
underground capital expenditure, all of which would materially,
adversely impact the timing of expected cash flows from the Oyu
Tolgoi underground project thereby further increasing the quantum
of Turquoise Hill's estimated incremental funding requirement and
would also likely in turn adversely affect the ability of the
Company and Oyu Tolgoi to obtain additional funding or re-profile
existing debt as contemplated by and/or within the timeframe set
out in the Heads of Agreement entered into between the Company and
Rio Tinto in April 2021.
Turquoise Hill remains committed to seeking resolution of
outstanding issues and remains mobilized in Mongolia to continue discussions with the
Government to progress timely resolution for the benefit of all
stakeholders. The Company will continue to monitor the situation,
assess any impact of any related delays and update the market as
appropriate.
Force Majeure
Oyu Tolgoi concentrate shipment volumes to customers improved
during Q3 2021; however, above target inventory levels remained at
the end of Q3 2021 as a result of the COVID-19 related Mongolia / Chinese border restrictions that
resulted in force majeure being declared from March 30, 2021. Shipments to Chinese customers
recommenced on April 15, 2021, and
Oyu Tolgoi continues to work closely with Mongolian and Chinese
authorities to manage any supply chain disruptions. The force
majeure will remain in place until there are sufficiently sustained
volumes of convoys crossing the border to ensure Oyu Tolgoi's
ability to meet its on-going commitments to customers and to return
on-site concentrate inventory to target levels.
Oyu Tolgoi
Production Data
|
|
|
|
|
|
|
|
|
All data
represents full production and sales on a 100% basis
|
|
|
|
|
|
|
|
|
|
|
3Q
|
4Q
|
1Q
|
2Q
|
3Q
|
9 months
|
9
months
|
Full Year
|
|
2020
|
2020
|
2021
|
2021
|
2021
|
2021
|
2020
|
2020
|
|
|
|
|
|
|
|
|
|
Open pit material
mined ('000 tonnes)
|
23,979
|
23,663
|
22,588
|
15,829
|
22,588
|
61,005
|
74,032
|
97,694
|
Ore treated ('000
tonnes)
|
10,072
|
9,594
|
9,813
|
9,401
|
9,336
|
28,550
|
30,606
|
40,200
|
Average mill head
grades:
|
|
|
|
|
|
|
|
|
Copper (%)
|
0.45
|
0.50
|
0.56
|
0.47
|
0.53
|
0.52
|
0.45
|
0.46
|
Gold (g/t)
|
0.21
|
0.41
|
0.68
|
0.50
|
0.63
|
0.60
|
0.18
|
0.24
|
Silver
(g/t)
|
1.22
|
1.16
|
1.29
|
1.19
|
1.29
|
1.26
|
1.19
|
1.18
|
Concentrates produced
('000 tonnes)
|
168.5
|
190.2
|
201.9
|
173.2
|
191.9
|
567.0
|
502.9
|
693.1
|
Average concentrate
grade (% Cu)
|
21.5
|
21.9
|
22.5
|
21.2
|
21.9
|
21.9
|
21.5
|
21.6
|
Production of metals
in concentrates:
|
|
|
|
|
|
|
|
|
Copper ('000
tonnes)
|
36.3
|
41.6
|
45.4
|
36.7
|
41.9
|
124.1
|
108.0
|
149.6
|
Gold ('000
ounces)
|
37
|
88
|
146
|
113
|
131
|
390
|
94
|
182
|
Silver ('000
ounces)
|
219
|
231
|
255
|
235
|
249
|
739
|
645
|
876
|
Concentrate sold
('000 tonnes)
|
167.9
|
181.5
|
186.3
|
92.6
|
224.4
|
503.3
|
488.1
|
669.6
|
Sales of metals in
concentrates:
|
|
|
|
|
|
|
|
|
Copper ('000
tonnes)
|
34.4
|
37.9
|
39.0
|
19.6
|
46.4
|
105.0
|
99.9
|
137.8
|
Gold ('000
ounces)
|
34
|
66
|
111
|
73
|
149
|
333
|
84
|
150
|
Silver ('000
ounces)
|
201
|
194
|
207
|
106
|
278
|
591
|
566
|
760
|
Metal recovery
(%)
|
|
|
|
|
|
|
|
|
Copper
|
78.9
|
85.9
|
86.3
|
79.7
|
83.9
|
83.6
|
77.4
|
79.6
|
Gold
|
53.7
|
68.8
|
72.2
|
69.3
|
68.7
|
70.3
|
51.0
|
58.6
|
Silver
|
54.6
|
64.3
|
65.3
|
62.5
|
64.1
|
64.0
|
54.0
|
56.4
|
Follow us on Twitter@TurquoiseHillRe
Forward-looking statements and forward-looking
information
Certain statements made herein, including statements relating to
matters that are not historical facts and statements of the
Company's beliefs, intentions and expectations about developments,
results and events which will or may occur in the future,
constitute "forward-looking information" within the meaning of
applicable Canadian securities legislation and "forward-looking
statements" within the meaning of the "safe harbor" provisions of
the United States Private Securities Litigation Reform Act of 1995.
Forward-looking statements and information relate to future events
or future performance, reflect current expectations or beliefs
regarding future events and are typically identified by words such
as "anticipate", "could", "should", "expect", "seek", "may",
"intend", "likely", "plan", "estimate", "will", "believe" and
similar expressions suggesting future outcomes or statements
regarding an outlook. These include, but are not limited to,
statements and information regarding: discussions with, and the
nature of the Company's relationship and interaction with, the
Government of Mongolia on the
continued operation and development of Oyu Tolgoi, including with
respect to the Definitive Estimate and the potential termination,
amendment or replacement of the Investment Agreement ("IA") or the
Oyu Tolgoi Mine Development and Financing Plan ("UDP") as well as
the willingness of the Government of Mongolia to further engage in meaningful
discussions with the Company, Rio Tinto and Oyu Tolgoi; the
willingness and ability of the parties to the IA or the UDP to
amend or replace the UDP; the approval or non-approval by the
OT Board of funding for a full budget uplift and the likely
consequences on the timing and overall economic value of the Oyu
Tolgoi project, including significant delays to first sustainable
production; the implementation and successful execution of the
funding plan that is the subject of the Heads of Agreement between
the Company and Rio Tinto entered into in April 2021 ( the "HoA") and the amount of any
additional future funding gap to complete the Oyu Tolgoi project
and the amount and potential sources of additional funding required
therefor, all as contemplated by the HoA, as well as potential
delays in the ability of the Company and Oyu Tolgoi to proceed with
the funding elements contemplated by the HoA as a result of delays
in approving or non-approval of a full budget uplift by the OT
Board; the expectations set out in the 2020 Oyu Tolgoi Technical
Report ("OTTR20"); the timing and ultimate resolution of certain
non-technical undercut criteria; the timing and amount of future
production and potential production delays; statements in respect
of the impacts of any delays on achieving first commercial
production the Company's cash flows; expected copper and gold
grades; the merits of the class action complaints filed against the
Company in October 2020 and
January 2021, respectively; the
likelihood that the Company will be added as a party to the
international tax arbitration brought by Oyu Tolgoi against the
Government of Mongolia and the
merits of its defence and counterclaim; liquidity, funding sources
and funding requirements; the amount of any funding gap to complete
the Oyu Tolgoi project; the amount and potential sources of
additional funding; the Company's ability to re-profile its
existing project debt in line with current cash flow projections;
the amount by which a successful re-profiling of the Company's
existing debt would reduce the Company's currently projected
funding requirements; the Company's ability to raise supplemental
senior debt; the timing of studies, announcements and analyses;
status of underground development; the causes of the increase in
costs and schedule extension of the underground
development; the mine design for Panel 0 of Hugo North Lift 1
and the related cost and production schedule implications; the
re-design studies for Panels 1 and 2 of Hugo North Lift 1 and the
possible outcomes, content and timing thereof; expectations
regarding the possible recovery of ore in the two structural
pillars, to the north and south of Panel 0; the possible
progression of a state-owned power plant ("SOPP") and related
amendments to the Power Source Framework Agreement ("PSFA") as well
as power purchase agreements and extensions to; the timing of
construction and commissioning of the potential SOPP; sources of
interim power; the continuing impact of COVID-19, including any
restrictions imposed by health or governmental authorities relating
thereto on the Company's business, operations and financial
condition, as well as delays and the development cost impacts of
delays caused by the COVID-19 pandemic; capital and operating cost
estimates; mill and concentrator throughput; the outcome of formal
international arbitration proceedings; anticipated business
activities, planned expenditures, corporate strategies, and other
statements that are not historical facts.
Forward-looking statements and information are made based upon
certain assumptions and other important factors that, if untrue,
could cause the actual results, performance or achievements of the
Company to be materially different from future results, performance
or achievements expressed or implied by such statements or
information. There can be no assurance that such statements or
information will prove to be accurate. Such statements and
information are based on numerous assumptions regarding present and
future business strategies, local and global economic conditions,
and the environment in which the Company will operate in the
future, including the price of copper, gold and silver; projected
gold, copper and silver grades; anticipated capital and operating
costs; anticipated future production and cash flows; the
anticipated location of certain infrastructure in Hugo North Lift 1
and sequence of mining within and across panel boundaries; the
availability and timing of required governmental and other
approvals for the construction of the SOPP; the ability of the
Government of Mongolia to finance
and procure the SOPP within the timeframes anticipated in the PSFA,
as amended, subject to ongoing discussions relating to a standstill
period; the willingness of third parties to extend existing power
arrangements; the status and nature of the Company's relationship
and interactions and discussions with the Government of
Mongolia on the continued
operation and development of Oyu Tolgoi (including with respect to
the causes of the increase in costs and schedule extension of the
underground development) and Oyu Tolgoi LLC internal governance
(including the outcome of any such interactions or discussions);
the willingness and ability of the parties to the IA or the UDP to
amend or replace either such agreement; the nature and quantum of
the current and projected economic benefits to Mongolia resulting from the continued
operation of Oyu Tolgoi; the implementation and successful
execution of the funding plan that is the subject of the HoA and
the amount of any additional future funding gap to complete the Oyu
Tolgoi project as well as the amount and potential sources of
additional funding required therefor, all as contemplated by the
HoA.
Certain important factors that could cause actual results,
performance or achievements to differ materially from those in the
forward-looking statements and information include, among others:
copper, gold and silver price volatility; discrepancies between
actual and estimated production; mineral reserves and resources and
metallurgical recoveries; development plans for processing
resources; public health crises such as COVID-19; matters
relating to proposed exploration or expansion; mining operational
and development risks, including geotechnical risks and ground
conditions; litigation risks, including the outcome of the class
action complaints filed against the Company; the outcome of the
international arbitration proceedings; regulatory restrictions
(including environmental regulatory restrictions and liability);
Oyu Tolgoi LLC or the Government of Mongolia's ability to deliver a domestic power
source for the Oyu Tolgoi project within the required contractual
time frame; communications with local stakeholders and community
relations; activities, actions or assessments, including tax
assessments, by governmental authorities; events or circumstances
(including public health crises strikes, blockades or similar
events outside of the Company's control) that may affect the
Company's ability to deliver its products in a timely manner;
currency fluctuations; the speculative nature of mineral
exploration; the global economic climate; global climate change;
dilution; share price volatility; competition; loss of key
employees; cyber security incidents; additional funding
requirements, including in respect of the development or
construction of a long-term domestic power supply for the Oyu
Tolgoi project; capital and operating costs, including with respect
to the development of additional deposits and processing
facilities; defective title to mineral claims or property; and
human rights requirements. Although the Company has attempted to
identify important factors that could cause actual actions, events
or results to differ materially from those described in
forward-looking statements and information, there may be other
factors that cause actions, events or results not to be as
anticipated, estimated or intended. All such forward-looking
statements and information are based on certain assumptions and
analyses made by the Company's management in light of their
experience and perception of historical trends, current conditions
and expected future developments, as well as other factors
management believes are reasonable and appropriate in the
circumstances. These statements, however, are subject to a variety
of risks and uncertainties and other factors that could cause
actual events or results to differ materially from those projected
in the forward-looking statements or information.
With respect to specific forward-looking information concerning
the continued operation and development of Oyu Tolgoi, the Company
has based its assumptions and analyses on certain factors which are
inherently uncertain. Uncertainties and assumptions include, among
others: the timing and cost of the construction and expansion of
mining and processing facilities; the timing and availability of a
long-term domestic power source (or the availability of financing
for the Company or the Government of Mongolia to construct such a source) for Oyu
Tolgoi; the implementation and successful execution of the funding
plan that is the subject of the HoA and the amount of any
additional future funding gap to complete the Oyu Tolgoi project as
well as the amount and potential sources of additional funding
required therefor, all as contemplated by the HoA; the status and
nature of the Company's relationship, interactions and discussions
with the Government of Mongolia on
the continued operation and development of Oyu Tolgoi (including
with respect to the causes of the increase in costs and schedule
extension of the underground development) and Oyu Tolgoi LLC
internal governance (including the outcome of any such interactions
or discussions); the willingness and ability of the parties to the
IA and the UDP to amend or replace either such agreement; the
nature and quantum of the current and projected economic benefits
to Mongolia resulting from the
continued operation of Oyu Tolgoi; the potential impact of
COVID-19, including any restrictions imposed by health and
governmental authorities relating thereto, as well as the
development cost impacts of delays caused by the COVID-19 pandemic;
the impact of changes in, changes in interpretation to or changes
in enforcement of, laws, regulations and government practices in
Mongolia; the availability and
cost of skilled labour and transportation; the obtaining of (and
the terms and timing of obtaining) necessary environmental and
other government approvals, consents and permits; delays and the
costs which would result from delays, including delays caused by
COVID-19 restrictions and impacts and related factors, in the
development of the underground mine (which could significantly
exceed the costs projected in OTTR20); projected copper, gold and
silver prices and their market demand; and production estimates and
the anticipated yearly production of copper, gold and silver at Oyu
Tolgoi.
The cost, timing and complexities of mine construction and
development are increased by the remote location of a property such
as Oyu Tolgoi. It is common in mining operations and in the
development or expansion of existing facilities to experience
unexpected problems and delays during development, construction and
mine start-up. Additionally, although Oyu Tolgoi has achieved
commercial production, there is no assurance that future
development activities will result in profitable mining
operations.
Readers are cautioned not to place undue reliance on
forward-looking information or statements. By their nature,
forward-looking statements involve numerous assumptions, inherent
risks and uncertainties, both general and specific, which
contribute to the possibility that the predicted outcomes will not
occur. Events or circumstances could cause the Company's actual
results to differ materially from those estimated or projected and
expressed in, or implied by, these forward-looking statements.
Important factors that could cause actual results to differ from
these forward-looking statements are included in the "Risk Factors"
section in the Company's annual information form for the year ended
December 31, 2020 ("AIF"), as
supplemented by the "Risks and Uncertainties" section of the
Company's management's discussion and analysis for the second
quarter ended June 30, 2021
("MD&A").
Readers are further cautioned that the list of factors
enumerated in the "Risk Factors" section of the AIF and in the
"Risks and Uncertainties" section of the MD&A that may affect
future results is not exhaustive. When relying on the Company's
forward-looking statements and information to make decisions with
respect to the Company, investors and others should carefully
consider the foregoing factors and other uncertainties and
potential events. Furthermore, the forward-looking statements and
information contained herein are made as of the date of this
document and the Company does not undertake any obligation to
update or to revise any of the included forward-looking statements
or information, whether as a result of new information, future
events or otherwise, except as required by applicable law. The
forward-looking statements and information contained herein are
expressly qualified by this cautionary statement.
View original content to download
multimedia:https://www.prnewswire.com/news-releases/turquoise-hill-announces-third-quarter-2021-production-and-provides-oyu-tolgoi-mine-update-301400863.html
SOURCE TURQUOISE HILL RESOURCES LTD